delivered the opinion of the court:
This is a suit brought by the Atlantic Contracting Company against the United States for the sum of $709,797.02, which sum includes the sum of $450,000, anticipated profits on that part of the contract unperformed. The plaintiff,, however, in the course of these proceedings abandoned its claim for anticipated profits and only asserts its claim to the sum of $259,743.21, which it claims is the amount due it for work done and material furnished to the Government.
The plaintiff is a corporation. At the time the contract in suit was entered into John F. Gaynor and Benjamin D. Greene owned all the stock of the corporation. The number of shares of stock held by Gaynor and Greene was 5,985. The 15 shares of stock were issued to relatives and friends of Gaynor and Greene for organization purposes. It then appears that Gaynor and Greene were the owners of the corporation — were in effect the corporation.
The contract in suit was for the benefit of and was in fact procured by John F. Gaynor, the president of the plaintiff corporation, and Benjamin D. Greene, the owner of about one-half of the capital stock of the corporation. On April 12, 1906, in the United States District Court of the Eastern Division of'the Eastern District of Georgia, John F. Gaynor and Benjamin D. Greene were convicted for conspiracy to defraud; for conspiracy in presenting false claims against the Government, and for embezzling from the Government the sum of $575,749.90, $845,000 of which sum was the amount paid to the plaintiff under the contract in suit, this sum having been paid to plaintiff through the agency of Capt. Oberlin M. Carter, the engineer in charge of the work under this contract. The said Gaynor and Greene, in pursuance of the verdict against them, were sentenced each to a term of four years in the United States penitentiary at Atlanta and fined each in the sum of $575,749.90. Oberlin M. Carter, captain in the Corps of Engineers, United States Army, was tried by a court-martial for his participation with Gaynor and Greene in the conspiracy to defraud the Government, and for his participation with Gaynor and Greene in the embezzlement of the money of the Government which was paid to Gaynor and Greene by virtue of and under the contract in suit. Said Carter was convicted of the charges and sentenced to be dismissed from the Army of the United States and to be imprisoned in the United States penitentiary. From the recital of the above facts it appears that Gaynor, Greene, and Carter have been con-
It seems to be admitted that no recovery can he had upon. the contract because it is tainted with fraud. But the plaintiff insists that this is not an obstacle to its recovery upon a quantum meruit, and it proceeded to prove the value of the work done by it and for which it seeks to recover. The plaintiff relies upon the case of Crocker v. United.States,
The United States has recovered from Carter a part of the money embezzled by him. United States v. Carter,
While the plaintiff seeks to recover upon a quantum meruit, yet it is apparent from the evidence that its alleged rights spring directly from the contract, which is illegal and fraudulent. No court will lend its assistance in any way to carry out the terms of an illegal contract, nor will the court enforce any alleged rights directly springing from such contract. McMullen v. Hoffman,
It appears from the facts found that the defendant never accepted the work of the plaintiff. On the contrary, the defendant insisted that the work did not meet the requirements of the specifications, and payment was refused on that ground. The fact that the work performed by the plaintiff and the materials furnished by it were used by the defendant does not of itself create a liability. The acceptance of such work and materials must have been voluntary. In this case the defendant, from the very nature of the work done, was
For the reasons above given the petition of the plaintiff must be dismissed. It is so ordered.