Bailey Construction Co. v. Purcell

88 Va. 300 | Va. | 1891

Lewis, P.,

delivered the opinion of the court.

*301This was a suit in equity in the circuit court of Washington county by the appellee, Purcell, against the Bailej' Construction Company, the South Atlantic & Ohio Railroad Company, and others. The construction company was the general contractor to construct the South Atlantic & Ohio Railroad Company, and employed the plaintiff to do certain work as a sub-contractor. The work was completed about the 1st ■ of December, 1887, whereupon the plaintiff duly recorded in the proper clerk’s office his mechanic’s lien for an alleged balance due him, amounting to about $9,000. The object of the suit was to enforce the mechanic’s lien and to recover that amount.

A copy of the original contract, between the parties is exhibited with the bill, wherein it was stipulated that for the work done and materials furnished under the contract, payment should be made on about, the 20th of each month, upon estimates, to be approved by the appellant’s engineer. Before the completion of the work, however, the parties entered into a new contract, dated November 17, 1887, whereby it was agreed that the first- contract should terminate on the 30th of the same month, and that the work done by the plaintiff should be measured up on or before the 1st day of December, of that year, and paid for as soon as the final estimates were finished.

The bill charged that the work done by the plaintiff amounted to about $37,000, according to the estimates of one Chai’les ~K. Moore, who, it is alleged, was the chief engineer of the construction company. But the company, both in its answer and cross-hill, denies that Moore was at any time its chief engineer, and avers, moreover, that the estimates made by him were not only inaccurate and excessive, but that the final estimates, upon which the plaintiff’s claim is based, were made after he had been discharged from the company’s service, which was on the 19th of October, 1887. It is averred that he was merely employed to do work as an engineer along with others, and that the company relied on its engineers, *302Jones and Hoclge, in whose skill and competency it had entire confidence.

The evidence iu the cause is voluminous, and we do not deem it necessary to review it. It is enough to say that we have examined it carefully, and are satisfied that the principal contention of the company, the appellant here, is supported by the record.

It appears that after the completion of the work done by the appellee, it was measured up by Jones and Hodge, whose competency and integrity is not assailed, and that they estimated the whole at $24,690.97. These estimates are less by several thousand dollars than those made by Hollins, another of the company’s engineers, whose estimates amounted to $28,327.40, the reasons for which difference are stated in the record. Taking Kollin’s estimate as the proper basis for a settlement between the parties — -and the appellant does not contend to the contrary — then-there would be abalance due the appellant of $1,493.8;'), as overpaid, it appearing that there has been paid to the plaintiff various sums, at different times, on account of the work, aggregating $29,821.25.

The decree against the appellant., and of which it complains, must therefore be reversed, and decree entered in its favor for the sum of $1,493.85 and costs.

It is proper to add that there was no error in overruling the demurrer to the bill. The appellant’s contention was that the case presented a simple question of quantum, meruit, which, upon the authority of Morgan v. Carson, 7 Leigh, 238, and other cases, belonged, properly, to a court of law, and not to a court of equity. ■ Hut a sufficient answer to this position is, that the object of the suit, was to enforce an alleged mechanic’s lien, and hence the case is one of equitable jurisdiction. Code, § 2484.

Upon the merits, however, the case is with the appellant, as we have said.

Decree reversed.