129 N.W. 464 | N.D. | 1910
Lead Opinion
The complaint alleges the following facts: That: on the 28th day of July, 1908, the city of LaMoure, through its council, entered into a contract in writing with the defendant Haggart, for the construction of a system of sewers in that city; that one O. M.. Baker was, by said city council, appointed supervising engineer, and was to superintend the construction of said sewers under said contract;. that he was appointed as such supervising engineer by reason of the-fact that no city engineer had been previously appointed by the mayor as provided by statute; that he duly accepted such appointment, and as such supervising engineer performed all of the duties required of him under said contract and under the statute; that he filed, with the-auditor of the city, a final estimate and report on said sewer system, and said final report was by the said city council referred to a committee for action thereon; that said committee reported to the council, and its report was adopted by said council on April 25, 1909; in this report: the committee recommended that portions of the sewers as constructed, by defendant be reconstructed, inasmuch as they were defectively constructed; that on the 21st day of May,'1909, said committee made' another report to the city council, in which it recommended the acceptance of the sewers as constructed by the defendant Haggart, under the contract, and that he be paid the balance due him in full, less the sum of $150, to be reserved by the city for the purpose of placing the streets-in proper condition; that the city council, by resolution, adopted said report, and ordered that warrants be issued in accordance therewith,, and that the auditor did issue warrants in favor of said Haggart, pursuant to said resolution, for the sum of $3,789.80.
The complaint further alleges that said supervising engineer has? never approved the construction of the sewers, but, on the contrary, has specifically disapproved portions of the work done by him under-the contract, and, in consequence of these facts, the contract has never been fully performed or completed, and that warrants were issued for such work in a sum largely in excess of the work actually done by said?, defendant Haggart.
The prayer of the complaint is that the city council be restrained' and perpetually enjoined from certifying to the special assessment: commission the cost of said sewer system, for the purpose of levying: the special assessment for the cost of said sewers.
The defendants demurred to the complaint, on the ground that it. does not state facts sufficient to constitute a cause of action. The demurrer was overruled, and the defendants have appealed from the-order overruling the same.
It is first claimed that the plaintiff has shown no such interest in the result of the levying of assessments to pay for the sewer improvements as entitled him to relief in a court of equity. In this regard the complaint alleges that the plaintiff is a “resident property owner and taxpayer of the city of LaMoure, . . . and that he owns property and lots abutting on certain streets in the city of LaMoure . . along which streets has been constructed the sewer hereinafter described, and that said property and lots are subject to assessments by
This allegation, in connection with the statements from the com-plaint quoted above, to- the effect that the proposed assessment against the plaintiff’s property would be illegal, is sufficient to show that the plaintiff has such interest in the contract as entitles him to the interposition of a court of equity. If not restrained, plaintiff’s property would be encumbered by a lien in excess of what it would be if the council had not exceeded its authority. Roberts v. Fargo, 10 N. D. 230, 86 N. W. 726; McCain v. DeMoines, 128 Iowa, 331, 103 N. W. 979.
It is claimed that the complaint does not show that any assessment will be made against plaintiff’s property to secure the payment of the .said sum of $3,017.30. The complaint shows that warrants have been issued for that 'amount, and there is no provision for the payment of .such warrants except through assessments against the lots abutting on .streets where the sewers are constructed. The plaintiff alleges that he owns such lots. No conclusion can be drawn from these allegations, except that these lots will be burdened with a lien for such excess. The fact that plaintiff’s lots are not specifically described in the complaint is not material.
It is also claimed that the complaint fails to show that the work was not done in the good and workmanlike manner called for by the contract. The allegation of the complaint above set forth 'shows that the .sewer has not yet been constructed in accordance with the contract. These defects are specifically pointed out in the report of the engineer. Furthermore the contract-provides that the sewer was to be built “to the satisfaction of the engineer selected.” Under the terms of the contract, and under §§ 2784 and 2800, Rev. Codes 1905, the approval of the engineer is necessary before the final action by the-city council. contract provides that the work shall be done “in good, workmanlike, and substantial manner, to the satisfaction and direction of the engineer to be selected by the said party of the second part, who shall have general supervision of all and each part of the said work to be testified by a certificate under the hand of the said engineer.”
Section 2784, supra, provides that “such contract'shall require the work to be done thereunder to be done pursuant to the plans and speci
Section 2800, supra, provides: “Whenever the work for which a special assessment shall be required to be made by such commission shall have been completed, and approved by the city engineer, and the total cost of such work shall have been ascertained as near as practicable, the city auditor shall notify the chairman of such commission of the completion of such work,” etc.
From the contract and these statutes, it is plain that approval by the engineer is intended as a prerequisite to final action by the council. The statutes were enacted to protect property holders from having to pay for poor work or materials, and from other abuses in public work liable to escape detection by those not specially informed on such matters. Engineers are supposed to have special training in such matters, hence the importance attached to their approval both' in the statuta and in the contract under consideration.
There is no question raised in this case as to the good faith of the engineer. The authorities make an exception as to a certificate by the engineer being necessary, if it is shown that the action of the engineer is arbitrary, fraudulent, or unreasonable. 28 Cyc. Law & Proc. 1049, and cases cited. Reid v. Clay, 134 Cal. 207, 66 Pac. 262; O’Dea v. Mitchell, 144 Cal. 374, 77 Pac. 1020.
