77 A.D. 528 | N.Y. App. Div. | 1902
' The contract, for the breach of which tin’s clnlm Ja-Brnd-e-Accfllust, the State, provides,Jn substance, that, if the execution—of. the contract shall be^uspended'by the State at any time for anv cause, im claim for m’ospectivg~TTronts on work not done shall be made and allowed, but the contractors shall complete the work when the State shall order it to be resumed, and the date of such completion shall be fixed by the Superintendent of Public Works. It is claimed on the part of the State that the breach complained of is but a “ suspension ” under the above provision. If such claim is correct, it is plain that not only could no prospective profits be now claimed as
But I am of the opinion that the Action of the State upon and after the 14th of May, 1898, was an abandonment of the work referred to in_the contract instead of a mere “ suspension ” thereof. The contract was then terminated by the State, and the contractors were notified to that effect. No suggestion was made that the work provided for in the contract was to be thereafter completed, or that any time would be thereafter fixed for its completion.
They were simply notified that the work was to cease, and operation under the contract was then brought to an end. Chapter 544 of the Laws of 1899 seems to be a declaration on the part of the State that it so considered the situation, and that if the contractors were willing to adopt that view and take what was due them upon their contracts and release all further claims, they would be paid upon that basis, including all moneys held by the State as security for the performance of the contract on their part. . A clear abandonment of the scheme to improve the canal to the depth of nine feet is here shown; and it is very apparent that the breach of which the appellants complain is not theniere suspension above referred to.
We have then this situation: The contractors institute against the State these proceedings for a breach of its contract, and- they claim not only the amounts due for work actually done by them thereunder, but also such damages as have naturally accrued to them on account of such breach. The amount still unpaid for work actually done is conceded to be $8,881.23; and the amount of money deposited with the State as security for the work is conceded to be $5,100. It is also conceded that, so far as they were permitted, the contractors have well and faithfully performed the work. The State having abandoned the work and prevented further performance on the the part of the contractors, it is clear that both the sum of $5,100 and the $8,881.23 are due and payable by it to the contractors; and under this view of the case, it is difficult to see why they should not recover them untrammeled by a provision in the judgment that they release all further claim for damages against the State.
On the face of the contract, and on the proof disclosed by the record before us, the total work which the contractors undertook to perform was, it seems to me, to “ construct and to finish” the improvement of a certain specified five and eighty-seven one-hundredths miles of the Erie canal according to plans and specifications submitted ! with and made a part of the contract. Such is their undertaking ,in the first provision of the contract. No change in such plans and (specifications has ever been made by the State, and it is conceded ¡that when abandoned such work had not been completed.
Such being the obligation on the part of the contractors, it would seem, from the proof disclosed by the record, that the reciprocal obligation on the part of the State to permit them to prosecute the work to completion, and to pay them for the same, exists, unless the State has reserved to itself the right to end the work at any period of its progress. If such right is reserved, undoubtedly, no loss of profits could be claimed as damages for a breach of the contract, because in that case there would be no breach. The court below has substantially held that such is the situation here, and has, therefore, rejected the contractors’ claim for such damages. If the solution of the question depends upon the construction of the terms of the contract alone, a careful study of that instrument will force the conclusion that no such reservation can be found within it.
