Associated Gas Distributors v. Federal Energy Regulatory Commission, the Peoples Gas Light & Coke Co., IntervenorsAssociated Gas Distributors v. Federal Energy Regulatory Commission, the Peoples Gas Light & Coke Co., Intervenors
Opinion for the Court filed by Circuit Judge SENTELLE.
The Federal Energy Regulatory Commission (“FERC” or “the Commission”) orders at issue require us to turn once again to certain aspects of the Commission’s Order No. 500, 52 Fed.Reg. 30,334 (1987),
record remanded sub nom. American Gas Ass’n v. FERC,
Certain pipelines, customers, and LDCs argue that the Commission’s “purchase deficiency” allocation mechanism is unlawful because it violates the filed rate doctrine. We agree and therefore set aside the orders. As a result, disposition of most of petitioners’ other claims is not essential to relieving them of burdens they claim are illegal. Nevertheless, because the Commission will undoubtedly attempt to revamp its passthrough policy in light of this decision, we will address a number of subsidiary issues which appear virtually certain to arise under any passthrough scheme.
I. Background
We recently summarized the genesis of the orders presented to us for review:
The Federal Energy Regulatory Commission embarked in the early 1980s on an ambitious program to restructure the natural gas industry along lines more competitive than it had traditionally followed. One of the major components of this program, the encouragement of natural gas pipelines to adopt an “open access” transportation policy, failed to pass muster when we reviewed it, because the Commission failed to show either that it had authority to impose, or that it could rationalize the imposition of, a few of its components. Associated Gas Distributors v. FERC,824 F.2d 981 (1987) (AGD). Because these components were inseparable from the whole, we vacated and remanded the Commission’s Order No. 436 for the agency to cure the defects we had identified. The Commission promptly, in Order No. 500, issued an “interim rule,” and undertook to issue a final rule when it had collected and analyzed certain information that it deemed essential.
AG A, at 141.
Unhappily, we found in AG A that Order No. 500 failed to comply with the mandate in AGD. We retained jurisdiction but remanded the record to the Commission for issuance of a final rule within sixty days. The statutory, regulatory and economic context in which the Commission undertook to implement its open-access transportation policy is set out in detail in this Court’s opinions in AGD and AG A. The pass-through mechanism is described in AG A, at 143-144. We refer to this background only as the need arises.
The Commission orders at issue implement the take-or-pay cost passthrough provisions of Order No. 500, with its “equitable sharing mechanism.” This pass-through policy is part of a larger attempt by FERC to spread the costs of the take-or-pay problem over the whole industry, at least insofar as the open-access transportation policy has aggravated the problem. The mechanism at issue here attempts to shift some of the costs to the customers; the crediting system in AG A, on the other hand, attempted to shift costs to the producers. Under the passthrough mechanism, the cost of buyouts and buydowns is shared between the pipeline and its customers. If a pipeline agreed to absorb between 25% and 50% of its take-or-pay costs, the pipeline would be permitted to recover an equivalent amount through a fixed charge. Such a pipeline would also be allowed an opportunity to recover the remaining costs through a volumetric surcharge on sales and transportation. Moreover, where the pipeline absorbed between 25% and 50% of the costs, the Commission established a rebuttable presumption that the remaining costs that the pipeline sought to pass on to its customers were prudently incurred. A pipeline customer could still challenge the pipeline’s prudence, but it took a chance in doing so — it would have to pay its pro rata share of 100% of the costs ultimately found to have been prudently incurred.
To allocate the buyout and buydown costs among customers, FERC proposed the imposition of a demand surcharge on each pipeline customer. Customers’ purchases of natural gas decreased sharply during the period from 1983 to 1986 and thereby exacerbated the pipelines’ problems. FERC therefore proposed to base the charge upon the customer’s “deficiency” of purchases during this period. This “purchase deficiency” was to be calculated by measuring the customer’s purchases in the “deficiency period” (1983-86) against its purchases in a prior “base period” (1981-82).
