The ATCHISON, TOPEKA AND SANTA FE RAILWAY COMPANY, Petitioner-Appellant, v. The PUBLIC UTILITIES COMMISSION OF the STATE OF COLORADO, the City and County of Denver, the Denver & Rio Grande Western Railroad Company, the Burlington Northern Railroad Company, the City of Arvada, the City of Colorado Springs, State Department of Highways-State of Colorado, the Union Pacific Railroad and the City of Westminster, Respondents-Appellees.
No. 87SA102.
Supreme Court of Colorado, En Banc.
Oct. 31, 1988.
Rehearing Denied Nov. 28, 1988.
762 P.2d 1336
VOLLACK, Justice.
The district court‘s dismissal order is vacated. The case is remanded to the district court for reinstatement of the charges and further proceedings consistent with this opinion.
Duane Woodard, Atty. Gen., Charles B. Howe, Chief Deputy Atty. Gen., Richard H. Forman, Sol. Gen., Eugene C. Cavaliere, Deputy Atty. Gen., Denver, for respondent-appellee Public Utilities Com‘n.
Stephen H. Kaplan, City Atty., John L. Stoffel, Jr. Asst. City Atty. Denver, for respondent-appellee City and County of Denver.
VOLLACK, Justice.
The Atchison, Topeka and Santa Fe Railway Company (Santa Fe) appeals the order of the Denver District Court affirming the decision of the Public Utilities Commission (Commission) to impose upon Santa Fe a fee of $572,000 as its share of the cost of rebuilding the 8th Avenue viaduct (viaduct). Santa Fe argues that the Commission failed to comply with the statutory requirements of
I.
The viaduct was constructed in 1936 to serve east-west pedestrian and motor traffic between Vallejo and Mariposa streets. The two-lane viaduct provided a separate grade crossing above railroad tracks and facilities owned by Santa Fe, Burlington, and the Denver and Rio Grande Railway Co. (Rio Grande).1 The viaduct was condemned in November 1983, and traffic was rerouted primarily to the 6th Avenue viaduct. On December 31, 1983, Denver applied to the Commission for authority to demolish and rebuild the viaduct. Santa Fe, Burlington, and Rio Grande were granted permission to intervene in the application proceedings, and hearings were held in January 1984.2
On February 7, 1984, the Commission granted Denver‘s application for permission to rebuild the viaduct, and assessed costs of $572,000 against Santa Fe based on the recommendation of John Baier, the Commission‘s transportation engineer. After exhausting its administrative remedies, Santa Fe appealed the Commission‘s decision to the Denver District Court. The district court affirmed the decision of the Commission on February 17, 1987, and Santa Fe appealed to this court pursuant to
II.
The January 1984 hearings were the first to be conducted pursuant to House Bill No. 1569, codified as
John Baier, the Commission‘s transportation engineer, developed a new methodology in an attempt to comply with
In this base case, Baier assumed that one public authority desired to build a road that intersected one set of railroad tracks. He stated that the road could be built on ground level or “at-grade,” above grade by means of a viaduct or overpass, or below grade by means of a tunnel or underpass. He then compared the benefits the public authority and the railroad receive from construction of an above grade road to the benefits received from construction of an at-grade railroad crossing. He observed that construction of a grade separation construction project was mutually beneficial to the public authority and the railroad because it eliminated any chance of collisions between trains and road traffic, disruption of train or traffic patterns, release of hazardous materials, and delay of emergency road vehicles. The railroad received additional benefits from construction of an above grade road, said Baier, including eliminating the possibility of damage to switches, tracks and equipment; decreasing the possibility of train delay or derailment; avoiding cost of installing and maintaining at-grade safety devices; and maintaining the railroad‘s “freedom of operation.”6 He stated: “It is extremely difficult to measure and quantify these benefits [to the railroad and the public authority]. However, the benefits are shared equally.”
Baier then weighed the responsibility that the railroad and the public authority had for the need for construction of a grade separation construction project. He surmised that a grade separation construction project “would not be required if either the railroad or the roadway did not occupy the same right of way.” Accordingly, he concluded that in the base case the railroad and the public authority bore equal responsibility for the need for con-
In measuring the benefit under
III.
