73 W. Va. 449 | W. Va. | 1914
The decree appealed from dismissed on demurrer plaintiff's original and amended bills, which sought foreclosure of its alleged mechanic’s or material-man’s lien for terra cotta furnished the Moore Construction Co., principal contractor, in the construction of an office building for and under a contract with Alderson and Stephenson, owners, situated in the City of Charleston.
The alleged lien, a copy of which is exhibited with the original bill, and vouched for the truth of the allegations thereof, purports a contract by plaintiff with the Moore Construction Co., principal contractor, not with the owners, and there is also exhibited with the bill a copy of said contract. The bill also alleges that said material was furnished in pursuance to such contract with said contractors, and whereby plaintiff contracted to provide all the material and perform all the work for the delivery of the terra cotta f. o. b. its plant in New York, with freight allowed to Charleston, West Virginia ; and the- Moore Construction Co. thereby agreed to make payment for said material monthly on or before the 20th of each and every month for the material shipped the preceding month to the amount of 85% of the value thereof, final payment to be made within thirty days after the final shipment of the material contracted for.
■ And after setting forth the alleged failure of the Moore Construction Co., to make payments in accordance with the contract, and the subsequent negotiations by plaintiff’s presi
Prom a copy of the alleged lien exhibited with the bill it appears that the first item or shipment was on June 17, the last items, delivered, October 17, followed by three items, one of October 17, and two of October 19, all marked opposite, “not used”, the year nowhere appearing therein, but the bill alleges the year 1910.
The affidavit of the president to the account was taken in New York, December 19, 1910, and the certificate of the clerk of the county court of New York, as to the official character of the officer taking the affidavit, is dated December 22, 1910, and the return thereon shows service of the account and notice on Alderson and Stephenson, on December 20, 1910, the affidavit thereto appearing to have been made before the officer December 27, 1910; the exact date of the filing in the clerk’s office nowhere appearing. There is here apparent conflict, for if the account and notice were in New York on December 22, 1910, the date of the clerk’s certificate attached, it could
We have already decided that documents, exhibited with a bill, vouching the truth of the allegations thereof, are controlling in case of discrepancy. Houston Lumber Co. v. Railway Co., 69 W. Va. 683; Board of Education v. Berry, 62 W. Va. 433; Richardson v. Ebert, 61 W. Va. 523; Loar v. Wilfong, 63 W. Va. 306; Phillips & Sons v. Roberts, 26 W. Va. 783; Lockhead v. Berkeley Springs W. & I. Co., 40 W. Va. 553, 556. Observing this rule we would have to sustain the ruling of the court below on the demurrer to the original bill, for on the face of the account and notice, and' treating October 19, as the date of the last delivery of material, and December 20, as the date of service on the owners, service was not had on them, nor delivery of the duplicate thereof to the county clerk, until more than sixty days after plaintiff ceased to furnish the material under the contract, wherefore the lien was invalid on its face and in fact. By the very terms of the statute, section 3, chapter 75, Code 1906, neglect or failure of the material-man to notify the owner within thirty five days after he has ceased to furnish material “shall release the owner from all responsibility, and his property from all lien for any item therein done or furnished prior to the said notice.” Nor would such lien be good as upon a contract with the owner for said material under section 2, chapter 75, Code 1906, for by section 4 of said chapter, “Every lien provided for by the second and third sections shall be discharged unless the person desiring to avail himself thereof shall, within sixty days after he ceases to labor on, or furnish material or machinery for such building or other structure, file with the clerk * '* * * a just and true account of the amount due him, after allowing all credits,” &c.
