67 W. Va. 503 | W. Va. | 1910
The refusal of certain instructions, asked for by the defendant, and the giving of an instruction, prepared and given by the court in lieu of those requested, constitute the grounds of complaint on this writ of error.
The Ashland Coal & Coke Company sued The Hull Coal & Coke Corporation, in assumpsit, for about $2,800.00, the price of coke sold to the latter in the months of June and July, 1906. The defendant claimed by way of set-off, $4,362.34, as commission on certain other coal, and, by way of recoupment, $2,575.37', both of which cross-claims grew out of an alleged breach of contract on the part of the plaintiff. The jury disallowed both and rendered a verdict for the full amount of the claim of the plaintiff.
'The contract involved was made about the first of February, 1906, and is evidenced by two letters, one written by Frank A. Hill, President of The Hull Coal & Coke Corporation, dated February 3, 1906, proposing, on behalf of said corporation, to act as sales agent for the coke manufactured by the Ashland Coal & Coke Company from February 1, 1906, until October 1, 1906, and to take and dispose of the entire output of said company’s plant, on a commission of eight per cent, on the selling price of the coke on board the ears at the ovens guaranteed to be not less
Whether technically the defendant was a sales agent or a purchaser of the coke is an immaterial question, since it does not deny its liability for the price of the coke sued for. Its answer to the demand of the plaintiff is a claim of recoupment, founded upon the alleged breach of the contract.
Jn the months of February, March and April, 1906, the contract was observed and complied with by both parties; but, in May of that year, the defendant was unable to handle the entire output of the plaintiff’s plant. This disability continued through the month of June. As to whether it was able to take all the coke contracted for in July, is a controverted matter and constitutes the crucial question in the case. About May 1st, the defendant lost' a large contract with the Algoma Steel Company at Sault Ste Marie. Sometime after that, an accident happened to the plant of another customer at Koanoke, Virginia. These adversities seem not to have been reported to the plaintiff at once, but the requisitions for coke from its plant fell off greatly, with the result that many of its ovens had to be put out and its force of laborers greatly reduced. However, it continued to deliver such quantities of coke as the defendant called for and never ceased to do so until about July 24th. ■ In February, the defendant took 190 cars, in March 261, in April 218, in May 60, and in June 104. The plaintiff had, at its two plants, Ashland and Monitor, 410 ovens, of which the largest number
In the meantime, without the knowledge of the Hull Corporation, the plaintiff entered into negotiations with the Norton Iron Works, of Ashland, Ky., through an agent, for the sale of its coke to that company, which culminated in a contract for the entire out-put of the plant, bearing date June 20, 1906, but it is admitted that it was not actually signed until Aug. 1, 1906. W. A. Phillips, President of The Ashland Coal & Coke Company, said in his testimony: “I think the contract had been entered into on July 20th, but had not been signed until Aug. 1st. The mistake was made in placing June instead of July, the earlier date.” Said company, on July 25, 1906, formally notified the defendant that it had sold the product of its ovens to the Norton Iron Works and-could not ship any more to the Hull- Corporation. Thereafter it ceased to do so and sold all of its coke to the Norton Iron Works. It is on the coke so sold that the defendant claims a commission of eight per cent.
As to the situation of the defendant and its relation to the plaintiff from July 1st until July 25th, there is conflict in the testimony. The' former claims that, relying upon the silence and acquiescence of the latter, with full notice to the plaintiff of the circumstances, causing embarrassment, and its intention to relieve the situation by securing- new contracts, it did secure them and was in a condition on or before July 25th to> take the entire out-put of the plaintiff’s ovens, and, from July 1st until July 25th, made requisition upon it covering- the entire out-put of the plant, and gave shipping directions for all of the cars, the latter reported as having been received and loaded. It continued, through the months of July, August and September, to send in its- written requisitions, which were ignored. The’ plaintiff says these requisitions were not made in good faith, but simply to bolster up a claim. It denies that- the defendant had any customers for the coke and says these requisitions named nobody as consignees, wherefore no shipments could be made under them. Some of its agents say in their
After the introduction of all the evidence, the defendant asked the court to instruct the juiy, (1) that the letter of July 25th, 1906, was an effort to cancel the contract, and that, in so doing, the plaintiff broke its contract, if the jury should believe that, on that date and prior thereto, the parties had been executing the contract, and at that time the defendant was
The court refused all of these instructions and gave one, prepared by itself, embodying in a general way, practically all that is included in those rejected, and covering nearly two pages of the printed record. It is not separated into paragraphs nor even sentences and- is very much involved. We will not undertake to analyze it fully. It suffices to point out one fatal defect in it, and to show, which of the instructions, requested by the defendant,' should have been given.
