In Docket No. 227720, plaintiffs, the Michigan Attorney General and the Michigan Department of Environmental Quality (collectively referred to as plaintiff), appeal as of right from an order granting summary disposition to defendant, Donald J. Harkins, which dismissed plaintiffs equitable action to restore wetlands that were altered in violation of a permit issued under Part 303 (Wetland Protection) of the Natural Resources and Environmental Protection Act (nrepa), MCL 324.30301
et seq.
In Docket No. 232934, defendant appeals as of right from the trial court’s order denying his request for attorney fees and costs for defending against plaintiff’s allegedly frivolous action. These cases were consolidated for purposes of
I. pacts and procedure
In 1987, defendant applied for a permit to fill certain portions of his lakefront lot, which measured approximately one-tenth of an acre, for the creation of a beachfront. Plaintiff denied defendant’s original permit application, and defendant appealed that decision. While his appeal was pending, defendant accepted plaintiff’s offer for a more limited permit, which was issued on
On August 28, 1990, plaintiff investigated a report that defendant had developed his property in violation of the modified permit. Defendant met with John Jurcich of the Department of Natural Resources, who concluded in his report that the work appeared to be within the guidelines of the modified permit. Despite Jurich’s conclusion, on August 8, 1991, plaintiff issued a cease and desist order against defendant, alleging that defendant’s work on his property did not conform with what was authorized by the modified per mit. The order prompted a criminal prosecution against defendant under the provisions of the former Wetland Protection Act, MCL 28.714, and the Inland Lakes and Streams Act, MCL 28.1951 et seq. On April 4, 1992, a district judge dismissed the criminal action. Plaintiff did not appeal this dismissal.
On March 28, 1996, plaintiff filed this action seeking an injunction requiring defendant to restore the wetlands and lake bottom and alleging that defendant filled or dredged the wetlands in violation of the modified permit. Plaintiff also requested civil fines. Defendant eventually moved for summary disposition. 2 On April 12, 2000, the trial court issued an opinion and order granting defendant summary disposition of plaintiff’s action under MCR 2.116(C)(10) (no genuine issue of material fact) and MCR 2.116(C)(7) (statute of limitations), and dismissing plaintiff’s complaint. Defendant subsequently filed a motion for attorney fees and costs, claiming that plaintiff’s action was vexatious, lacked a factual basis, and was filed with the intent to harass. Following a hearing on October 26, 2000, the trial court denied defendant’s motion.
H. ANALYSIS
A. DOCKET NO. 227720: STATUTE OF LIMITATIONS
The trial court held that the six-year period of limitations set forth in MCL 600.5813 barred plaintiff’s injunctive action to enforce the permit and restore the wetlands in question. Specifically, the trial court observed that defendant’s alteration of the wetlands was completed in 1988. This action was commenced eight years after the wetlands were altered. The trial court concluded that plaintiff’s equitable action was therefore barred by the six-year period of limitations. MCL 600.5813.
The applicability of a statute of limitations is a question of law that we review de novo.
Ins Comm’r v Aageson Thibo Agency,
Defendant argues on appeal that the six-year limitations period contained in § 5813 bars plaintiff’s claim. Judicial interpretation of a statute requires that effect be given to the plain meaning of the words used by the Legislature in the statute under review.
Federated Publications, Inc v City of Lansing,
Section 5813 provides, “ [a]ll other personal actions shall be commenced within the period of 6 years after the claims accrue and not afterwards unless a differ ent period is stated in the statutes.” 3 Black’s Law Dictionary (6th ed) defines “personal action” as follows: “In civil law, an action in personam seeks to enforce an obligation imposed on the defendant by his contract or delict; that is, it is the contention that he is bound to transfer some dominion or to perform some service or to repair some loss.” See also 1 Am Jur 2d, Actions, § 32, p 744 (“Personal actions are those brought for the recovery of personal property, for the enforcement of a contract or to recover for its breach, or for the recovery of damages for an injury to the person or property.”)
Here, plaintiff brought a civil action against defendant, an individual who allegedly failed to comply with portions of Part 303 of the nrepa. Plaintiff’s injunctive action to require defendant to restore the wetland comes within the meaning of a “personal action” as defined in § 5813, because it seeks to “repair some loss.” Actions brought by the Attorney General on behalf of government departments are deemed personal actions. See
Great Lakes Gas Transmission Co v State Treasurer,
Further, as both parties acknowledge, there is no applicable statute of limitations set forth in the nrepa. While MCL 324.30316 provides for the commencement of a civil action by the Attorney General to seek “appropriate relief, including injunctive relief” for permit violations, it does not state a period of limitations for bringing such actions. The Revised Judicature Act specifies that § 5813 is the general statute of limita
tions applying to “[a]ll other personal actions . . . unless a different period is stated in the statutes.” This Court has held that “a civil cause of action arising from a statutory violation is subject to the six-year limitation period found in § 5813, if the statute itself does not provide a limitation period.”
DiPonio Constr Co v Rosati Masonry Co, Inc,
Having determined that the six-year period of limitations applies to this cause of action, we must next determine when the claim accrued. The accrual provision in MCL 600.5827 provides that “the claim accrues at the time the wrong upon which the claim is based was done regardless of the time when damage results.” Here, plaintiff granted defendant the modified permit on March 15, 1988. Defendant completed his work on the property in 1988. Plaintiff filed the instant action on March 28, 1996. Plaintiff alleges that defendant violated the modified permit issued to him on March 15, 1988. Consequently, more than six years passed between the time the purported violation occurred in 1988 and the time the claim was filed on March 28, 1996.
