109 Mo. App. 646 | Mo. Ct. App. | 1904
This is an action by the plaintiff— a corporation — to enforce a mechanic’s lien for materials furnished for the construction of certain buildings, etc. At the inception of the trial the defendant objected to the introduction of any evidence by plaintiff on the ground that the petition did not state facts sufficient to constitute a cause of action in that it — the petition— did not allege that the defendant at the time of the execution of the contract for the erection of the buildings was the owner of the land upon which the erection was to be made. By referring to the petition it is seen that the third paragraph thereof alleges that ‘ ‘ the defendant is now and was at all times hereinafter mentioned the owner of the following described real estate ’ ’ —describing it. The fourth alleges that “heretofore, to-wit, on the — day of--, 1901, and prior to the furnishing of any of the materials hereinafter mentioned, the defendant as owner of said premises entered into one general contract with said Madorie & Son whereby for a valuable consideration to be paid by defendant they agreed to erect three separate three-story brick flats on the above-described premises.”
Now, if we construe the foregoing allegations of the petition, as we must, most strongly against the pleading plaintiff, we must still conclude that the defendant’s objection was not well taken and that it was, therefore,, properly overruled. These allegations in substance and effect are that, in the year 1901 the land therein described belonged to the defendant as owner thereof, and that he, defendant, in that year, as owner entered into the contract with Madorie & Son, etc. The language of the third and fourth paragraphs already alluded to when taken in its entirety, it seems to us, must be held to allege that at the time the defendant and Madorie & Son entered into the contract for the erection of the buildings the defendant was the owner of the land on which such erection was to be made.
The defendant’s second contention is that the evidence did not tend to prove that the materials alleged to have been furnished by plaintiff under said contract were used and actually went into the land, and, therefore, his demurrer to it should for that reason have been sustained. The testimony, given by witnesses Thompson and Madorie was quite ample to warrant the submission of the case to the jury on this issue.
The defendant’s third contention is that the evidence adduced by plaintiff to prove the ownership of the land at the time of the making of the contract between him and Madorie & Son was inadmissible because secondary and not the best — no foundation having been laid for its introduction. To this contention we are unable to yield our assent because the record discloses that the plaintiff introduced in evidence a deed from the Holmeses to defendant by which the title to the land was vested in the latter on January 21,1901. Nothing appearing to the contrary, the presumption would be that the defendant was still the owner of the land when he made the contract a month later. [Besides, the contract itself recites the fact of the defendant’s ownership of the land. More could not have been reasonably required.
The defendant’s fourth contention is that the evidence adduced by plaintiff to establish the contract between defendant and Madorie & Son was incompetent. To this we can not agree for the reason that we think that the testimony of the witnesses Thompson and E. P. Madorie very clearly negate it.
At the conclusion of the evidence the court at the request of the plaintiff directed the jury to “give a verdict for plaintiff, finding the issues in its favor, and that the plaintiff was entitled to a lien on the property in question for the amount which it believed from the
The defendant’s last insistence is that the court erred in its action in refusing to admit any evidence in support of his separate affirmative defense, and in refusing his second instruction, which latter was to the effect that, “if you believe and find from the evidence that the said H. Madorie & Son executed and delivered to the said defendant a bond with themselves as principals and Alfred Toll as surety therein, and that the said bond provided amongst other things that it was to be attached to the said contract and made a part thereof, and that the said defendant should he saved harmless from any mechanic’s liens upon-said buildings and real estate, and if you further believe that the plaintiff is a corporation organized and existing under the laws of the State of Missouri, and that the said Toll was at the time of the execution of said bond the president of the plaintiff and that the said Toll became surety upon said bond (if you find that he did so) at the instance and request of the plaintiff, .and in eon
It is not contended that the plaintiff signed the indemnity bond, but that Toll, who was its president, signed it. There is no evidence that he signed it at the request of the plaintiff beyond the bare circumstance that he was its president. If from this circumstance any such inference was to be deduced it was rebutted by the testimony of Toll himself, to the effect that he became surety on said bond on his own account and not on account of any transaction of the plaintiff with Madorie & Son. Turning to the answer, it will there be seen that it alleges that one of the conditions of said bond was that defendant should be saved harmless from all mechanics’ liens in the construction of said buildings and that said Toll having signed said bond as surety as the agent of and in the place of the plaintiff
If at the time the defendant was notified by plain- ' tiff of its lien account he was indebted to the contractor in an amount equal to that of the lien account then he could, with the amount so in his hands, pay off the lien account and thus protect his property. If, on the other hand, he had paid • the contractor the full contract price and owed him nothing, he would tlien, in a suit on the lien, have the right to resort to the indemnity. He could plead the provisions of the bond and set up as a counterclaim the amount of the lien which the plaintiff, the lienor and surety was seeking to enforce against his property. The exercise by plaintiff of the statutory right to file a mechanic’s lien for the contract or reasonable value of the materials furnished the contractor and used in the erection could not hurt a landowner where he is indebted to the contractor on the contract price in an amount equal to or greater than that of the lien, for he then has it in his power to protect .himself. These statements of the law find support in the rulings made, in the following reported cases. [Hartman v. Berry, 56 Mo. 487; Deitz v. Leete, 28 Mo. App. 541; Handley v. Ward, 70 Mo. App. 146; Fullerton Lumber Co. v. Gates, 89 Mo. App. 205.]
It is thus made to appear that the law does not presume from the mere fact of the filing of the lien that the landowner is hurt and thereby authorizes a resort to the indemnity. Something more is required. He
The judgment must therefore be affirmed.