94 P. 773 | Cal. Ct. App. | 1908
The case represents the consolidation of two actions brought to foreclose liens for labor bestowed upon a certain canal and right of way belonging to defendants.
The appeal is from the judgment in favor of plaintiffs and an order denying a motion for a new trial.
About June 25, 1904, appellants entered into a contract with defendants W. B. Livermore and J. W. Livermore, who were doing business as partners under the firm name of Livermore Brothers, under which the latter agreed to construct a certain ditch or canal leading from Kings river in Kings county.
The amount agreed to be paid thereunder was in excess of one thousand dollars, but the contract was not recorded until some time after the work of construction was begun. It is conceded, therefore, that the work done by plaintiffs must be deemed to have been bestowed upon the canal at the personal instance of the owners. (Code Civ. Proc., sec. 1183; Kellogg v. Howes,
Appellants, however, assail the judgment upon various grounds, among which is, that the claims of lien were prematurely filed by plaintiffs.
The work was not completed by Livermore Brothers. In fact, a very small part of it was done by them. On the 24th of September they were notified by the owners that the contract under which the work was being done was canceled and the said Livermore Brothers were forbidden to do any further work on the canal. Consequently, on September 26th, they ceased their work and the owners took possession. On October 26th, the owners filed in the office of the county recorder *484 the statutory notice that said contractors on the twenty-sixth day of September ceased to perform any labor in the construction of said canal and that said cessation from such labor had continued for more than thirty days. Each plaintiff in the complaint alleges: "That within thirty days after the cessation of labor upon said canal the plaintiff filed for record in the office of the county recorder . . . a written notice of his claim of lien," etc. The contention of appellants is that the contract is not deemed completed until there has been a cessation of labor for thirty days in addition to the occupation by the owners. The language of section 1187, Code of Civil Procedure, is: "And in all cases the occupation or use of a building, improvement or structure by the owner, or his representative, or the occupation by said owner or his agent of said building, improvement and structure, and cessation from labor for thirty days upon any contract or upon any building, improvement or structure, or the alteration, addition to or repair thereof, shall be deemed equivalent to a completion thereof for all the purposes of this chapter." If the legislature did not intend to provide that both conditions should exist, to wit, occupation and cessation from labor for thirty days before the structure or contract should be deemed complete for the purposes of a lien, it is difficult to conceive what language could be chosen to express such intention.
It will not be controverted that if it appears from the complaint that the claims of lien were filed prematurely the general demurrer of appellants should have been sustained, as the only cause of action against them is based upon the theory of the compliance by respondents with the provisions of the statute in reference to liens.
A claim of lien filed prematurely cannot, of course, be enforced. (Roylance v. San Luis Hotel Co.,
But these decisions and others cited by respondents were rendered under the provisions of section 1187, Code of Civil Procedure, as it existed prior to the amendment of 1897, until which time it read: "And in case of contracts, the occupation or use of the building, improvement or structure by the owner or his representative, or the acceptance by said owner or his agent of said building, improvement or structure shall be deemed conclusive evidence of completion."
In other words, occupation or acceptance alone was deemed conclusive evidence of completion, but now, as we have seen, occupation and cessation of labor for thirty days must concur before the work is deemed complete. The law was changed probably because of the difficulty, sometimes encountered, suggested in the Orlandi case, supra, of determining when the structure was really occupied to the exclusion of the contractor.
In the case of Santa Monica L. M. Co. v. Hege,
In the same case, though, it is held that "the plaintiff was required to file its notice of lien within thirty days after the completion of the building," and furthermore, "unless the building was completed before the notice of lien was filed, the filing was premature and conferred no right to enforce the lien."
We think it clear, therefore, from the provisions of the law, that either the contract must be actually completed or deemed completed before the right to file a claim of lien accrues. But in the case at bar it is not claimed that the contract was completed. Reliance is had upon what the statute provides shall be deemed equivalent to a completion. This is, as we have seen, occupation and cessation from labor for thirty days. The claims of lien were filed before the expiration of the thirty days, and hence the action was premature.
While the law of liens is a remedial measure and should be liberally construed with a view of accomplishing its beneficent purpose, yet it is for the legislature to determine the method by which a lien can be enforced and the courts are not at liberty to disregard any statutory requirement.
We cannot see how the judgment can be upheld without ignoring the plain provisions of the law to which attention has been directed.
As to the order denying the motion for a new trial, we deem it sufficient to say that the aggregate amount for which liens were declared is somewhat in excess of the sum shown by the evidence; but it is not necessary to review the matter in detail, as under the view we have taken of the subject the liens cannot be maintained for any amount or at all.
The judgment and order as to appellants are reversed.
Hart, J., and Chipman, P. J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on March 26, 1908. *487