Review of the Commission‘s decisions is limited to three concerns: whether the Commission has regularly pursued its authority; whether its decisions are just and reasonable; and whether its conclusions are in accordance with the evidence.
Factual determinations of the Commission are entitled to considerable deference. G & G Trucking Co. v. Public Util. Comm‘n, 745 P.2d 211, 216 (Colo. 1987). A reviewing court must view the evidence in the light most favorable to the Commission. Peoples Natural Gas Div. v. Public Util. Comm‘n, 193 Colo. 421, 427, 567 P.2d 377, 381 (1977). It may not disturb those factual determinations that are supported by substantial evidence in the record. Acme Delivery Serv. v. Cargo Freight Sys., 704 P.2d 839 (Colo.1985). Nor may a reviewing court substitute its judgment for that of the Commission. Public Serv. Co. v. Public Util. Comm‘n, 644 P.2d 933, 940 (Colo.1982).
In determining whether to disturb the factual determinations of the Commission, the reviewing court must search the record for evidence favorable to the Commission, North Eastern Motor Freight, Inc. v. Public Util. Comm‘n, 178 Colo. 433, 437, 498 P.2d 923, 925 (1972), because findings may be express or implied from a reading of the record as a whole, see Aspen Airways, Inc. v. Public Util. Comm‘n, 169 Colo. 56, 62, 453 P.2d 789, 792 (1969). Findings may not be set aside merely because the evidence before the Commission is conflicting or because more than one inference can be drawn from the evidence. Morey v. Public Util. Comm‘n, 629 P.2d 1061, 1068 (Colo.1981). Finally, whether an order is supported by substantial evidence is a question of law. Public Util. Comm‘n v. Northwest Water Corp., 168 Colo. 154, 169-70, 451 P.2d 266, 273-74 (1969). See generally Colorado Mun. League v. Mountain States Tel. & Tel. Co., 759 P.2d 40, 44 (Colo.1988). With these principles in mind, we turn to Santa Fe‘s claims.
IV.
The essential question before us is whether the conclusions of John Baier, the Commission‘s transportation engineer, constitute substantial evidence upon which to base the Commission‘s findings. Santa Fe characterizes Baier‘s conclusions as mere assumptions, entitled to no evidentiary weight. The Commission characterizes Baier‘s conclusions as expert opinions entitled to substantial deference.
A.
Santa Fe argues that there was insufficient evidence to support the Commission‘s finding that Santa Fe and Burlington received any benefit whatsoever from construction of the viaduct because an at-grade crossing was neither in place nor proposed at the time of the application. Denver argues that an at-grade crossing was considered and rejected at the time of the application, and that the benefit Santa Fe received was being relieved of burdens related to construction of an at-grade crossing.
The record reveals that the option of constructing an at-grade crossing was considered and rejected at the time of the application to rebuild the viaduct. On January 19, 1984, John Stamm, Denver‘s director of design and construction engineering, testified that reconstruction of the viaduct was the “best alternative in all those being considered.” He testified that he would not recommend an at-grade crossing because it “would create a great deal of conflict, possible conflict, between train movements and the vehicular, and pedestrian, and bicycle traffic.” In addition, John Baier testified that the alternative of constructing an at-grade crossing is always considered when a grade separation construction project is proposed.
The Commission faced a choice of two alternatives that would permit traffic to enter and leave downtown Denver. It chose the alternative of constructing a viaduct after considering traffic, safety, and geographic distribution as required by
B.
Santa Fe argues that, even if it did receive a benefit from construction of the viaduct, there was no evidence to support the Commission‘s finding that the benefit derived by the affected railroads was equal to the benefit derived by Denver. Santa Fe raises two related arguments in support of this position. First, the Commission misapplied
1.
The General Assembly in enacting
2.
The Commission did not gather statistical or other empirical evidence of the benefit that affected railroads and Denver received from construction of the viaduct. Neither
C.