In October of 1987, after promulgation of Order No. 500, Tennessee Gas Pipeline Company (“Tennessee”) filed a settlement proposal to resolve a previous Section 4 rate filing. The proposal called for direct charge recovery of 50% of Tennessee’s reformation and buyout costs. Tennessee would absorb the remaining 50%. Tennessee also agreed to render a limited-term standby sales service. In addition, Tennessee proposed a 31 December 1989 “sunset date,” which limited the time for filing for recovery under the “equitable sharing mechanism,” rather than Order No. 500’s original sunset date of 31 December 1988 (which the Commission subsequently extended to 31 March 1989 in Order No. 500-F). Five competing settlement proposals were filed.
The Commission modified and approved Tennessee’s proposed settlement.
Tennessee Gas Pipeline Co.,
On rehearing in May of 1988, FERC altered Tennessee’s cost-allocation formula on the grounds that the formula in Order No. 500 relied solely on the “purchase deficiency” method, whereas the Tennessee formula combined the purchase deficiency method and a method based on the customer’s annual quantity limitations.
Tennessee Gas Pipeline Co.,
Various petitioners filed for review in this Court on and after 27 May 1988.
In June of 1988, Tennessee filed tariff sheets that incorporated a 1989 sunset date. In July of 1988, the Commission accepted the tariff sheets and allowed Tennessee to begin direct billing its customers as of 1 July 1988 (subject to refund).
Tennessee Gas Pipeline Co.,
II. Analysis
A. Filed Rate Doctrine
The Commission has allowed Tennessee to directly bill its customers surcharges proportional to the customers’ purchase reductions during the 1983-86 “deficiency period,” reductions calculated on the basis of the customers’ purchases from Tennessee during the “base period” of 1981-82. According to petitioners, the charges constitute a retroactive change in rates without advance notice and therefore violate the filed rate doctrine as expressed in
Arkansas Louisiana Gas Co. v. Hall,
The Commission claims that
Columbia Gas
is inapposite because the pricing mechanism at issue here does not really affect rates retroactively; rather, “what is involved here is simply a legitimate Commission decision to allocate
current
take-or-pay expenses in a fair and equitable fashion consistent with the Commission’s broad discretion.... All that the agency has done here is to utilize a calculation of a customer’s past purchasing patterns in order to allocate its share of a
current
expense.” Brief for Respondent
Petitioners respond that characterizing the costs as “current” is disingenuous because “[t]he level of the surcharge to each Tennessee customer is determined without reference to current or future purchases or service levels.” Joint Reply Brief of Certain Petitioners and Intervenors in Support of Petitioners in Opposition to Orders Under Review at 5-6 (“Joint Reply Brief”). Petitioners do not argue that the Commission is prohibited from using accurate historical data in the course of determining future rates; rather, the Commission may not impose a direct surcharge geared to past gas purchases.
The Commission also argues that Tennessee’s customers had sufficient notice of deficiency billing from the language of Order No. 380.
See
Order No. 380, FERC Stats. & Regs. ¶ 30,571 [Regulations Preambles 1982-1985] (1984),
aff'd in part, remanded in part sub nom. Wisconsin Gas Co. v. FERC,
We agree with petitioners that the purchase allocation mechanism and its direct charge violate the filed rate doctrine. The Commission’s attempted distinction of
Columbia Gas
is unpersuasive. Under
Columbia Gas,
the relevant question is not which costs are “current” and which are “past.” Rather, the appropriate inquiry seeks to identify the purchase decisions to which the costs are attached. After making this inquiry, we have little doubt that the mechanism at issue violates the filed rate doctrine. Indeed, the Commission now even forces past customers who no longer purchase
any
gas from Tennessee to pay their share of the take-or-pay liability.
See United Gas Pipe Line Co.,
The Commission’s assertion that Order No. 380 provided sufficient notice is equally unavailing. Order No. 380 post-dated the entire base period and half of the deficiency period. The Commission can perhaps assume that petitioners have some acquaintance with regulatory changes in the natural gas industry, but it cannot require them to be clairvoyant. Upon consideration of the text of Order No. 380, we conclude that FERC’s indication that carrying charges on prepayments “may require special consideration” is delphic at best; in any event, the reference is irrelevant in light of the Commission’s explicit statement in Order No. 380 that it was making no final disposition of the issue.