By the amended bill, however, plaintiff undertook by allegation to correct these alleged errors in dates, and it is insisted that these alleged errors in dates do not invalidate the lien, and that the correct dates can be shown in pleadings and proof. For this proposition the following authorities are cited and relied on. 27 Cyc. 201, and cited cases; Treusch v. Shryock, 55 Md. 330; Johnson v. Otto, 105 Iowa 605; St. Croix Lumber Co. v. Davis, 105 Iowa 27; Union Trust Co. v. Casserly, 127
Accepting for the present the correctness of this proposition, let us see whether the amended bill presents a case for its proper application. The account and notice, filed with the owner, was sworn to by the plaintiff's president; the bill is unsworn to. The amended bill alleges that the dates given in the account filed, except as to the last four car loads, are the dates of the shipments, not the dates of the delivery of .the material in Charleston. By the terms of the contract the material was to be delivered f. o. b. cars at plaintiff’s- plant, with freight allowed to destination. Of the last four loads it is alleged that one was shipped October 15th, two- October 17th, one October 19th, 1910; that these four loads were shipped not to the contractor but to plaintiff’s own order at Charles*ton; that the load of October 15th was not in fact delivered to the Moore Construction Company until October 28th; and that one of the loads of October 17th was likewise not delivered to said company until October 28th; that the remaining load of October 17th, and the one -of October 19th, were never accepted by the construction company, because, as this bill alleges, before the shipment of said four car loads of material, said company ‘ ‘had failed and refused to make the payments as required by said contracts” and because “said company and the said Alderson and Stephenson * * * finally refused to comply with their contract of November 17th, 1910, and” because “said company * * * finally refused to accept said material on said date, as fully set forth in paragraph 6 of plaintiff’s bill of complaint.” Wherefore, it is further alleged in the concluding paragraph of the amended bill, plaintiff “ did not cease to perform labor and deliver materials to said Moore Construction Company under said contract with it and said Alderson and Stephenson until November 17th, when it was finally advised by the Moore Construction Company that it would not accept said material. ’ ’
Going back to the sixth paragraph of the original bill, to
It is apparent that if we treat October 28th as the date of delivery of the last material that went into the construction of the building, still the account and notice would not have been delivered to the owners within thirty five days thereafter, for the time which elapsed between October 28th and December-20th, the date of said service, was fifty three days, and as a lien of a sub-contractor,- therefore, it was and is invalid, as to the owner, by the force of the statute. But upon the theory of a contract with the owner on October 17th, and delivery on October 28th, the lien for the material actually delivered, and which actually entered1 into the construction of the building, if actually delivered on October 28th, would have been filed in the clerk’s office and recorded in time. But for reasons to be hereinafter given we are unable to agree with counsel in their interpretation of the account and notice filed, and the allegations of the original and amended bills, that plaintiff had any such contract with the owner for the furnishing of said material.
The general rule, that there can be no lien for material furnished a contractor not used and incorporated in the building or structure, is conceded. This proposition is affirmed in our cases of Cushwa v. Improvement L. & B. Ass’n., 45 W.
Assuming these exceptions to be established by the authorities cited, is a case here presented for their proper application? We do not think so. As to the first of these exceptions, it is nowhere alleged in the original or amended bills that the owner refused to accept or use the materials, nor is there any allegation, specifically, or by implication, charging that the contractor refused to accept or use the material called for by the contract. The allegation that the Moore Construction Company notified plaintiff that unless the terra cotta was' delivered at once it would complete the building with other material, and that the two car loads not delivered or used were never accepted by said company, and the reasons given in the amended bill why plaintiff refused to comply with its contract, are not sufficient to bring the case within this exception to the general rule. On the contrary we think these and other allegations of the bill clearly imply a demand for the delivery of the material, and a request that the same might be furnished and used in the construction of the build
Nor is a case presented for the application of the second alleged exception. In the case, of Howes v. Reliance Wire-Works Co., supra, relied on, the contract was made directly with the owner, for a wire enclosure for an elevator to be made and installed in the building. The controversy was between the purchaser of the property, who had notice of. the contract and purchased subject to all liens and claims of liens thereon. The contractor ■ tendered performance of the contract which was refused by the purchaser, and he forbade him putting the structure in the building. No such case is presented here. Quite the contrary.
Nor have we here a case coming under the supposed third exception. The claim here is not for work done on material at the yard or shop of the contractor,, under a contract with the owner; the contract here is that of a sub-contractor for the finished product, and who has declined to deliver the material contracted for or to suffer it to go into the construction of the building, except upon new term® and conditions. So we' hold that our ease has not been brought under any of these alleged exceptions.
Lastly, as to the theory of plaintiff of a new contract with the owner, as of October 17th, 1910. The only foundation for this theory is the fact alleged, that at that time the owners promised to pay $5,000.00, for the Moore Construction Company, on the construction company’s contract, by a given date, on condition that the material would be delivered and allowed
■ But it is contended that plaintiff was entitled to a personal decree, notwithstanding it may have been rightfully denied a mechanic’s lien, and that the bill was maintainable for relief on this ground, on the theory that having acquired jurisdiction for one purpose a court of equity will go oh to give complete relief. For this proposition our case of United States Blowpipe Co. v. Spencer, 40 W. Va. 698, and 27 Cyc. 432, Rockel on Mechanics’ Lien, section 284, and Johnston v. Bunn, 108 Va. 490, are cited and relied on.
The proposition stated assumes, necessarily, that jurisdiction in equity' has been acquired upon some ground of equit
For the foregoing reasons the decree below will be affirmed.
Affirmed.