Notice that bids for the performance of the work upon the five and eighty-seven one-hundredths miles covered by this contract would be received was published. Accompanying .that notice, the plans, specifications and statement of the engineer’s estimate for the work to be done thereon were submitted and filed as required by chapter 794 of the Laws of 1896 (amdg. Laws of 1895, chap. 79, §§ 4, 5). Under such notice and statement these claimants made a bid and affixed theiihpoicesjDer yard and per foot to the several estimated amounts of excavationTconstrucrion or material' contained» in such statement. They were awarded the work, and thereupon entered ..a into the contract which is set forth at length in the appeal book. U By such contract, such plans, specifications and statement are made
t There are several provisions in the contract, specifications and I statement which it is claimed amount to a reservation by the State of the right to terminate at any time it desired the work under this contract. First. In the bid which is written and signed by the contractors, at the foot of the “ statement ” of estimated amounts,, etc., they offer “ to construct and to finish, so far as the superintendent of public works shall direct, all of the work to which prices are affixed in the above schedule in all respects according to the contract and specifications, etc., * * * this day exhibited. * * * ” But this offer is no part of the contract and it is to be noticed that in the contract their undertaking is to do all the labor, etc., necessary to “ construct and to Jmish in every respect ” the five and. eighty-seven one-hundredths miles in question, and such work is to be done according to the plans and specifications furnished, etc. Here is a distinct undertaking on the part of the contractors to finish the contract according to the plans, and there is no provision or suggestion here that they are to do that work or so much thereof as the Superintendent of Public Works shall require. Under the contract they are required to do it all. And the mutual obligation on the part of the State to permit them to do it all and to pay them accordingly is not in any way limited by any provision here made. The limitation suggested in the offer is not incorporated into the contract.
Moreover, if such offer is to be deemed a controlling part of the contract, then the contractors’ obligation to do work would extend
It will hardly be claimed that either party expected that no more work should be done than was specified in that estimate, inasmuch as the contractor is distinctly notified that the quantifies there named are “ approximate only,” and the provision of the contract headed
Alterations and Directions,” etc., and the 28th specification, hereinafter referred to, are utterly inconsistent with that theory. So, ■also, the contractors in several instances did more work than was specified in the estimate, thus indicating that the parties understood ¡that the amount of work to be done was not limited by that estimate.
In all these respects the offer differs materially from the contract and cannot be deemed to modify or control it.
There are certain other provisions in the contract in which it is required that the work shall be “ prosecuted at the times and in the manner directed by the resident engineer,” etc. These have reference to the method of carrying on the work, and clearly were not .intended to provide that the resident engineer might at any time order an abandonment of the work.
It was further provided in section 28 of the specifications that "“'TlTYS'tate reserves the right, to increase or diminish the amount or amounts of any class of work from the_ amount shown 'on' the bidding sheet,” and in that ■■event-the-amount-of...work required will be done at the rates named in the contract, and no claim for damages or prospective profits shall be made on .account of such change. It is insisted that this amounts to a reservation by the State of the right to cease the work at any time, without incurring any liability for damages. Theji.rgn ment seems .tQ-ba-thaL-u-nd-eE-this-provision. the State mighFdiminish the amount of each class of work specified in TEe""estffnateWr'^^"iffdmg^eet7T~EYlMleT)rnothingj- and • in that -manner abandon the work long before its completion!....... • .......
'The'whole sclleme ofIi£iIcontemt--repelPtbb-idear--that--such -was tffie'pvirpose, or understood meaning, of this provision., The “ bidding" sheet,” to which it refers, was the estimate of quantities, etc., required by the statute above cited to be made by the engineers
- Had the real agreement between the parties been to the effect that the contractors should do all the work necessary to complete the improvement of this section of the canal, or so much thereof only as the State should require, it is fair to assume that such a provision would in plain and distinct terms have been inserted in the contract itself. In view of its absence and of its great importance, had such been the agreement, I am of the opinion that the several disconnected, indefinite and inconsistent provisions which the State now relies upon should not be construed into such a reservation. If the State is correct in its claim as to the construction of the contract, these contractors were obligated to perform work and furnish materials that, at agreed prices, would amount to at least over $98,000, and possibly much more; while the State might have ended their operations before they had earned enough to pay the expenses incurred in preparing for the work. Such an agreement is not usual and should not be inferred from language no more explicit than is to be found in this contract.
