delivered the opinion of the court:
Nearly two years after she was denied insurance coverage for the loss of her pleasure boat, plaintiff, Marjorie Atwood, sued defendant, St. Paul Fire & Marine Insurance Company, for breach of the parties’ insurance contract (Policy). Defendant moved for summary judgment, arguing that, based on a one-year limitations period in the Policy, plaintiff’s suit was untimely. The trial court agreed and granted defendant’s motion. Plaintiff appeals, and we affirm.
I. BACKGROUND
The relevant facts are undisputed. The Policy provided coverage in the event of certain losses associated with plaintiffs 28-foot pleasure boat. 1 For example, the Policy covered salvage and towing costs. Also, the Policy covered many items of personal property on the boat. However, the Policy did not cover loss due to the boat’s deterioration.
The Policy outlined steps for plaintiff to follow in the event of a loss. In particular, the Policy detailed how plaintiff should go about obtaining coverage. Additionally, the Policy spelled out what plaintiff needed to do if coverage was denied and if she believed that the denial was improper. Specifically, plaintiff could sue defendant to recover for the damage, but she needed to do so within one year of the date on which the damage occurred, unless state law provided her more time (Policy Limitations Period). This requirement appeared in the Policy under a bold heading:
“Lawsuits to recover under physical damage coverage. Any lawsuit to recover on a physical damage claim must begin within one year after the date on which the direct physical loss or damage occurred. If a state law provides you more time, we’ll conform to that law.”
On September 6, 2002, plaintiffs pleasure boat sank. Several days later, on September 9, the loss was reported to defendant, and a coverage investigation began. The investigation determined that the sinking was due to the boat’s deterioration, which had allowed water to enter
On September 7, 2004, almost two full years after being notified of the denial of coverage, plaintiff sued defendant for breach of contract. In her complaint, plaintiff did not respond to the conclusion that deterioration had caused her boat to sink; she simply stated that the loss was covered and that defendant had therefore wrongfully denied coverage. In response, defendant filed a motion for summary judgment, arguing that plaintiff’s claim was untimely under the Policy Limitations Period. The trial court granted that motion. Plaintiff appeals.
II. ANALYSIS
We begin with the standard of review. The use of the summary judgment procedure is to be encouraged as an aid in the expeditious disposition of a lawsuit. Adams v. Northern Illinois Gas Co.,
Here, plaintiff argues that the trial court erred in finding that, based on the Policy Limitations Period, plaintiffs suit was untimely. To evaluate plaintiffs argument, we must construe the Policy Limitations Period. An insurance policy is a contract, and, accordingly, its interpretation is governed by the familiar rules that govern the construction of contracts in general. Hobbs v. Hartford Insurance Co. of the Midwest,
The Policy Limitations Period limits the time within which a lawsuit may be brought. In particular, it states that “[a]ny lawsuit to recover on a physical damage claim must begin within one year after the date on which the direct physical loss or damage occurred. If a state law
At the outset, we note that there is no suggestion that the Policy Limitations Period contravenes public policy. Nor could there be. See Village of Lake in the Hills v. Illinois Emcasco Insurance Co.,
Under plaintiffs interpretation, the Policy Limitations Period is a nullity in every state where a general statute of limitations on contract actions gives a party more than one year to file suit. This appears to be every state. See, e.g., Conn. Gen. Stat. Ann. § 52 — 576 (West 2002) (six years in Connecticut); Minn. Stat. Ann. § 541.05 (West 2002) (six years in Minnesota); N.C. Gen. Stat. Ann. § 1 — 52 (West 2002) (three years in North Carolina); N.D. Cent. Code § 28 — 01—16 (West 2002) (six years in North Dakota); Vernon’s Tex. Civ. Prac. & Rem. Code Ann. § 16.004 (Vernon 2002) (four years in Texas). Accordingly, if plaintiffs interpretation is correct, then the Policy’s reference to state law renders wholly meaningless the one-year limitation on filing suit.