The Commission asserts that a significant factual difference between Columbia Gas and the present case is that the direct charge in Columbia Gas was for gas taken whereas the direct charge at issue here is for gas not taken. This, of course, is only one way of looking at the basis of the charge in the present case. As a mathematical fact, the charge is as much a result of gas taken during the base period as it is of gas not taken during the deficiency period. In other words, the volume of gas that actually generates the specific charge, being the difference between base-period gas taken and deficiency-period gas not taken, is actual gas taken.
In any event, even if we were to recognize the difference asserted by the Commission, that recognition would not save the Commission because both the
Columbia Gas
orders and the mechanism before us undermine the purpose of the filed rate doctrine. As we said in
Columbia Gas,
“[providing the necessary predictability is the whole purpose of the well established ‘filed rate doctrine’.... ”
Columbia Gas,
The Commission’s attempt to analogize the passthrough mechanism to minimum bills is also misplaced. The two are similar insofar as they are both fixed charges imposed without reference to current purchases of gas, and can be avoided only by leaving the pipeline entirely through an abandonment proceeding or by a change of tariffs under Sections 4 or 5.
1
The pass-through mechanism differs from the minimum bills, however, in one crucial respect: the aggregate amount charged is calculated on the basis of past purchasing decisions, whereas minimum bills are generally based on current contract entitlement.
See
Order No. 380, FERC Stats. & Regs. [Regulations Preambles 1982-1985] ¶ 30,571 at 30,958-60 & n. 5 (1984) (eliminating minimum commodity bill provisions which had been generally based on a “specified percentage of [the customer’s] contract entitlement”). The Commission calls our attention to its own dicta concerning an earlier minimum bill based in part on historical data.
See Atlantic Seaboard Corp.
(Opinion No. 523), 38 FPC 91, 93-94 (1967),
aff'd,
B. Title I
Title I of the Natural Gas Policy Act (“NGPA”), 15 U.S.C. §§ 3301-3333, establishes price ceilings (“maximum lawful prices” or “MLPs”) for first sales of natural gas. Section 504(a) of Title V of the NGPA, 15 U.S.C. § 3414(a), makes it unlawful for any person to sell natural gas at a first sale price in excess of any applicable MLP. All parties before us assume, and we do not doubt, that the wellhead sales in question were first sales. Under Section 601(b) of Title VI, 15 U.S.C. § 3431(b), payments made for natural gas that are not in violation of Title I are deemed just and reasonable, and they may be passed through, absent a showing of fraud or abuse; conversely, the Commission treats amounts not found to be just and reasonable under Section 601(b) as per se imprudent and therefore ineligible for pass-through.