I have given so far only what seems to me a fair construction of the terms of the contract as it reads, and if it can be shown that such a contract was authorized I see no way by which the State can avoid payment of damages for its breach. But there are other considerations which are barely suggested by the record and by the
It must be admitted, I think, that the Superintendent of Public-Works had no power to create a contract debt on the part of the-State beyond the $9,000,000 voted by the People under section 4,. article 7 of the Constitution. Nor had the State the power to-authorize the creation of a debt beyond that sum. Hence it would seem that if the aggregate of the contracts let contemplated the-expenditure of a greater sum, then as to such excess they are notenforcible against the State. It would, perhaps, seem plainer if the entire improvement was under a single contract. No one, I apprehend, would then say that a contract involving an indebtedness of $20,000,000, where a debt of only $9,000,000 was authorized, could be enforced beyond the $9,000,000 appropriated. This seems to-have been clear to the Legislature in conferring upon the Superintendent of Public Works the power to contract. The Legislature-intended to keep within its constitutional powers, and did not intend that the aggregated contracts should involve the making of improvements beyond the sum voted by the People. This is plain from the reading of the act of 1895 (Chap. 79) and the act as amended in 1896 (Chap. 794). By the amendment of 1896 it was provided that “ None of the work called for by this act shall be contracted for until the State Engineer shall have ascertained with all practicable-accuracy the quantity of embankment, excavation, masonry, the-quantity and quality of all materials to be used and all other items• of work to be placed under contract, and a statement thereof, with, the maps, plans and specifications, corresponding to those adopted by the Canal Board and on file in the office of the State Engineer, is-publicly exhibited to every person proposing or desiring to make a. proposal for such work. The quantities contained in such statement shall he used in determining the cost of the work” The act. -then provides for filing the proper maps, etc., with the State Engi. neer, and that no alteration shall be made in the specification or the plan of any work under contract during its progress, except an:
It is here contemplated that the bids should be for specific work, and the price bid should determine the cost of the improvement contracted to be done. Safeguards are provided against any increase over the sum bid, and, if these directions were adhered to, it was reasonable to suppose that the aggregate of the sums bid would fairly determine the whole cost of the entire improvements contracted for. If the aggregate of these bids was within the $9,000,000, it would seem that the contracts up to the bids made on each would have been authorized. I assume that such was the fact, to wit, that the aggregate of these bids was within that sum, though this record shows nothing on the subject. If the sum of these bids practically exhausted the $9,000,000, I do not see how there remained any room for expansion in any contract, and the elastic quality in the direction of increase over the sum bid in any contract would seem under this theory to have been prohibited. I deduce from this that the $9,000,000 was, at the time the bids were accepted and contracts entered into, divided up and to each contract was apportioned the sum stated in the bid, which the law said should determine “ the cost of the work ; ” and if the contract in terms contemplated the expenditure of any sum beyond the sum so apportioned, it was to that extent unauthorized. For the same reason it would seem also that if any sum has been paid to any contractor beyond the sum bid, such payment was unauthorized, because there was no fund from which it could be lawfully paid; and it could not be properly taken from the sum apportioned to any other contractor. If we are right in this theory of an apportionment of the $9,000,000 to the several contractors up to the amount of their bids, we are lead to the conclusion that each contract was binding upon the State up to the amount of the bid and not beyond — provided, of course, that the aggregate of the bids did not exceed $9,000,000 — and that any abandonment by the State of any contract before the amount of the bid had been exhausted was a breach and entitled the contractor to prospective profits for work undone up to the amount
Our conclusion that the contract has been abandoned on the part of the State entitles the claimants to a judgment for money conceded to be due for the work actually done, and for the sum deposited as security for performance of the contract. And if the facts shall prove to be, what it has been suggested that they really are, viz., that the aggregate of the contracts upon their face, as shown by the estimates and bids, was not in-excess of the $9,000,000 voted, the plaintiffs may be entitled to such damages as they can show that they have suffered by reason of the abandonment on the part of the State before the sum of $98,760, the amount of plaintiffs’ bid on the estimate presented, was exhausted.
The judgment of the Court of Claims is reversed, with costs, and a new trial before the Court of Claims is directed.
All concurred.
Judgment of the Court of Claims reversed, with costs, and a •new trial before the Court of Claims granted.