OPINION OF THE COURT
Memorandum.
The order of the Appellate Division, insofar as appealed from, should be reversed, with costs, and judgment granted to Niagara Mohawk Power Co. (NiMo) on its third-party complaint against third-party defendants Weber Construction Co., Inc., and Kenneth Begin.
The Appellate Division affirmed the dismissal, following trial, of NiMo’s third-party complaint insofar as it demanded indemnification from Weber for liability arising out of NiMo’s gross negligence. The demand was based on an agreement by Weber to indemnify NiMo for any liability caused by the latter’s negligence resulting, in whole or in part, in bodily injury arising out of work performed by Weber under a construction contract. The Appellate Division relied on this court’s pronouncements, in Gross v Sweet (
Chief Judge Wachtler and Judges Meyer, Simons, Kaye, Alexander and Titone concur; Judge Jasen taking no part.
Order reversed, with costs, and judgment granted to Niagara Mohawk Power Corporation in accordance with the memorandum herein.