Dawn BACIOTTI, Carmen Baciotti and Melanie Baciotti, his wife v. Michael V. SIMMONS and Strasburg Township.
Superior Court of Pennsylvania.
Filed Sept. 18, 1985.
498 A.2d 1351
Argued April 24, 1985.
Appellant‘s final arguments are specious. The record does not disclose any reason for the court sua sponte to interrogate the members of the jury daily to determine whether they had obtained extra-judicial information about appellant or the criminal charge against him. Similarly, appellant‘s contention that the trial court refused to enforce a defense subpoena is unwarranted and unsupported.
The judgment of sentence is affirmed.
Richard H. Wix, Harrisburg, for Simmons, appellee.
Sharon D. Hyde, Lancaster, for Strasburg, appellee.
Before SPAETH, President Judge, and CAVANAUGH, BROSKY, ROWLEY, WIEAND, McEWEN, DEL SOLE, BECK and TAMILIA, JJ.
The issue in this appeal concerns the application of
On January 23, 1980, Dawn Baciotti1 commenced an action against Michael V. Simmons and Strasburg Township to recover damages for personal injuries sustained in an automobile accident occurring in Lancaster County on December 13, 1978. On March 1, 1982, Strasburg Township made a written offer to settle Baciotti‘s claim for $50,000.00, its policy limits, in exchange for a joint tortfeasor‘s release, but Baciotti rejected the offer. Simmons, on March 6, 1982, offered to pay Baciotti $100,000.00 if she would execute a joint tortfeasor‘s release in his favor. This offer was accepted. Although Strasburg Township‘s offer of $50,000.00 was not revoked prior to trial, Baciotti continued to reject it. On April 27, 1982, following trial, a jury returned a verdict for Baciotti, fixed her damages at $150,000.00, and apportioned negligence as follows: Baciotti—10%; Simmons—40%; and Strasburg Township—50%. Baciotti then filed a petition to mold the verdict. Included was a request for delay damages pursuant to
Rule 238. Award of Damages for Delay in an Action for Bodily Injury, Death or Property Damage
(a) Except as provided in subdivision (e), in an action seeking monetary relief for bodily injury, death or property damage, or any combination thereof, the court or the arbitrators appointed under the Arbitration Act of June 16, 1836, P.L. 715, as amended,
5 P.S. § 30 et seq. , or the Health Care Services Malpractice Act of October 15, 1975, P.L. 390,40 P.S. § 1301.101 et seq. , shall(1) add to the amount of compensatory damages in the award of the arbitrators, in the verdict of a jury, or in the court‘s decision in a nonjury trial, damages for delay at ten (10) percent per annum, not compounded, which shall become part of the award, verdict or decision;
(2) compute the damages for delay from the date the plaintiff filed the initial complaint in the action or from a date one year after the accrual of the cause of action whichever is later, up to the date of the award, verdict or decision.
. . . .
(e) If a defendant at any time prior to trial makes a written offer of settlement in a specified sum with prompt cash payment to the plaintiff, and continues that offer in effect until commencement of trial, but the offer is not accepted and the plaintiff does not recover by award, verdict or decision, exclusive of damages for delay, more than 125 percent of the offer, the court or the arbitrators shall not award damages for delay for the period after the date the offer was made.
The rule was adopted by the Supreme Court in 1978 “as an extension of the compensatory damages necessary to make a plaintiff whole.” Feingold v. Southeastern Pennsylvania Transportation Authority, 339 Pa.Super. 15, 31, 488 A.2d 284, 293 (1985), quoting Laudenberger v. Port Authority of Allegheny County, 496 Pa. 52, 66, 436 A.2d 147, 154 (1981), appeal dismissed sub nom., Bucheit v. Laudenberger, 456 U.S. 940, 102 S.Ct. 2002, 72 L.Ed.2d 462 (1982). An award of delay damages “serves to compensate the plaintiff for the inability to utilize funds rightfully due him, but the basic aim of the rule is to alleviate delay in the disposition of cases, thereby lessening congestion in the courts.” Greenspan v. United Service Automobile Association, 324 Pa.Super. 315, 323, 471 A.2d 856, 860 (1984), quoting Laudenberger v. Port Authority of Allegheny County, supra 496 Pa. at 59, 436 A.2d at 151. By providing that delay damages are tolled after a written offer of settlement has been made which, in retrospect, is eighty percent or more of the ultimate verdict, the rule attempts not only to encourage pre-trial settlement but to foster settlement at an early date. Laudenberger v. Port Authority of Allegheny County, supra, 496 Pa. at 59, 436 A.2d at 151. Defendants are given an opportunity to protect themselves from exposure to pre-judgment interest by making a reasonable offer of settlement in good faith and in a timely fashion. Id., 496 Pa. at 59-60, 436 A.2d at 151. Accord: Krupa v. Williams, 316 Pa.Super. 408, 423, 463 A.2d 429, 436 (1983).
The purposes to be accomplished by
In order to assess the liability of Strasburg Township for delay damages, it will be necessary to examine three distinct phases of the pre-verdict negotiations. The first phase consists of the period from the commencement of Baciotti‘s action until the time when Strasburg Township made an offer of $50,000.00. The second phase of settlement negotiations is the period between the time this first offer was made and the time when Baciotti accepted Simmons’ offer of $100,000.00. The third period includes the time between Baciotti‘s acceptance of $100,000.00 from Simmons and the time of the verdict.
For the period following the filing of the complaint on January 23, 1980 and continuing until March 1, 1982, when Strasburg Township made its offer, Baciotti was clearly entitled to recover damages for delay from Strasburg Township.
