On March 5, 1981, plaintiff-appellants David and Maxine Arst brought suit against respondent Max Barken, Inc. for breach of express and implied warranties in the construction of their residence, and for breach of a subsequent agreement to repair. Respondent filed a third party petition against Reitz & Jens, Inc. and Freeman Contracting Company. On May 13, 1982, the trial court sustained respondent’s motion for summаry judgment and this appeal followed. We affirm.
Before this court, respondent filed a motion to dismiss appellants’ appeal on the grounds that appellants’ statement of the facts is nоt a fair and concise statement as required by Rule 84.04(c). Although appellants’ statement of facts did omit certain facts, the dismissal of an appeal is a drastic remedy and we find that it would be inappropriate here. Motion denied.
Appellants entered into a contract with respondent on June 20, 1969, for the purchase of a residence which was constructed by respondent. Within one month after occupying their residence, appellants discovered cracks and shifting of the foundation and on August 29, 1969, appellants gave respondent notice of this condition. Aftеr such notification, respondent’s agents made numerous verbal assurances that the cracks would be repaired. On October 28, 1971, and again on January 21, 1974, appellants notified respondent thаt despite its repair of the cracks, leaks continued and additional cracks appeared.
Respondent’s employees inspected the residence in 1974 and again in 1975. In 1976, respоndent notified appellants that based upon examinations by Reitz & Jens, respondent’s soil engineers, the cracking was a result of underlying soil conditions which caused the vertical settling of the residеnce. Respondent then contracted with Freeman Contracting Company to underpin the foundation and patch the cracks in appellants’ residence. Nevertheless, more crаcks appeared after the foundation was underpinned.
Respondent continued to monitor the problem but did nothing further to remedy the condition. In a letter dated August 7, 1979, respondent’s president stated to appellants, “I do not feel that Max Barken, Inc. *847 has any further responsibility to you in connection with the construction of your home.”
Appellants thereafter retained two soil enginеering firms which inspected the premises and concluded that the residence was not settling vertically, but rather was sliding horizontally down the slope because respondent had rechanneled an adjacent creek without stabilizing the slope prior to construction.
In their brief, appellants relied on four points. All four of these points, however, deal with the question of whether the trial court erred in sustaining respondent’s motion for summary judgment on the grounds that the action was barred by the statute of limitations.
On review of a grant of a motion for summary judgment, parties against whom summary judgment was entеred must be accorded every favorable intendment of the record.
Thompson v. Parker,
In their petition, appellants alleged that respondent expressly and impliedly warranted that the residence it sоld to appellants was constructed in a good and workmanlike manner and that respondent breached these warranties when it constructed the residence on a slope which was unstаble. Such actions are governed by a five year statute of limitations. § 516.120 RSMo 1978;
Ruhling v. Robert Dawes Construction Company,
Under § 516.100 RSMo 1978, the five year statute of limitations does not begin to run until the cause of action accrues, which is defined as follows:
... the cause of action shall not be deemed to accrue when the wrong is done or the technical breach of contract or duty occurs, but when the damage resulting therefrom is sustаined and is capable of ascertainment, and, if more than one item of damage, then the last item, so that all resulting damage may be recovered, and full and complete relief obtained.
§ 516.100 RSMo 1978.
Appellants contend that their damages were not ascertainable until after April, 1976, when “additional movement occurred,” and “only then could appellants have maintained an action for the full extent of their damages to a successful conclusion.”
Only when there is more than one item of damage does the cause of action accrue, so as to begin only after the last wrong has been completed.
Ruhling v. Robert Dawes Construction Company,
Appellants cite three Missouri cases in which there was a delayed manifestation of injury:
Krug v. Sterling Drug, Inc.,
In the case at bar, there was no such delayed manifestation of injuries. Appellants discovered cracks and shifting of their foundation in August of 1969 and they knew who caused such damage, yet they neglected to employ an expert to ascertain the nature of their damages until August of 1979. We find that аppellants had notice of their cause of action against respondent in August of 1969 and it is then that the statute of limitations began to run.
Appellants alleged that the question of whether their claim was filed within the statute of limitations contained genuine issues of material fact. We find that the record before us presents no substantial evidence to make the question of when plaintiffs’ cause of action accrued a question for the jury.
Krug v. Sterling Drug, Inc.,
In a subpoint, appellants contend that a purchaser must give the builder notice of the breach and an opportunity to repair as a prerequisite to bringing an action for breach of an implied warranty. For authority, appellants cite the cases of:
Crowder v. Vandendeale,
Appellants further contend that, assuming their cause of action is barred by the statute of limitations, respondent’s written promise to remedy the condition through a written contract with Freeman Contracting Company revived appellants’ action from the bar of the statute of limitations, or, alternatively, is the basis for a new cause of action not barred by the statute of limitations.
Section 516.320 RSMo 1978 provides that in order to take a case out of the statute of limitations, a written promise must be made by the party chargeable thereby. Appellants contend that respondent “promised to remedy the condition by underpinning the foundation” in a letter written to them. In respondent’s letter, respondent denied any liability for the cracked foundation, but did inform appellant that it would contract to have their foundation underpinned. However, respondent made it clear that it’s action was not to be understood as an agreement to do any further repairs.
We fail to find “a written promise to remedy the condition” in respondent’s letter. (emphasis ours) Therefore, the requirements of Section 516.320 RSMo 1978 were not met to toll the statute of limitations. Since we find no promise to repаir in respondent’s letter, we also find no basis for a separate cause of action against the respondent for breach of an agreement to repair the defective cоnditions of appellants’ residence.
Finally, appellants allege that if their cause of action is deemed to accrue when they noticed the foundation cracks, respondеnt’s attempts to repair estopped it from asserting the statute of limitations as a bar to this action. This court in
Neal v. Laclede Gas Company,
Judgment affirmed.
