This is a case where a counterclaim alleged tort and requested punitive damages. The trial court persuaded the claimant to change the allegation to one of breach of contract rather than tort, leaving the impression that punitive damages would still be allowed. The court was in error in two respects. First, it abused its discretion in instigating an amendment
The only facts necessary to an understanding of the issues on appeal are: Randall S. Kurtz purchased the net assets of a restaurant business after obtaining oral consent from the landlord, Autumn Grove Joint Venture, to an assignment of the lease of the premises. Shortly after commencing operations, questions arose regarding payment for common area charges in the surrounding shopping center, heating bills, sewer odors and a fire protection system. Autumn Grove claimed that it never consented in writing to the assignment and therefore was not responsible for those items.
Thereafter, Kurtz decided to sell the business for about $95,000 and one Anthony Selensky was interested. Simultaneously, Autumn Grove attempted to terminate its lease with Kurtz and tentatively leased the business premises to a third party. Upon learning of Kurtz’s difficulties, Selensky offered only $25,000.
The offer was eventually raised to $45,000, mostly payable by note, contingent upon Selensky’s being able to negotiate a new lease with Autumn Grove. Kurtz agreed. Selensky and Autumn Grove signed a new lease at a greatly increased rental payment to Autumn Grove. Yet, Autumn Grove then refused to honor the new lease unless Kurtz paid $6500 for rent, the fire protection system and the common area charges it claimed were still in dispute. Subsequently, Selensky tried to sell, but his efforts faltered because
Autumn Grove started the lawsuit, seeking termination of the lease and the rights of Kurtz and underlying third parties. Kurtz counterclaimed, alleging tortious interference of contract and sought both compensatory and punitive damages. Kurtz later amended his counterclaim, adding claims of unreasonable withholding of consent to the assignment of the lease and breach of various covenants.
In a summary judgment proceeding, the trial court apparently dismissed Autumn Grove’s complaint, ruling that it failed to give proper notice of termination. This left only the counterclaim. 1
On the morning of trial, the court persuaded Kurtz to drop his claim that Autumn Grove tortiously interfered with the. ongoing contractual negotiations between Selensky and him. The trial court also persuaded Kurtz to drop his allegation that Autumn Grove unreasonably withheld approval of the lease assignment and breached various covenants. Instead, the claim became one of improper termination of the lease by Autumn Grove. 2
The jury found in the affirmative and assessed compensatory and punitive damages against Autumn Grove. Autumn Grove then brought this appeal, claiming prejudicial surprise in the eleventh hour amendments and also claiming that punitive damages cannot be collected for an underlying breach of contract action. We agree on both counts.
We acknowledge that the trial judge must be more than a referee,
see Schultz v. State,
Autumn Grove was prepared to try a tort case. Interference with contractual relations occurs where one who, without privilege to do so, induces or otherwise purposely causes a third party not to perform a contract.
Pure Milk Prods. Coop. v. National Farmers Org.,
We also hold that the trial court’s shifting of theories prejudiced Kurtz. It appears from the trial transcript and from our oral argument that the trial court induced Kurtz to operate under the impression that one can recover punitive damages when the underlying cause of action is one of contract, not tort. The trial court, in fact, stated that the "labels” as to whether the action was based upon a contract theory or tort theory were not important. 3
It is true there was a disregard for the plaintiffs right but this is true in every breach of contract.Ford’s breach did not have those characteristics which constitute a tort. Punitive damages are not allowed for a mere breach of contract_[Empha-sis added.]
Entzminger,
Section 752.35, Stats., authorizes the court of appeals to order a new trial if the real issue has not been fully tried or if it is probable that justice has been miscarried. Faced with the confusing procedures followed in this case, due in large part to the well-intentioned but misguided undertakings of the trial court and its erroneous view of the law of punitive damages, we order a new trial to assure that the real controversy will be fully tried. The issue of whether Autumn Grove tortiously interfered with Kurtz’s contractual relations was one of the real issues in controversy; it was never tried. The original contractual allegations were also never really tried, though one of the claims did ultimately go to the jury. That issue should be retried so that the litigators have a full opportunity to place the proper evidence before the jury.
We reverse and remand for a new trial. The trial court shall allow such amendments to the pleadings as the parties deem necessary consistent with this decision and the applicable statutes and rules.
By the Court. — Judgment reversed and cause remanded with directions.
Notes
A definitive order concerning the status of the complaint as either dismissed or still in effect was never made by the trial court. Neither party at oral argument was able to explain the present status of the complaint and this uncertainty exists even to this date. In any event, it appears that the court and all of the parties agreed that for purposes of the ensuing trial, this ruling left only Kurtz’s counterclaim and Autumn Grove’s reply as the governing pleadings.
The amendment to the counterclaim was premised, in part, upon the trial court’s belief that the parties had conducted their substantial pretrial negotiations on this basis. This may well have
At one point, near the end of the trial, the court stated:
THE COURT: Okay. Well, a quick study, there’s no way I’m going to digest all those cases at 9 o’clock with the jury having been told we’re starting at quarter to nine, so on. So my impression of the law certainly is punitive damages are available in non-tort actions, and it’s no longer crucial what kind of label you put on something. I think we’ve gotten away from that in the law. I think we’re interested in the substantive issues rather than what kind of action; some lawyer may not have chosen to denominate his lawsuit and certainly would allow another amendment, in exercising my discretion, if it is necessary to amend to allege something else to conform to the proof. ... Obviously my impression is they’re available, has been my impression throughout and still is my impression, and the question labels, I’ll certainly do whatever I can to change the label if that’s necessary.
The court also stated;
Mr. Cannon stated cases said you can’t have [punitive damages] in contracts, but I’m not much of a label man myself; so I think that my ruling would probably be, "Hey, if you can have punitive damages in a negligence action, you can have them in a contract action too,” and that’s what the Court is trying to tell us, I think; that it’s not limited to intentional torts which you used to think because we think punitives can only follow from wanton and intentional, outrageous conduct, et cetera, et cetera. So to me unless we continue in the dark ages and get results upon labels, Wangen also leads to the conclusion you can have punitives in breach of contract actions too.
We note that two other appellate court decisions since
Wangen v. Ford Motor Co.,
"Ordinarily, a breach of a contract is not a tort, but a contract may create a state of things which furnishes the occasion of a tort.”
Colton v. Foulkes,
It is also appropriate to point out that Wisconsin has not recognized a cause of action for "tortious breach of contract.”
Anderson v. Continental Ins. Co.,