There are three serious problems with this interpretation. First, it offends a well-settled principle of contract construction: a contract must not be interpreted in a manner that nullifies provisions of that contract. See, e.g., Smith v. Burkitt,
Second, plaintiffs interpretation suggests a post hoc reading of the Policy that cannot reasonably be said to be consistent with the intent of the parties at the time they entered into the contract. For its part, defendant certainly did not intend the Policy’s one-year time limit to be meaningless in every state, and plaintiff could not have reasonably read the Policy as suggesting such an intent on defendant’s part. Therefore, plaintiffs interpretation of the policy is unreasonable. See Schwinder v. Austin Bank of Chicago,
Third, plaintiffs interpretation is undermined by the weight of authority. For
Likewise, in the present case, accepting plaintiffs interpretation of the Policy Limitations Period renders the one-year limitation meaningless. We decline to give the Policy Limitations Period such a construction.
Plaintiff attempts to distinguish Wabash by arguing that there, unlike in the present case, the provision at issue dealt with fire insurance, the limitations period for which is set by the state Director of Insurance and may not be contractually altered. See Wabash,
Courts in other jurisdictions have reached the same result as the Wabash court. For example, in Bargaintown, D.C., Inc. v. Bellefonte Insurance Co.,
For her part, plaintiff cites no case in which a court reached a different result. And our research has uncovered only two cases in which courts accepted arguments similar to the one that plaintiff advances. But neither of these cases alters the conclusion that the Policy Limitations Period does not refer to the statute of limitations on contract actions in general. In one of these cases, which was decided almost 30 years ago, the Georgia Supreme Court found that the phrase “ ‘unless a longer period of time is provided by applicable statute’ ” referred to the statute of limitations on contract actions in general. Queen Tufting Co. v. Fireman's Fund Insurance Co.,
As the above authorities illustrate, plaintiffs interpretation of the Policy Limitations Period is not reasonable. However, another interpretation is reasonable: the Policy Limitations Period provides one year to file suit, unless a specific state law directed at insurance provides more. See Graingrowers Warehouse,
It turns out that Illinois law does require more time than the Policy Limitations Period. In particular, section 143.1 of the Illinois Insurance Code (Code) (215 ILCS 5/143.1 (West 2002)) requires that, when an insurance policy limits the time within which suit may be filed, the running of that time is tolled between the time the insured files proof of loss with its insurer and the time the insurer denies the claim. 2 Here, the Policy Limitations Period requires that an insured file suit within one year of the date of loss. By application of section 143.1, however, that time is extended. Specifically, the time is extended by excluding from the one-year calculation the time after which proof of loss is filed and before which the claim is denied. But in the present case, plaintiffs suit is untimely even after section 143.1 is applied. Thus, this extension does not make plaintiffs suit timely.
To summarize, plaintiffs interpretation of the Policy Limitations Period is inconsistent with basic principles of contract construction. Moreover, plaintiffs interpretation does not reflect the intent or reasonable expectations of the parties at the time they entered into the contract. Finally, numerous cases, including a decision from our own appellate court, support the conclusion that the Policy Limitations Period does not refer to the statute of limitations on contract actions in general. In short, plaintiffs interpretation of the Policy Limitations Period is unreasonable. A reasonable interpretation, by contrast, views the Policy Limitations Period as referring to a specific statute directed at insurance, such as section 143.1 of the Code. Put another way, plaintiffs suit was not timely under a reasonable interpretation of the Policy Limitations Period. Therefore, the trial court properly granted summary judgment.
III. CONCLUSION
For the reasons stated, we affirm the judgment of the circuit court of Lake County.
Affirmed.
BYRNE and KAPALA, JJ., concur.
Notes
To be precise, plaintiffs husband was the Policy’s named insured. This distinction is irrelevant for present purposes.
Plaintiff argues that section 143.1 does not apply to “marine” insurance, and, therefore, that it does not apply here. However, section 143.1 excludes “ocean” marine insurance, and plaintiffs policy was for “inland” marine insurance. Thus, plaintiffs argument is unpersuasive. Morever, her argument is counterproductive. It is to plaintiffs advantage to have section 143.1 apply, because, as discussed, that section extends the time for filing suit. The problem for plaintiff is that, in her case, it does not extend it enough.
