293 Mass. 297 | Mass. | 1936
This is a suit in equity whereby the plain-. tiff seeks to have applied to the satisfaction of his claim security which was furnished under a written contract between the Commonwealth and B. Perini & Sons, Inc., hereinafter called the defendant. The defendant in its answer denies the allegations of the bill and in its amended answer sets forth a counterclaim. The case was referred to a master who heard the parties and their witnesses, and filed a report. The defendant filed certain objections to the report. An interlocutory decree was entered confirming the report, except that portion of it which recited testimony to which the defendant had objected. A final decree was entered for the plaintiff for the full amount of his claim less the amount' of the counterclaim which was allowed. The case is before this court upon appeal by the defendant from the final decree. It does not appear that any appeal was taken from the interlocutory decree. G. L. (Ter. Ed.) c. 214, § 27, provides: “Interlocutory decrees not appealed from shall be open to revision upon appeals from final decrees, so far only as it appears to the full court that such final decrees are erroneously affected thereby.” See Arwshan v. Meshaka, 288 Mass. 31, 34.
The master made the following findings: The suit is brought to recover $1,804.99 with interest from February 7, 1933, as set out in an account marked “A” annexed to the plaintiff’s bill. There was a written contract between the plaintiff and the defendant made September 7, 1932, which incorporated by reference and made a part of said contract, a contract between the Commonwealth and the defendant. The contract was not changed subsequently to its execution. It required the plaintiff to set all the necessary edgestones in the construction of a section of a State highway between Boston and Worcester. The plaintiff set all of the required edgestones provided for in the contract “under the direction of” and to the satisfaction of the engineer in charge for the Commonwealth and also to the satisfaction of the defendant. The plaintiff covenanted in
The master further found that all the extra work in dispute between the plaintiff and the defendant was required by the action of the defendant in laying the macadam road before the plaintiff had a reasonable opportunity to set the edgestones, and that the extra work in issue was not made necessary by any delay on the part of the plaintiff; that the number of men and the hours worked by each, as charged for by the plaintiff in the account annexed, are the same as actually were used by the plaintiff in the extra work described; and that the prices paid to the workmen and charged to the defendant were fair and reasonable for such labor.
The following findings also appear: The plaintiff, shortly after the contract declared on was signed, attempted to get liability insurance covering the public and compensa
An order for a final decree was entered in the Superior Court providing that the defendant was indebted to the plaintiff in the sums of $1,216.19 and $588.80 with interest from the date of the bill, and that the plaintiff was indebted to the defendant in the sum of $420 with interest from the date of the bill; that the net indebtedness of the defendant to the plaintiff was established in the sum of $1,384.99 with interest from the date of the bill. Thereafter a final decree was entered establishing the net indebtedness of the defendant to the plaintiff in the sum of $1,384.99 with interest from March 21, 1933, and ordering that the Commonwealth pay from the money in its hands, to the plaintiff, the amount due him with interest, and directing the application of the security sought to be reached to its satisfaction so far as the money in the hands of the Commonwealth was insufficient. The defendant appealed from the final decree.
The facts found by the master show that the plaintiff acted in good faith and that there was no intentional departure by him from the provisions of the contract which would prevent his recovery under the account annexed for work performed under the terms of the contract and for extra work actually performed and properly charged for. Glazer v. Schwartz, 276 Mass. 54, 57. Soares v. Weitzman, 281 Mass. 409. Zarthar v. Saliba, 282 Mass. 558, 561, and cases therein cited. The master found that the plaintiff, shortly after the contract was signed, endeavored to obtain
The plaintiff is entitled to recover the amounts charged and allowed for the extra work caused by the defendant laying macadam over the roadway in which the edgestones were set, Howard v. Harvard Congregational Society, 223 Mass. 562. Although the contract provided that the plaintiff was to do all the digging, there was evidence of a usage that a- roadbed of macadam was never laid before the edgestones were set in position. The contract of the plaintiff to do all the digging must be interpreted in view of ■this usage. Work incurred by the plaintiff as a result of the' disregard of this usage by the defendant manifestly would not be included within the. terms of the plaintiff’s
As no error appears the decree entered is to be affirmed.
Ordered accordingly.