Atlanta Flooring Design Centers, Inc. v. R. G. Williams Construction, Inc.Atlanta Flooring Design Centers, Inc. v. R. G. Williams Construction, Inc.
Lead Opinion
The award rendered by the arbitrator[s] shall be final and binding on the parties and judgment upon the award may be entered in any court of competent jurisdiction. Contractor and Subcontractor hereby expressly agree not to challenge the validity of the arbitration or the award.
After a dispute was submitted to arbitration, and the arbitrator rendered an award, AFDC filed a motion pursuant to
“The [GAC] requires a trial court to confirm an award upon the timely application of a party to the award, unless one of the statutory grounds for vacating or modifying the award is established.” Greene v. Hundley,
acknowledge [d] the fundamental principle that parties have the right to freely contract, [but recognized that] courts may not enforce a contractual provision which contravenes the statutory law of this statе [,] . . . [and concluded that] the [GAC] does not permit contracting parties who provide for arbitration of disputes to contractually expand the scope of judicial review that is authorized by statute.
Id. (citation and punctuation omitted). Similarly, we conclude that the GAC does not permit contracting parties who provide for arbitration of disputes to contractually waive or eliminate a party’s right to apply to a court to vacate or modify an award on the statutory grounds set fоrth in
“Because [the GAC] closely tracks federal arbitration law, we look to federal cases for guidance in construing our own statutes.” Brookfield Country Club,
Accordingly, we find that the contract provision stating that the parties “expressly agree not to challenge the validity of the arbitration or the award” conflicts with and frustrates Georgia public policy as exрressed in the GAC, and is void and unenforceable, to the extent it prevents AFDC from challenging the validity of the arbitration or the award by filing a motion under
Judgment reversed.
Concurrence Opinion
concurring specially.
Although I agree with the result reached in this appeal, I write separately to emphasize both the way this court views arbitration agreements generally and the uniqueness of the question presented in this case — that is, whether two commercial parties may agree to waive the right to contest an arbitration award on the limited grounds listed in
In this case, claimant Atlanta Flooring and Design Centers, Inc. (“AFDC”) filed an arbitration petition against R. G. Williams Construction, Inc. (“Williams”), a general contractor which had refused to pay AFDC as the flooring subcontractor on the ground that AFDC had delayed completion of its subcontract. AFDC filed a motion to vacate on the grounds that the arbitrator had overstepped his authority and manifestly disregarded the law when he awarded Williams liquidated damages. Williams moved to dismiss AFDC’s motion to vacate on the ground that in their agreement to arbitrate, the parties had “expressly agree [d] not to challenge the validity of the arbitration of [any] award” made. AFDC appeals from the trial court’s grant of Williams’s motion to dismiss AFDC’s motion to vacate the award.
As a preliminary matter, it bears repeating that “[i]n enacting the GAC, the General Assembly estаblished a clear public policy in favor of arbitration.” Order Homes v. Iverson,
In Brookfield Country Club v. St. James-Brookfield, LLC,
First, the Second Circuit’s decision in Hoeft v. MVL Group,
An agreement thаt contemplates confirmation but bars all judicial review presents serious concerns. Arbitration agreements are private contracts, but at the end of the process the successful party may obtain a judgment affording resort to the pоtent public legal remedies available to judgment creditors. In enacting§ 10 (a) , Congress impressed limited, but critical, safeguards onto this process, ones that respected the importance and flexibility of private dispute resolution mechanisms, but at thе same time barred federal courts from confirming awards tainted by partiality, a lack of elementary procedural fairness, corruption, or similar misconduct. This balance would be eviscerated, and the integrity of the arbitration process could be compromised, if parties could require that awards, flawed for any of these reasons, must nevertheless be blessed by federal courts. Since federal courts are not rubber stamps, parties may not, by private agreement, relieve thеm of their obligation to review arbitration awards for compliance with§ 10 (a) .
Id. at 64-65. Similarly, I believe that the parties to this arbitration agreement, who must turn to a Georgia court in order to confirm an arbitration award, were not empowered to reliеve the Georgia courts of their obligation to review the same kind of award for the fundamental flaws identified in
Second, I wish to emphasize, as the Supreme Court of Georgia has repeatedly done, that the grounds for vacatur set out in
Third, our result merely reverses the trial court’s grant of Williams’s motion to dismiss AFDC’s motion to vacate the arbitration award, such that AFDC’s motion to vacate remains pending below. It would be a misreading of оur result, moreover, to infer any conclusion from it as to the merits of that pending motion. See, e.g., Berger v. Welsh,
Because I believe these matters require further explanation and require a slightly different analysis, I concur in the judgment only.
Notes
Although Hoeft construes the Federal Arbitration Act (FAA), both the FAAand the GAC contain a provision detailing the limited grounds for challenging an arbitration award. See
See Court of Appeals Rule 33 (a) (“an opinion is physical precedent only with respect to any Division of the opinion for which there is a concurrence in the judgment only or a special concurrence without a statement of agreement with all that is said”).