NOTICE: Federal Circuit Local Rule 47.8(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.
AVISON LUMBER COMPANY, Plaintiff-Appellant,
v.
The UNITED STATES, Defendant-Appellee.
No. 92-5041.
United States Court of Appeals, Federal Circuit.
July 14, 1992.
Before RICH, MAYER and MICHEL, Circuit Judges.
MICHEL, Circuit Judge.
DECISION
Avison Lumber Company appeals the decision of the United States Claims Court which dismissed Avison's suit for lack of subject matter jurisdiction. Avison Lumber Co. v. United States, No. 590-88C, (Cl.Ct. Oct. 28, 1991). Because neither the November 9, 1982 submission nor the October 14, 1987 submission was a properly certified claim and because the two submissions cannot be combined to satisfy the prerequisites for Claims Court jurisdiction, we affirm.
DISCUSSION
The Contract Disputes Act (CDA) provides: "All claims by a contractor against the government relating to a contract shall be in writing and shall be submitted to the contracting officer for a decision." 41 U.S.C. § 605(a) (1988). This provision has been interpreted to mean that in order for a submission to be a claim it must contain a request for a final decision. Mingus Constructors, Inc. v. United States,
Likewise, the October 14, 1987 submission does not appear to satisfy the requirements for a claim. The Federal Acquisition Regulation (FAR) defines the term "claim" as:
a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract.
48 C.F.R. § 33.201 (1991). See Essex Electro Engineers, Inc. v. United States,
Even if the October 14, 1987 submission were interpreted to request a sum certain in the lower amount and thereby satisfy the regulatory requirements for a claim, the October 14, 1987 submission fails to satisfy the statutory requirement that the claim be certified. See 41 U.S.C. § 605(c)(1) (1988). Although the November 9, 1982 submission was certified, the October 14, 1987 submission was not. Therefore, the October 14, 1987 submission cannot, in and of itself, serve as a basis for Claims Court jurisdiction. See Skelly and Loy v. United States,
The issue then becomes whether the two submissions can be considered together to satisfy the jurisdictional prerequisites for Claims Court jurisdiction. They cannot. "[T]he [CDA] ... makes clear that the time for certification is upon submission of a written claim to the contracting officer. Section 605(c)(1) & (2)." Id. at 418. Thus, Avison's November 9, 1982 certification cannot be combined with its later submission on October 14, 1987 to satisfy the statutory requirement of certification. See also J.M.T. Mach. Co., Inc. v. United States,
Notes
With respect to the proposed settlement, the October 14, 1987 letter stated:
If you are unwilling to agree to this settlement, please issue a formal contracting officer's decision on Avison's November 9, 1982 certified claim so that suit can be filed in the U.S. Claims Court to recover the remaining amounts owed.
We note that the letter also stated:
Avison Lumber Co. modifies and limits its certified claim to recover $56,918.00, plus interest as allowed by law from November 9, 1982 until paid.