Delay damages must be measured in the same manner after the Township made an offer of $50,000.00 and before Simmons settled for $100,000.00. The Township‘s offer was inadequate to terminate its liability for delay damages. The amount of its liability, i.e., $75,000.00, as found by the jury, exceeded its offer by more than 125 percent. This offer, therefore, did not terminate the Township‘s liability for Rule 238 damages. See:
When we examine the findings of the jury and apply them retrospectively to the absence of adequate settlement negotiations prior to March 6, 1982, we see that Strasburg Township‘s liability during this period of time was $75,000.00. Both the adequacy of its offer and the computation of delay damages, therefore, must be measured against this amount of $75,000.00. This was the Township‘s liability, as found by the jury, and this is the amount which must be used to measure the reasonableness of the demands made by the plaintiff and the offers made by the Township during negotiations.
After Simmons had settled for $100,000.00, however, there was necessarily a change in the focus of negotiations between Baciotti and Strasburg Township. Both parties knew that under existing law the Township was now entitled to a credit for any overpayment made by Simmons. Their continuing negotiations, therefore, were controlled primarily by the amount which Strasburg Township would be required to pay Baciotti. To expect that the parties would thereafter negotiate with respect to the amount of a possible verdict, without considering the actual amount which would have to be paid, would be wholly unrealistic.
We conclude, for these reasons, that Strasburg Township is liable for delay damages from January 23, 1980 to March 6, 1982. Those damages must be computed at the rate of ten percent per annum on the sum of $75,000.00.
Remanded for the entry of judgment consistent with the foregoing opinion. Jurisdiction is not retained.
CAVANAUGH, J., files a dissenting opinion in which SPAETH, President Judge, and McEWEN and BECK, JJ., join.
CAVANAUGH, Judge, dissenting:
I agree with the majority that the non-settling defendant, Strasburg Township, must pay delay damages under Rule 238 computed upon $75,000.00. I disagree, however, that its responsibility should be terminated as of March 6, 1982,
The primary purpose of Rule 238 is “to alleviate delay in the disposition of cases, thereby lessening congestion in the courts.” Laudenberger v. Port Authority of Allegheny County, 496 Pa. 52, 59, 436 A.2d 147, 151 (1981). More specifically, the Rule is designed to foster the early resolution of disputes, as evinced in drafter‘s comments:
Statistics show that only 38 percent of these cases ever go to trial and 25 percent ever go to verdict. Thirty-eight percent are settled without going to trial. Some are settled through pretrial conciliation techniques, but in too many cases meaningful negotiations commence only after a trial date is fixed or on the courthouse steps or in the courtroom, thus leading to delay in the disposition of cases and congestion of the courts. The present practice provides no incentive for early settlement.
8 Pa.Admin.Bull. 2668 (1978) (emphasis added). In order to accomplish this goal of early settlement, the Rule seeks to penalize defendants who refuse to settle through the imposition of delay damages, and to encourage plaintiffs to accept reasonable settlement offers by cutting off the accrual of those delay damages.
I seriously question whether the majority‘s application of Rule 238 where one defendant has settled furthers the espoused goal of prompting the seasonable disposition of cases. Under the majority‘s holding, the reasonableness of a non-settling defendant‘s offer to settle is determined in light of that defendant‘s adjudged share of the verdict less any overpayment by a settling defendant. If the non-settling defendant‘s offer is eighty percent or more of the adjusted figure, then according to the majority, the non-settling defendant‘s delay damage liability is terminated as of the date of the accepted settlement.
My concerns with this result are several. Under the majority‘s approach, delay damages may accrue against a non-settling defendant up until the date that the plaintiff
My second concern is perhaps more philosophical. It is apparent from the Rule and its comments that the drafters sought to prompt all defendants to engage in reasonable settlement negotiations. Cf.
Finally, I think that it is important to note that the non-settling defendant‘s ultimate financial responsibility is not diminished by a settling co-defendant‘s overpayment. The Uniform Contribution Among Tort-feasors Act has been construed
to permit a right of contribution on the part of a settling tort-feasor, when by the settlement, the settling tort-feasor pays more than his share of the total liability ultimately found. In that situation the rule would thus allow the settling tort-feasor to seek contribution from a non-settling tort-feasor to the extent that the amount paid by the settling tort-feasor exceeds his percentage of negligence, but in no event more than the percentage of negligence attributable to the non-settling tort-feasor.
Charles v. Giant Eagle Markets, 330 Pa.Super. 76, 82, 478 A.2d 1359, 1362 (1984) (footnote omitted). See also Mong v. Hershberger, 200 Pa.Super. 68, 186 A.2d 427 (1962). Thus, for example, in the instant case defendant Simmons may have a right of contribution against Strasburg Township for $40,000.00. Because of this outstanding liability, I do not think it is realistic to expect and require, as the majority
The language of
8 Pa.Admin.Bull. 2668 (1978). Similarly, in the present situation, I do not believe that a possible windfall to the plaintiff is enough to justify the construction of the Rule espoused by the majority. I would opt for the most straightforward application of Rule 238, thereby avoiding any uncertainty in the calculation of delay damages.
For these reasons, I would affirm the order of the trial court in favor of settling defendant, Simmons. I would reverse and remand the case for the imposition of delay damages against Strasburg Township calculated on $75,000.00 for the period from January 23, 1980 until April 27, 1982, the date of the verdict.
SPAETH, President Judge, and McEWEN and BECK, JJ., join in this dissenting opinion.
Notes
Fourth, recognizing that additional defendants may often be involved, and in some cases may even be joined after the initial one-year period has expired and damages for delay begin to accrue, an additional defendant who is joined at a late date must neverthe-
