173 P. 664 | Or. | 1918
Chapter 185, Gen. Laws Or. 1915, was evidently patterned after an act of the legislative assembly of the State of Washington, approved March 4, 1909 (Laws Wash. 1909, Chap. 45), and incorporated in Rem. & Bal. Code as Section 1133, the material parts of which read:
“Every person furnishing material or supplies to be used in the construction, alteration or repair of any * * building * * shall, at the time such material or supplies are delivered to any person or contractor, deliver or mail to the owner, or reputed owner, of the property, on, upon or about which said materials or supplies are to be used, a duplicate statement of all such materials or supplies delivered to any contractor or person to whom any such materials or supplies have been sold or delivered, and no materialmen’s lien shall be filed or enforced unless the provisions of this act have been complied with.”
The decree appealed from herein is based upon the assumption that the contract for the delivery of the lumber was made prior to May 21, 1915, when the amendment of Section 7116, L. O. L., became operative ; that before any alteration had thus been made in the law, the plaintiffs’ contract and the material which
In Benbow v. The James Johns, 56 Or. 554, 560 (108 Pac. 634), in speaking of the security which the statute afforded materialmen and laborers, it is said:
“The lien is created by the law, and attaches as soon as the labor or material is furnished and is not dependent on any subsequent condition, expressed or implied.”
It is doubtful if the lien attaches at the time stated. In Johnson v. Tucker, 85 Or. 646, 649 (167 Pac. 787), it is believed Mr. Justice Burnett correctly states the rule as follows:
“Although a mechanic’s lien takes its origin with the furnishing of labor or materials it is not perfected until the notice or claim of lien is filed, whereupon it relates back to the beginning when the work commenced or the materials were furnished.”
In Steamer Gazelle v. Lake, 1 Or. 119, after lumber had been furnished with which to build a steamboat,
In Willamette Falls Transp. & Mill. Co. v. Riley, 1 Or. 183, 185, pursuant to a contract made in June, 1853, work and labor was performed upon a building until September, 1854. On May 1st, of the latter year, however, a statute enacted in 1851, which gave a lien for such service, was repealed without any saving clause, and another law was adopted in lieu thereof. In deciding that the right to the lien continued notwithstanding the repeal, Mr. Chief Justice Williams remarks :
“When Eiley commenced labor upon the buildings of said company, the law, to secure the payment of his wages, gave him alien therefor upon said buildings, and required him, within sixty days from their completion, to file a notice of his intention to hold such lien; but before said buildings were completed, the law was repealed, and another enacted at the same time, which allowed him three months in which to file, and in which he did file, said notice. Now, as one statute ceased to exist, and the other was created uno flatu, we think that the act of 1854 may be regarded as a continuation of the act of 1851, so that the laborer may have that security for his hire which the law promised when he commenced work; the labor, in question, must be regarded as an entirety, and the rights of the party to the whole job be determined in accordance with the law in force at the time the contract was made, or in accordance with the law in force at the time the work was finished. ’ ’
The act of the legislative assembly of the Territory of Oregon passed February 4, 1851, and referred to in
“work done, and supplies or materials furnished by the tradesmen, mechanics, or others for, on account of, or towards the building * * such boats or vessels, and the debts so contracted, shall be a lien on such boats or vessels”: Gen. Laws Or. passed at the second session begun and held at Oregon City, December 2, 1850, p. 169, § 1.
That act contained no provision for the filing of any claim as a condition precedent to securing the lien, but required the claimant to file a verified statement of his claim against the boat or vessel with the justice of the peace of the county where the boat was, if the demand did not exceed $100, or if greater than that sum such verified statement was to be filed with the clerk of the District Court of the proper county, whereupon a warrant of attachment was issued and the boat or vessel seized by the sheriff nr constable: Id., § 2.
As no claim of lien was required to be filed at that time in respect to such class of property, it was properly held in the case last cited that the lien thus recognized was not inchoate, but became vested upon the delivery of the lumber which was used in building the steamboat. Under enactments like those at present in force in Oregon, it is believed however, that the right to a statutory lien is only inchoate, and that the lien does not become vested until the notice or claim has been filed, as required by law: Bloom, Mechanics’ Liens, § 416; 27 Cyc. 110; 18 R. C. L. 946. It will be seen that the decision rendered in Steamer Gazelle v. Lake, supra, which is cited and relied upon by plaintiffs ’ counsel, is not controlling herein.
In Weaver v. Sells, 10 Kan. 609, a claimant who had sold and delivered lumber which was used in the construction of a building, filed a claim of lien for the value of the material so supplied. The statute giving the lien was repealed without excepting any causes from its operation. In deciding that case it was held that a lien for material became vested when the lumber was furnished, and that it was not within the power of the legislature afterward to destroy the right, by repealing the statute under which the right accrued. In that case as the filing of the notice was essential to the preservation of the lien, we do not think the right became vested until the claim was filed.
A text-writer in discussing this subject remarks:
“Some courts hold that a mechanic’s lien is a vested right, which the legislature cannot take away after it has once accrued; but the better reason and an equal weight of authority sustain the doctrine that the lien pertains merely to the remedy, and may therefore be taken away by the legislature that created it”: Boisot, Mechanics’ Liens, § 33.
Another author observes:
“Where a contract was made and materials were furnished while a certain lien law was in force, but the notice of lien was not filed in the recorder’s office until*293 after a subsequent lien law went into effect, the court held that the lien was not lost, but that it must be enforced in accordance with the provisions of the latter act. In the second act there was a saving clause. ‘Nothing contained in this act shall be deemed to apply to or affect any lien heretofore acquired. ’ Until the claim was filed there was simply a right to a lien, and the lien had not yet been ‘acquired’ (although this point was not specially noticed in the case referred to); yet the court held that ‘after the new statute went into effect, all subsequent acts and proceedings relating to the lien or its enforcement were governed by, and must have been in accordance with, its provisions’ Bloom, Mechanics’ Liens, § 36.
The right to the lien not being vested when the amendment was enacted, such statute pertained only to the remedy, and this being so the alleged lien must fail for want of delivering or mailing to the owners of the real property duplicate statements of the ma
Rehearing Denied.