145 P. 107 | Cal. Ct. App. | 1914
The action is against appellant American Bonding Company of Baltimore as surety upon a bond given by the Lennig-Rapple Engineering Company for the doing of public work in the city and county of San Francisco. The bond was given pursuant to a statute enacted in 1897 requiring that the person seeking relief under the bond shall file with the board of public works a verified statement of his claim within thirty days from the time such work is completed, and providing, further, that suit may be filed by such claimant within ninety days after the filing of such claim. The work here was completed prior to February 26, 1912, but the claim was not filed until April 12, 1912, and the suit was begun July 18, 1912. But, while the statute in force at the time of the execution of the contract required the filing of the claim and the commencement of the action as stated above, in 1911 (Stats. 1911, p. 1422) the said act was amended and said respective periods were extended, and it is conceded by said appellant "that if the act of 1911 is operative in this case, the claim was properly filed and the suit commenced within proper time." It is insisted, however, that "the amendatory act of 1911 should not be construed as being retroactive and the provisions of the act in force when the bond was executed should be considered the sole criterion." *643
Respondent, though, calls attention to several decisions directly in point that support the view taken by the trial court. Appellant has not seen fit to notice any of these cases although it is stated that they were relied upon in the trial court. We content ourselves with specific reference to only three of those cited.
In Bear Lake v. Garland,
A later case is National Surety Co. v. ArchitecturalDecorating Co.,
The case of Kerckhoff-Cuzner Mill Co. v. Olmstead,
We think the foregoing cases properly state the rule and are decisive of the controversy here.
There is no more merit in the contention of appellant that the bond does not conform to the requirement of the statute. It seems to follow closely the language of the statute and specifies that the bond is given as required by an act of the legislature entitled "An act to secure the payment of the *645 claims of materialmen, mechanics or laborers employed by contractors upon state, municipal or other public work, approved March 27, 1897."
The foregoing are the only points made by appellant and, as they seem untenable, the judgment and order are affirmed.
Chipman, P. J., and Hart, J., concurred.