We find unpersuasive plaintiff’s claim that the limitations period was tolled by defendant’s continuing wrongful acts. “The continuing-wrongful-acts doctrine states that ‘[w]here a defendant’s wrongful acts are of a continuing nature, the period of limitation will not run until the wrong is abated; therefore, a separate cause of action can accrue each day that defendant’s tortious conduct continues.’ ”
Jackson Co Hog Producers v Consumers Power Co,
Plaintiff further contends that defendant performed additional dredging in 1991 while attempting to comply with the cease and desist order issued by plaintiff on August 8, 1991. Plaintiff alleges that the dredging in 1991 was a “continuing wrongful act” that tolled the statute of limitations until 1997. We disagree.
Defendant was granted a permit to construct a ten-foot vide pathway. Defendant stated in his affidavit that in 1989 or
Defendant’s actions in 1991 conformed to the cease and desist order. Were we to adopt plaintiff’s argument, we would place defendant in the very peculiar position of having an otherwise time-barred claim revived solely because of defendant’s efforts to comply with a cease and desist order issued by plaintiff. The action taken in 1991 by defendant can hardly be termed a “wrongful tortious act,” but rather an attempt to comply with an order issued by plaintiff. Defendant was merely attempting to remedy an effect that occurred as a result of the installation of the pathway in 1988. Defendant’s actions in this regard may result in two possible outcomes. If defendant’s actions satisfied the cease and desist order, there would be no reason to pursue further proceedings of any type. Alternatively, if defendant did not comply with the order, plaintiff could have timely brought an action under the nrepa, or plaintiff could have pursued contempt proceedings for defendant’s failure to comply with the order. Plaintiff may not, however, do nothing for five years and then pursue otherwise time-barred claims dating back to 1988. Therefore, we conclude that defendant’s attempt to comply with the cease and desist order does not equate to a wrongful tortious act within the meaning of the continuing violation doctrine.
Plaintiff also contends that the statute of limitations should not bar its action because plaintiff did not sit idly by between 1988, when it issued the modified permit, and March 1996 when it filed the complaint in this action to restore the wetlands. Specifically, plaintiff claims that throughout that period defendant litigated plaintiff’s denial of the original permit, and plaintiff attempted to enforce its modified permit and obtain restoration of the wetlands in a criminal action brought in the district court. However, plaintiff did not have to wait until the Supreme Court denied defendant’s application for leave to appeal the
denial of the original permit before instituting a civil suit against defendant for violations of the modified permit. The fact that plaintiff filed a criminal action in the district court against defendant to enforce its permit underscores the fact that plaintiff could have timely filed a civil action against defendant for violating the modified permit. Plaintiff simply chose not to do so. There is no link between defendant’s attempts to have plaintiff’s denial of the original permit reversed and plaintiff’s failure to prosecute the instant action in a timely fashion. Cf.
Gebhardt v O’Rourke,
B. DOCKET NO. 232934: ATTORNEY FEES AND COSTS
Defendant appeals the denial of costs and attorney fees as sanctions for the pursuit of frivolous claims by plaintiff. We find no clear error in the trial court’s determination that defendant was not entitled to attorney fees and costs under either MCR 2.114 or MCR 2.625. A trial
Eveiy document of a party represented by an attorney must be signed by at least one attorney of record,
which constitutes a certification that: (1) the signor has read the document; (2) to the best of the signor’s knowledge, information, and belief after reasonable inquiry, the document is well grounded in fact and is warranted by existing law or a good faith argument for the extension, modification, or reversal of existing law; and (3) the document is not interposed for any improper propose, such as to harass or to cause unnecessary delay or needless increase in the cost of litigation. MCR 2.114(D). If a pleading is signed in violation of MCR 2.114(D), the party or attorney, or both, must be sanctioned. MCR 2.114(E). In addition, a party pleading a frivolous claim is subject to costs under MCR 2.625(A)(2). MCR 2.114(F). The frivolous claims provisions impose an affirmative duty on each attorney to conduct a reasonable inquiry into the factual and legal viability of a pleading before it is signed.
LaRose Market, Inc v Sylvan Ctr, Inc,
We cannot conclude that the trial court clearly erred when it determined that plaintiff’s legal position regarding the statute of limitations issue was meritorious. This is apparently the first time that the catch-all six-year period of limitations for “all personal actions” found in § 5813 has been applied to a case arising under the nrepa. In addition, plaintiff’s tolling arguments, although rejected by this Court and the trial court, were not so lacking in legal merit as to support a conclusion that plaintiff’s action was frivolous. Sanctions are not required and should not be imposed merely because the legal argument advanced by a litigant is rejected by the court. Where, as here, there is no developed case law mandating a particular result, sanctions under MCR 2.114 and MCR 2.625 are not warranted.
III. conclusion
In sum, the trial court properly granted summary disposition on the ground that the six-year period of limitations in MCL 600.5813 barred plaintiff’s action. Further, we find no clear error in the trial court’s decision that defendant was not entitled to attorney fees and costs. We affirm the trial court’s order granting defendant summary disposition and affirm the trial court’s order denying defendant costs and attorney fees.
Affirmed.
Notes
Defendant also raises various issues regarding the constitutionality of the nrepa, which were never addressed by the trial court. We decline to consider defendant’s constitutional claims “because this Court’s review is limited to the record developed by the trial court. ...”
Harkins v Dep’t of Natural Resources,
The trial court previously granted defendant summary disposition on January 15, 1997, on the ground that plaintiff filed an untimely brief in opposition to defendant’s motion for summary disposition. This Court reversed the dismissal as “too harsh a remedy” and reinstated plaintiff’s action in Attorney General v Harkins, unpublished opinion per curiam of the Court of Appeals, issued July 7, 1998 (Docket No. 202323).
Section 5813 applies “equally to all actions whether equitable or legal relief is sought.” MCL 600.5815.
To the extent that
Preserve the Dunes, Inc v Dep’t of Environmental Quality,