In lieu of .the defendant’s 6th instruction, above quoted, the court inserted this in its instruction: “And that such breach ■was not waived by the plaintiff.” The difference between the-two instructions on the subject of waiver is manifest. The one requested by the defendant sets forth hypothetically the facts and tells the jury that, if they find they are established, the plaintiff has waived the breach, committed by the defendant, and cannot rely upon it as matter of defense to the claim of recoupment. Sometimes a waiver is a mere matter of intention, a fact to be ascertained by the jury; but it is not always so. It is often a mixed question of law and fact and, when it is, the court, if asked to do so, should submit only the questions of fact to the jury, and' declare the law thereon itself. The in
If the plaintiff had desired to do so, no doubt it could have suspended the contract on the failure of the defendant, for the reasons disclosed by it, to take the product of the plant. The contract contemplated it, by giving, to the party not in default, the alternative right of cancellation, during the continuance
Hnder this principle, waiver follows as matter of law, if the facts conditionally assumed in the instruction are true Hence, the refusal of said instruction anfi failure to give a proper one on the subject matter thereof constitute error to the prejudice of the defendant, for which the judgment will have to be reversed and a new trial allowed.
The same principle sustains defendant’s instructions Nos. 1 and-5. All the others were properly refused. Nos. 2 and 4 are bad, for lack of a limitation on the amount of the damages claimed by way of recoupment. Neither of these claims is a set-off. A set-off is.a debt due the defendant from the plaintiff. Case Mfg. Co. v. Sweeney, 47 W. Va. 638; Clark’s Cove Guano Co. v. Appling, 33 W. Va. 470; Harrison v. Workman, 8 Leigh 296; Robertson v. Hogshead, 3 Leigh 667; Christian v. Miller, 3 Leigh 78. Unliquidated damages cannot be the subject of a setoff. The loss of commission by reason of plaintiff’s alleged breach of the contract is a claim of that land. The commissions were not earned. The defendant did not sell the plaintiff’s coke to the Norton Iron Works, on account
Instruction No. 3 embodies -defendant’s interpretation of the suspension or strike clause and claims the benefit thereof under a state of facts hypothetically submitted to the jury. For the purpose of testing the correctness of this instruction and settling the principles of the case for the new trial, it becomes necessary to construe this clause. We think it gives right to the party not in default, in the case of an accident of any of the kinds therein mentioned, not to cancel the contract wholly and for all time, but only during the period of the interruption. This accords with the letter of the clause. It says immediate notice of cancellation shall be given, if such party desires to cancel. This negatives the right to cancel by notice at any time such party may see fit to do so, within the period of interruption. The desire to cancel must be communicated immediately on the happening of the interruption or as soon as may be practicable thereafter. The party having such right must elect at the beginning of the period whether he will cancel or take partial performance. Then the clause says the contract may be canceled during the period of interruption, which excludes the idea of a cancellation for all time. Partial 'performance, however, is not optional with either party. It is justified only by the causes specified. Partial performance not justified in that way is a breach of the contract. When there is justifiable partial performance, it does not alter the contract nor confer any right of alteration. All of this is within the contract.' It is provided for by it. Just what considerations ■ induced the insertion of this provision in the contract, we do not know, but it is easy to perceive some upon which it may have been founded. Partial performance on the part of one company might, under certain circumstances, become very
Instruction No. 3 adopts the erroneous view that the letter of June 13, 1906, indicating probability of capacity to take no more than five to seven ears per day, after July 1st, and failure of the plaintiff to reply thereto or indicate, in any way, its dissatisfaction with the prospect, amounted to a modification of the contract and relieved the defendant of its obligation to take more than that quantity of coke after July 1st. When that letter was written, the defendant was operating under the suspension clause, without any notice of a desire on the part of the plaintiff to suspend the contract during the period of interruption. It was bound to exert itself to overcome the difficulties, causing the interruption and put itself in a situation, as soon as possible, to take the entire. out-put of the plaintiff’s plant. Its partial performance was justified only during the period of its inability to render full performance, and if it was able to take all the coke that the plaintiff could produce after the first of July, or, by the exercise of reasonable diligence, could have been able to do so, but was not, it was bound to taire it in the one instance, and its refusal to take it, in the other, amounted to a breach of the contract. Therefore, we think this instruction was properly refused.
. In conformity with our interpretation of this clause, we are of the opinion that the loss of the Algoma Steel Company contract was not one of the causes of interruption specified as justifying partial performance, if such loss resulted from underbidding by a competing company, and failure on the part of the defendant to take all of the plaintiff’s coke, due to such loss, constituted a breach of the contract, justifying renuncia
Our conclusion is that the court erred in refusing defendant’s instructions Nos. 1, 5 and 6 and in giving its own charge to the jury, from which it follows that the judgment must be reversed, the verdict set aside and the case remanded for a new trial.
Reversed and Remanded.