455 N.E.2d 517 | Ohio Ct. App. | 1982
This is an appeal from a judgment of the Court of Common Pleas of Franklin County.
Plaintiff filed a complaint along with a motion for a temporary restraining order, which the trial court later dismissed. Defendant filed an answer. Subsequently, plaintiff filed a motion to amend its complaint. The court sustained the motion and added that defendant's answer would be considered an answer to the amended complaint.
Thereafter, plaintiff filed the amended complaint against defendant, alleging plaintiff was a contractor which submitted a bid in writing for city construction work called the Westerville Reservoir Outlet Works Improvement, Contract 81-W-1. Plaintiff alleged that its bid of $63,700 was the lowest and the best with the next bid being $64,800. Plaintiff alleged that defendant's failure to accept its bid was "grossly arbitrary, capricious, unreasonable, unconscionable and unlawful." Plaintiff contended that, because of defendant's failure to award the contract, it suffered $4,000 loss due to costs incurred in the competitive bidding process, $10,000 loss of profits and $5,000 loss due to litigation costs in this action.
Defendant moved for summary judgment and included the following affidavit:
"I, John R. Stewart, being first duly sworn, depose and say:
"1. I am an elected member of the Westerville City Council. Currently, I am serving as the elected Chairman of Council.
"2. I served as the Chairman of the Westerville City Council at the Council meeting held on July 7, 1981.
"3. At such Council meeting, the members of the Westerville City Council voted 6 to 0 to award the City of Westerville Water Works Improvement and Westerville Reservoir Outlet Works Improvement Contract to Legg Davis.
"4. The members of Council jointly found that the bid of Bale Contracting, Inc., was not the best bid. A material provision was lacking in that Bale Contracting, Inc., failed to bid on the time in which it would complete the water works improvement.
"5. My judgment, and to the best of my knowledge, the judgment of the other members of City Council, was honestly exercised in good faith with the intent of awarding the bid to the lowest and best bidder.
"FURTHER AFFIANT SAYETH NAUGHT."
In response, plaintiff submitted an affidavit:
"Patricia L. McKee, being first duly sworn, says that she is the secretary of Plaintiff Bale Contracting, Inc. and that:
"1. The allegations set forth in Plaintiff's Amended Complaint herein are true. *272
"2. The outlet channel work was the only work of substance in the subject project since the gate house portion involved (principally) the furnishing of material.
"3. That is, in submitting the subject bid (Defendant's Exhibit A), Plaintiff accepted the 120 calendar days indentified [sic] with the outlet channel work as the outside time limit for finishing the entire project since the only substantial area of work was the outlet channel; the gate house item was of no consideration in determining a project competion [sic] date.
"4. In completing Defendant's bid form, Plaintiff omitted filling in the blank, for several good reasons:
"(a) as set forth in paragraph 3 above, the 120 days dictated for the outlet channel was accepted by Plaintiff as the entire project time limit.
"(b) Defendant's bid form was, according to construction industry standards, unclear with respect to what project completion time limit the Defendant desired and, therefore, Plaintiff was reluctant to insert a time limit contrary to the wishes of Defendant since the item could normally be settled at a later date.
"5. Contrary to usual construction industry custom, Defendant arbitrarily and unreasonably refused to allow Plaintiff to amend its bid by adding the project completion date according to Defendant's desires with regard to that date.
"6. In the context of usual construction industry practice, Defendant has failed to act in a reasonable manner with regard to allowing Plaintiff to clarify its bid concerning the non-material matter of a project time limit (considering that 120 days was given as an outside limit with regard to substantially all of the work).
"7. Defendant's action in rejecting Plaintiff's bid was clearly contrary to accepted construction industry standards as they relate to Ohio municipal corporations to the point of being arbitary [sic,] capricious, unreasonable and unconscionable."
The trial court sustained defendant's motion for summary judgment.
Plaintiff now appeals and asserts the following assignment of error:
"The trial court erred in sustaining appellee's motion for summary judgment in that there existed genuine issues of material fact."
It is definite and uncontroverted that plaintiff's bid was incomplete. Plaintiff failed to specify the time involved to complete the project. The materiality of this time provision is supported by Section 15.1 of the General Conditions. In fact, that entire page is devoted solely to time of performance. The Agreement, Notice to Proceed and Change Order documents all required that the time bid for completion be inserted in the contractual documents.
Furthermore, R.C.
"All contracts under sections
The affidavit of Patricia L. McKee is insufficient to create a genuine issue of material fact concerning the materiality of the time provision. The reason plaintiff did not specify a time is not relevant. The point is that this was not done and such requirement was a material part to the contract.
Moreover, it was not error in refusing to allow plaintiff to clarify the provision. When a bid is modified in any particular way, after the time for bidding has passed, such bid cannot be considered as legal. If bidders were permitted to make better offers after their sealed proposals had been made and opened, there would *273 not be a valid rationale for the formality of submitting sealed proposals.
Consequently, reasonable minds construing the evidence for plaintiff, could not differ that the material term of the contract was omitted or left unresolved. (Civ. R. 56[C].) Further, reasonable minds could not differ that defendant did not abuse its discretion in refusing to award plaintiff the contract.State, ex rel. Shafer, v. Ohio Turnpike Commission (1953),
Reasonable minds could definitely not find a bid with the material term of time unspecified to be the "best bid," when compared with another comparably priced bid that included such term.
For the foregoing reasons, plaintiff's assignment of error is overruled, and the judgment is affirmed.
Judgment affirmed.
STRAUSBAUGH and COOK, JJ., concur.
COOK, J., of the Eleventh Appellate District, sitting by assignment in the Tenth Appellate District.