Arst v. Max Barken, Inc.Arst v. Max Barken, Inc.
On March 5, 1981, plaintiff-appellants David and Maxine Arst brought suit against respondent Max Barken, Inc. for breach of express and implied warranties in the construction of their residence, and for breach of a subsequent agreement to repair. Respondent filed a third party petition against Reitz & Jens, Inc. and Freeman Contracting Company. On May 13, 1982, the trial court sustained respondent’s motiоn for summary judgment and this appeal followed. We affirm.
Before this court, respondent filed a motion to dismiss appellants’ appeal on the grounds that appellants’ statement of thе facts is not a fair and concise statement as required by Rule 84.04(c). Although appellants’ statement of facts did omit certain facts, the dismissal of an appeal is a drastic remedy and we find that it would be inappropriate here. Motion denied.
Appellants entered into a contract with respondent on June 20, 1969, for the purchase of a residence which was constructed by respondent. Within one month after occupying their residence, appellants discovered cracks and shifting of the foundation and on August 29, 1969, appellants gave respondent notiсe of this condition. After such notification, respondent’s agents made numerous verbal assurances that the cracks would be repaired. On October 28, 1971, and again on January 21, 1974, appellаnts notified respondent that despite its repair of the cracks, leaks continued and additional cracks appeared.
Respondent’s employees inspected the residеnce in 1974 and again in 1975. In 1976, respondent notified appellants that based upon examinations by Reitz & Jens, respondent’s soil engineers, the cracking was a result of underlying soil conditions which causеd the vertical settling of the residence. Respondent then contracted with Freeman Contracting Company to underpin the foundation and patch the cracks in appellants’ residеnce. Nevertheless, more cracks appeared after the foundation was underpinned.
Respondent continued to monitor the problem but did nothing further to remedy the condition. In a letter dated August 7, 1979, respondent’s president stated to appellants, “I do not feel that Max Barken, Inc.
Appеllants thereafter retained two soil engineering firms which inspected the premises and concluded that the residence was not settling vertically, but rather was sliding horizontally down the slope because respondent had rechanneled an adjacent creek without stabilizing the slope prior to construction.
In their brief, appellants relied on four points. All four of these points, however, deal with the question of whether the trial court erred in sustaining respondent’s motion for summary judgment on the grounds that the action was barred by the statute of limitations.
On review of a grant of a mоtion for summary judgment, parties against whom summary judgment was entered must be accorded every favorable intendment of the record.
Thompson v. Parker,
In their petition, appellants alleged that respondеnt expressly and impliedly warranted that the residence it sold to appellants was constructed in a good and workmanlike manner and that respondent breached these warranties whеn it constructed the residence on a slope which was unstable. Such actions are governed by a five year statute of limitations.
Under
... the cause of action shall not be deemed to accrue when the wrong is done or the technical breach of cоntract or duty occurs, but when the damage resulting therefrom is sustained and is capable of ascertainment, and, if more than one item of damage, then the last item, so that all resulting damage may be recovered, and full and complete relief obtained.
Appellants contend that their damages were not ascertainable until after April, 1976, when “additional movement occurred,” and “only then could appellants have maintained an action for the full extent of their damages to a successful conclusion.”
Only when there is more than one item of damage does the cause of action accrue, so as to begin only after the last wrong has been completed.
Ruhling v. Robert Dawes Construction Company,
Appellants cite three Missouri cases in which there was a delayed manifestation of injury:
Krug v. Sterling Drug, Inc.,
In the case at bar, there was no such delayed manifestation of injuries. Appellants discovered cracks and shifting of their foundation in August of 1969 and they knew who caused such damage, yet they nеglected to employ an expert to ascertain the nature of their damages until August of 1979. We find that appellants had notice of their cause of action against respondent in August of 1969 and it is then that the statute of limitations began to run.
Appellants alleged that the question of whether their claim was filed within the statute of limitations contained genuine issues of material fact. We find that the record before us presents no substantial evidence to make the question of when plaintiffs’ cause of action accrued a question for the jury.
Krug v. Sterling Drug, Inc.,
In a subpoint, appellants contend that a purchaser must give the builder notice of the breach and an opportunity to repair as a prerequisite to bringing an action for breach of an implied warranty. For authority, appellants cite the cases of:
Crowder v. Vandendeale,
Appellants further contend that, assuming their cause of action is barred by the statute of limitations, respondent’s written promise to remedy the condition through a written contract with Freeman Contracting Company revived appellants’ action from the bar of the statute of limitations, or, alternatively, is the basis for a new cause of action not barred by the statute of limitations.
We fail to find “a written
promise
to remedy the condition” in respondent’s letter. (emphasis ours) Thеrefore, the requirements of
Finally, appellants allegе that if their cause of action is deemed to accrue when they noticed the foundation cracks, respondent’s attempts to repair estopped it from asserting the statute оf limitations as a bar to this action. This court in
Neal v. Laclede Gas Company,
Judgment affirmed.