279 F. 307 | D.C. Cir. | 1922
Thompson & Spear Company, Inc., hereinafter designated as the corporation, sued Arnold for a balance of $3,115.42, claimed to be due for certain work done by the corporation as a subcontractor under Arnold. The case was tried to a jury, which returned a verdict for the entire amount claimed. Judgment was entered on the verdict, and Arnold appeals.
Arnold had a contract with the United States government for the construction of a general storehouse at the submarine base near New London, Conn. He entered into a subcontract with the corporation to do the plumbing and related work for $3,800, which was to be paid as follows:
“On the 1st of each month as the work progresses * * * 90 per cent, of the value of the completed work as based on the shove contract price, and the remaining 10 per cent. 80 days after the completion of this subcontract and acceptance of the same by the above-named owner or architect.”
The Navy Department was named as owner, and the Bureau of Yards and Docks as architect. It was also provided that, should Arnold at any time during the progress of the work direct any additions to or omissions from the work, the corporation should do it in the manner directed. If work was omitted, it was to be deducted from the contract price; if added, to be added to that price. Work was added, which the corporation claims was worth $1,088.92, while Arnold says it was worth only $1,025.60. The corporation alleges that it performed all the work required of it with due diligence, and that the total amount of the contract, with the additions, was $4,888.92; that it received $1,-773.50 from Arnold, but that he refused to pay the balance, namely, $3,115.42.
Arnold filed several pleas. He denied that he was indebted to the corporation, and alleged that by reason of its failure to complete the contract according to its terms he was damaged in the sum of $694.66, for which he asked judgment. Arnold offered no evidence in support of his claim for damages, and therefore it went out of the case. The ultimate question, then, is as to whether or not the corporation proved performance.
Errors are assigned by Arnold with respect to the admission of evidence, the refusal of the court to peremptorily instruct the jury to return a verdict for him, its refusal of certain other prayers for instructions, and with respect to parts of the charge to the jury.
As we have seen, the contract provided that the final sum was not
“Please do not write back and cause any delay in starting the work. * * * The quicker you get tbe plans and specifications to us, the sooner we will make the layout for the plumbing and get the stock on the job.”
This indicates conclusively that no work was done before November 5, and as Mr. Thompson, according to his own statement, did not see the work after that, he had no personal knowledge as to whether or not it was done. His testimony is purely hearsay.
In an effort to qualify it, the corporation produced as a witness Commander Burrell, who said that he first met Thompson in New London in the winter of 1917-18, and was quite sure he, Thompson, was there in June, 1918. But this has no tendency to show that Thompson examined the work at that time, especially in view of the latter’s unqualified statement that he had not seen it after November 5, 1917._
The commander also testified that he was in the Civil Engineer Corps, under the Bureau of Yards and Docks; that he reported for duty at the submarine base in October, 1917, and continued there throughout December, 1919; that he had supervision of all construction work at the submarine base, both by contract and day labor; that he knew that the defendant Arnold had a contract to construct a storehouse there, and that the corporation was a subcontractor for the plumbing work on the house; that he had supervision of the preparation of all reports relating, to the work, and the preparation of vouchers in payment therefor. He said that the corporation furnished the labor and material, and installed the plumbing work “in the regular contract and in the extra,” and that it was satisfactory, without saying to whom it was satisfactory. He was then asked if the work was accepted. This was obiected tó on the ground that the acceptance could be made'only by the Bureau of Yards and Docks; that if it had been made the acceptance was a matter of record, and could be proved only by the record. The court ruled that the record should be produced.
“Where the parties, in their contract, fix on a, certain mode by which the amount to he paid shall be ascertained, as in the present case, the party that seeks an enforcement of the agreement must show that he has done everything on his part, which could be done, to carry it into effect. He cannot compel the payment of the amount claimed, unless he shall procure the kind of evidence required by the contract, or show that by time or accident he is unable to do so." United States v. Robeson, 9 Pet. 319, 326, 9 L. Ed. 142.
Cases supporting the same view of the law are Kihlberg v. United Stales, 97 U. S. 398, 24 L. Ed. 1106; Sweeney v. United States, 109 U. S. 618, 3 Sup. Ct. 344, 27 L. Ed. 1053; George A. Fuller Co. v. B. P. Young Co., 126 Fed. 343, 61 C. C. A. 245; Bush v. Jones, 144 Fed. 942, 75 C. C. A. 582, 6 L. R. A. (N. S.) 774. There is no claim here that the corporation was prevented by time or accident from producing the necessary evidence.
For this reason, the judgment is reversed, with costs, and the case remanded, with instructions to grant a new trial.
Reversed.