The complaint and exhibits attached thereto and made a part thereof show wherein the sewers were not constructed in accordance with the contract, which provided that they were to be constructed in a good and workmanlike manner. In his report, the city engineer specifically •disapproves of the work of the contractor, and states that the contract price should be reduced as to 10-inch pipes in the sum of $3,017.30. The complaint also shows other defects, and that the city engineer specifically disapproved the work and recommended a deduction from the contract price in a sum in all amounting to $4,389.80. These allegations refute, so far as the demurrer to the complaint is concerned, any contention that the refusal of the engineer to approve the work was arbitrary and unreasonable. We are now only determining whether the complaint states a cause of action as against demurrer. We are not determining that to refuse to approve of the work under the contract, for
The fact that the supervising engineer in this case was appointed by the council especially for the work, for the reason that there was no-regular city engineer, has no force to change the binding effect of the* contract that the engineer’s approval was necessary, or as to the application of §§ 2787 and 2800, supra, to such contracts. The statute-provides that when there is no city engineer the council shall employ one.
In McGuire v. Rapid City, 6 Dak. 316, 5 L.R.A. 752, 43 N. W. 706, the effect to be given to a certificate of approval of a city engineer under a contract very much the same as the one in question was considered, and the court said: “By its terms, the plaintiff was to perform the work under direction of the city engineer, and to his satisfaction. The city made the engineer its agent to approve and accept the-work. His judgment was the judgment of the city, and the plaintiff' was only required to perform the work in such a manner as to meet with his approval. It is true that the contract does provide that the* work was to be done in a ‘good, workmanlike, and substantial manner,’ but whether it was so done or not was to be determined by the-engineer himself. The plaintiff and defendant contracted that the.- ' work must pass the inspection of the defendant’s engineer; and though a court and jury, or other competent tribunal, might be satisfied that-the work was done in a good, workmanlike, and substantial manner, yet it would not avail the plaintiff under this contract, unless, perhaps, the-engineer should fraudulently or wrongfully withhold his approval.”
The complaint states a cause of action, and the demurrer was properly overruled.
Dissenting Opinion
(dissenting). I have no dissent to enter as to most of the principles of law announced in the majority opinion. The due protection of property rights of citizens of cities from the ill-considered, careless, or corrupt action of city councils requires that statutes granting them powers in matters relating to municipal, improvements for which property may be assessed shall be construed with at least reasonable strictness. However, it is well settled that courts will not hold to as strict a construction in actions commenced after the work has been done, as in those by which it is sought to enjoin the officials or others before work has been performed in the execution of the con
It appears, from the complaint, that a contract was entered into for the construction of a system of sewers for the city of LalVIoure, and that the city was districted for that purpose. The contractor proceeded with the work, and, in accordance with the terms of the contract, was from time to time paid by warrant an amount equaling 80 or 90 per cent of the contract price, and the warrants against which this proceeding is directed are for the balance claimed to be due him on the whole system. The complaint utterly fails to show that the property of the plaintiff which is claimed to be affected or liable to a special assessment is located within any district in which the sewer, as constructed, failed to meet the approval of the city engii-eer, also fails to show that the warrants in question were drawn for the work which he condemned. Nor all that appears in the complaint, they may have been drawn for that part of the sewer system which was approved. If drawn in payment of the disapproved part of the sewer system, and that portion was in another district than that in which the property of the plaintiff is situated, he has no cause of action. It would not effect his property, hence I conclude that the complaint fails to state a cause of action in behalf of the plaintiff. Of course if the complaint showed the whole city to have been included in one distinct, a different question would arise, but it is clear that the complaint shows neither that his property is to be assessed to pay for that part of the sewer disapproved, nor that the warrants against which the complaint is directed were drawn for the condemned portion of the sewer system. The allegation that his property will be affected is a mere conclusion of law, unsupported by facts pleaded.
However, if in this respect the complaint is sufficient, it is insufficient and fails to state a cause of action as to the main part of the
•For these reasons I dissent.
Concurrence Opinion
(concurring specially). I concur in the result reached in the majority opinion, but deem it proper to express'my views upon the reasons given by the supervising engineer for refusing to approve of a portion of the sewer. He disapproves of about 2,743 feet of the 10-inch pipe sewer, because it does not stand the light test, in other words, because a light cannot be seen from manhole to manhole. The plans and specifications nowhere call for the light test, and the supervising engineer does not claim that they do, but bases his refusal to approve of that part of the work that will not stand the light test, on the authority of a text-book on Sewers, by Professor Ogden, of Cornell University. The supervising engineer admits that water flows freely through that portion of the sewer disapproved of, and does not claim that the work is not in accordance with the plans and specifications, but bases his refusal to approve wholly on the light test. The supervising engineer cannot arbitrarily or unreasonably withhold his approval of the work. There is no pretense but that the work was done in accordance with the plans and specifications, except that a 24-foot back pressure gate valve to be placed at the river has not been furnished, also that the surface of the streets was not left in as good condition as it was before the commencement of the work. I think the supervising engineer in withholding his approval of the 2,743 feet of sewer on account of its failure to stand the light test is arbitrary and unreasonable, but as the contractor did not furnish the 24-foot back pressure gate valve, and left the surface of the streets in a rough condition, the plaintiff is entitled to relief against paying for that portion of the work. Hence the demurrer was properly overruled.