Petitioners argue that this statutory structure means that “all forms of consideration received by the producer-seller must be added together to determine whether the total
value
received exceeds the MLP.” Joint Initial Brief of Certain Petitioners and Intervenors in Support of Petitioners in Opposition to Orders Under Review at 57 (emphasis in original). Petitioners complain that the Commission has allowed two loopholes to the MLP. First, in its 1985 policy statement,
Regulatory Treatment of Payments Made in Lieu of Take-or-Pay Obligations,
FERC Stats. & Regs. ¶ 30,637 (1985), the Commission indicated that take-or-pay buyout and buydown costs would not be considered part of a pipeline’s payments for gas, and therefore would not violate Title I. Second, in July of 1988, the Commission allegedly opened the second loophole by deciding in
ANR Pipeline Co. v. Wagner & Brown,
Petitioners seek to close the first of these asserted loopholes by having the Commission add together (1) buyout and buydown payments made for gas not taken under a contract and (2) all payments made for gas taken. The sum would be divided by the amount of gas actually taken, and petitioners would find a violation of the NGPA to the extent that the resulting “average price” exceeded the MLP. Petitioners argue further that the Commission’s reliance on a policy statement in approving a passthrough of Tennessee’s buyout and buydown costs violates
Pacific Gas & Electric Co. v. FPC,
The Commission responds that the principles of its
Wagner & Brown
decision excluding nonrecoupable prepayments from the definition of “payments for gas” and therefore from Title I were confirmed in
Diamond Shamrock Exploration Co. v. Hodel,
Buyout and buydown costs fall within the same rule, according to the Commission, because “they also involve the situation in which payments are made to avoid obligations to buy gas, not to pay for gas.” Brief for Respondent
Petitioners attempt to distinguish Diamond Shamrock on the grounds that Diamond Shamrock addressed the issue of whether prepayments are subject to royalty payments, at least where the government is the claimant of the royalties. In petitioners’ view, the Shamrock court’s holding — that royalties are due only on gas actually produced and taken, not on prepayments — is irrelevant to the Title I question before us. Petitioners also claim that Kaiser-Francis relied on the flawed Wagner & Brown theory without making an independent judgment on the Title I question and should be rejected. Finally, petitioners argue that FERC misperceives their Title I attack: rather than being a situation where no gas has changed hands at all, as FERC would describe it, the problem arises precisely because the purchaser has taken some volumes of gas but has also made additional payments for the gas it could not take. Thus, the “sale” and the “prepayment” are part of the same contractual event. Petitioners assert that the prepayment (or the cost of buyouts and buy-downs) “plainly relates to the volumes delivered to Tennessee by that seller pursuant to that contract, and to none other.” Joint Reply Brief at 32. Those volumes are therefore necessary, petitioners conclude, “in order to determine whether the total payment per unit of volume received exceeds the maximum lawful price (MLP).” Id. at 33.
We conclude that the Commission’s position on this issue, as evidenced by the
Wagner & Brown
proceedings, is final; we do not believe that the Commission has
We find nothing in petitioners’ argument that warrants such a conclusion. The Fifth Circuit’s decision in
Callery Properties,
C. Tennessee’s Settlements with Equitable and Columbia
Equitable Gas Company (“Equitable”) and Columbia Gas Transmission Corporation (“Columbia”) are customers of Tennessee. Their petitions involve their Commission-approved take-or-pay settlement agreements with Tennessee. Columbia seeks “credit” for payments that it has already made to Tennessee, pursuant to its agreement, in order to reimburse Tennessee for take-or-pay costs. Equitable argues that its agreement with Tennessee was still in force until 31 October 1989 and that Tennessee cannot recover any amount from Equitable in excess of the amount specified in the settlement during the term of that settlement. Because the Commission did not give an adequate, reasoned basis for its treatment of these agreements under the purchase deficiency allocation, we vacate the orders on this point and remand to the Commission. On remand, the Commission is to justify in a rational and adequate fashion the effect of the purchase deficiency allocation on these agreements. Otherwise, the Commission must adjust any recovery from either Equitable or Columbia for any take-or-pay liability that is covered by the settlement agreements.
Tennessee and Equitable entered into a settlement agreement on 11 April 1986 (the “April settlement”). The Commission approved the April settlement.
Tennessee Gas Pipeline Co.,
Similarly, Columbia paid its proportional share of take-or-pay costs for the years 1982 and 1983 pursuant to a settlement agreement with Tennessee originally entered into in November of 1984 (the “November settlement”). The Commission approved the November settlement.
Columbia Gas Transmission Corp. v. Tennessee Gas Pipeline Co.,
Equitable argues that Tennessee’s unilateral imposition of the higher take-or-pay charges without a general rate filing under Section 4 of the NGA, 15 U.S.C. § 717c, violated both the
Mobile-Sierra
doctrine,
see FPC v. Sierra Pacific Power Co.,
Columbia’s claim is also based on allegations that the Commission acted arbitrarily. Columbia argues that, by its own terms, the Commission’s use of the purchase deficiency mechanism was designed to rationally correlate take-or-pay cost incurrence with cost causation.
