200 Pa. 406 | Pa. | 1901
Opinion by
Plaintiffs sued for a balance on a building contract, and tbe defense was a defalcation of damages for delay. The contract provided that plaintiffs should enter upon the work at once when directed by the architect, and “ finish and complete the same and every part and detail thereof in a durable and substantial manner, within ninety days from the date of starting the erection which is to be started within ninety days from the date of this contract and approved detail plans.”
It is practically undisputed that the work was not done within the contract time, and the real question between the parties was who was responsible for the delay. There was evidence, including, inter alia, their own letters to the architect, that plaintiffs were partly in fault, but on the other hand there were several admitted changes of detailed plans, one as late as October 29, 1896, causing delay clearly chargeable to defendants. The question was therefore necessarily for the jury. It would have been more satisfactory in the result probably, had the jury’s attention been directed specifically to the exact ascertainment of how much additional 'time plaintiffs were entitled to by reason of defendant’s changes of plans, for that was the pinch of the case. But the evidence had been elaborately discussed by counsel on both sides, and the points presented covered the law so fully that the learned judge thought it sufficient, after a very brief general statement of the nature of the action, to limit his charge to his answers to the points. As no exception was taken to its adequacy, we assume that the charge_was satisfactory to the appellant at the time except in the two matters assigned for error.
By the contract payments were to be made in monthly instalments “upon certificate of the architect to estimates and valuations for materials furnished and work done,’’etc. Plaintiffs offered in evidence a certificate by the architect that plaintiffs “ are entitled to the payment of Eighteen Thousand and Fifty-Two—68 Dollars on account of their contract with the Trustees of the Presbyterian Board of Publication and Sabbath School work, for material furnished and work done under steel and iron contract up to the date of this order.”
The admission of this certificate is the first assignment of error. The certificate does not follow the language of the con
The second assignment of error is to the affirmation of plaintiffs’ point that if the jury believe “ that the plaintiffs deliv
The objection to this is to the phrase “ substantially completed,” whereas the contract required plaintiffs to “ finish and complete the same and every part and detail thereof ” within the specified time. If plaintiffs’ point stood alone it would clearly be an inaccurate statement of the law of the case. But it must be read in connection with the defendant’s first point, which stated the requirement of the contract in full, to wit: that plaintiffs were bound to “ finish and complete the same and every part and detail thereof within ninety days,” etc. By his affirmance of this point the learned judge gave the jury the exact rule applicable to the case, and in the form selected by the defendant itself. It does not appear that any special emphasis was laid by the court on either the word “substantially ” in the one point, or the words, “ every part and detail thereof ” in the other, nor was he requested so to do. The only specific instructions asked were embodied in the points themselves. In fact the work had finally been completed not only substantially, but in every part and detail, and the attention and efforts of the parties at the trial were directed, not so much to the fact of completion as to the time of it. While as already said, it would probably have been more satisfactory in the end to both parties had the judge gone over the facts and the law more in detail in his charge, yet he was not requested to do so, and was entitled to follow his own judgment in regard to it. It not infrequently happens when a ease has been fully discussed before the jury by competent counsel, that a brief charge in general terms is entirely sufficient for the occasion, though when put in print for review it may seem very bare and inadequate. In such cases much must be conceded to the discretion of the trial judge, and where no positive error appears, likely to have misled the jury, the presumptions are all in favor of the judgment. That is the case here. Under all the circumstances we cannot say that the use of the word “substantially” fol
Judgment affirmed.