Santa Fe argues that there was no evidence to support the Commission‘s finding that the benefit to Santa Fe was equal to the benefit derived by Burlington. It claims that mere ownership of railroad tracks is not a sufficient basis to support the Commission‘s findings that construction of the viaduct would benefit Santa Fe and Burlington equally. Santa Fe points out that, on average, Burlington trains are almost three times longer than the average Santa Fe train, and run six times as often.9 If benefit to affected railroads under
John Baier testified at the January 20 hearing that he rejected the idea of basing measurement of benefit to Santa Fe and Burlington on volume of train traffic or revenue generated to the railroad. He said that Santa Fe and Burlington could change the terms of their contract to adjust the payments that each railroad was assessed by the Commission. He concluded that benefit to each railroad should be based on ownership of the tracks.
While a good case can be made that benefit to each railroad should be based on the number of trains or the revenue generated to each railroad, the Commission rejected this basis in favor of basing benefit on ownership of the tracks. Because each of these solutions was reasonable, we cannot substitute our judgment for that of the Commission. The Commission‘s findings were based on substantial evidence in the record. We therefore conclude that the Commission did not abuse its discretion in finding that Burlington and Santa Fe received equal benefit under
The order of the district court is affirmed.
ERICKSON, J., dissents.
ROVIRA and KIRSHBAUM, JJ., join in the dissent.
ERICKSON, Justice, dissenting:
I respectfully dissent. In my view there is no competent evidence in the record before us to support the commission‘s conclusions that the railroads and the City and County of Denver derive equal benefits from the viaduct, and that the assessment against Santa Fe and Burlington should be equally divided.
Although a reviewing court may not substitute its judgment for that of the PUC, it must determine whether there is competent evidence in the record to support the PUC‘s decision. RAM Broadcasting of Colorado, Inc. v. Public Utilities Comm‘n., 702 P.2d 746 (Colo.1985); Atchison, Topeka & Santa Fe Ry. Co. v. Public Utilities Comm‘n, 194 Colo. 263, 572 P.2d 138 (1977). Similarly, while the findings and conclusions of the commission are presumed to be valid, and must be reviewed in the light most favorable to the commission‘s decision, a PUC decision that is not supported by substantial evidence must be set aside. Home Builders Ass‘n v. Public Utilities Comm‘n, 720 P.2d 552 (Colo.1986).
Here, the commission concluded that Denver‘s benefits of increased traffic flow are equal to the railroads’ benefits of increased speed over a surface crossing and the elimination of auto-train accidents that might occur at a grade-level crossing. However, the commission‘s conclusion is based entirely on expert opinion testimony, primarily that of John Baier, Staff Transportation Engineer for the PUC. Baier‘s testimony is comprised only of assumptions and conclusions, without any statistical data or empirical observations to support his opinions. For example, he did not provide the commission with data concerning the frequency of auto-train accidents at an at-grade crossing, with data concerning the added time the railways would save by a viaduct crossing, or with data concerning the railways’ exposure to liability resulting from an at-grade crossing. In sum, Baier‘s “base case” methodology reaches the presumptive and unsupported conclusion that Denver and the railways benefit equally from the viaduct. Common sense dictates that the main benefit of the viaduct is better handling of traffic flow, a benefit to Denver only. Baier‘s testimony assumed equal benefits instead of attempting to actually measure, quantify or document the benefits to Denver and the railroads, and then weigh the benefits of each party against each other.
In my view, therefore, the commission acted arbitrarily when it relied on Baier‘s
Further, the commission disregarded a statutory directive when it allocated the cost assessment between Burlington and Santa Fe solely on the basis of track ownership.
Disregarding the plain meaning of
Because I believe that the commission abused its discretion by rendering decisions unsupported by competent and substantial evidence, I would reverse and remand to the district court with directions to return the case to the Public Utilities Commission for further proceedings consistent with this opinion.
I am authorized to say that JUSTICE ROVIRA and JUSTICE KIRSHBAUM join in this dissent.