Tennessee Gas Pipeline Co.,
The Commission responds that Equitable’s argument is overly formalistic: when the Commission rejected Tennessee’s initial Section 4 filing and issued its own decision, the Commission argues, it implemented a rate change that was the result of a “proceeding instituted by the Commission pursuant to Section 5” as contemplated by the April agreement. According to FERC, its actions were therefore consistent with the settlement, and the fact that the rate change was not initiated by the
pipeline company
is irrelevant. The Commission argues further that Equitable’s argument is inconsistent with Equitable’s own prior conduct because Equitable allegedly recognized that the April settlement would be supplanted upon issuance of a decision on the merits in the present case. In any event, the Commission concludes, no different result is required here even if Equitable’s arguments are correct because the practical relief available to Equitable is minimal inasmuch as Equitable’s “overall allocation cannot be reduced merely because the payment level could not be applied to it until October 1989 [the date at which the April settlement expired].” Brief for Respondent
As to Columbia, the Commission argues that if it were to approve the “credit” requested by Columbia, it would have to make a similar adjustment every time a pipeline and one of its customers entered into an agreement that could be read as relieving the pipeline of take-or-pay liability (as an example, FERC points to the so-called “released gas programs”). The Commission also claims that it has consistently denied such credits or adjustments on the grounds that a customer in Columbia’s position receives a number of additional benefits in such agreements, and that therefore Columbia’s request is merely an attempt to add extra terms to the original agreement.
Although the Commission correctly asserts that it is entitled to deference in the interpretation of settlement agreements before it,
National Fuel Gas Supply Corp. v. FERC,
As to Columbia, regardless of the fact that its settlement with Tennessee used a cost-causation approach similar to that used by the Commission here, it has already paid an amount agreed upon between itself and Tennessee for its share of take- or-pay liability for a specific period. It should be given credit for having done so, absent a good explanation.
D. Section 5, the Sunset Provision, the Litigation Exception, and Implementation Issues
Petitioners argue that the Commission erred in failing to consider whether the buyout and buydown costs at issue were unjust and unreasonable and therefore violated Section 5 of the NGA, 15 U.S.C. § 717d. The Commission responds that this question should be considered in the generic Order No. 500 proceedings.
This issue is now mooted by our recent decision in
American Gas Ass’n v. FERC,
Various petitioners attack the deadline of 31 March 1989 for filing under the “equitable sharing mechanism” (the “sunset date”) and the Commission’s “litigation exception” to the sunset date (i.e., that take- or-pay liabilities in litigation as of 31 March 1989 are exempt from the deadline). Our decision in AGA invalidated the sunset provision as arbitrary and capricious. AGA, at 151. Because the litigation exception was merely a dispensation from the sunset date, that issue is now moot.
Finally, because of our conclusion that direct billing based on purchase deficiencies violates the filed rate doctrine, all implementation issues are moot.
III. Conclusion
The purchase deficiency allocation mechanism violates the filed rate doctrine. Because we find that prepayments are not payments for gas to the extent that the gas is not taken, we reject petitioners’ Title I attack on the orders before us. The Commission did not present a reasoned explanation with regard to the effect of its purchase deficiency allocation on Equitable and Columbia. On remand, the Commission must adequately and reasonably justify its orders, particularly with regard to the
Mobile-Sierra
doctrine, to findings necessary prior to Commission action, and to its refusal to grant Columbia “credit” for payments already made. Otherwise, the Commission must adjust any recovery from either customer for any take-or-pay liability covered by their respective agreements. Our recent decision in
AGA
moots various petitioners' claims as to Section 5,
Notes
. The Commission now apparently requires even customers who secure abandonment of service to pay their share under the passthrough mechanism.
See United Gas Pipe Line Co.,
. Because we do not reach the issue of the lawfulness of the Commission’s treatment of released gas sales, we point out that our decision does not turn on the asserted distinction between settlement payments and released gas, and we express no opinion on that question.