96 Wis. 274 | Wis. | 1897
The first proposition of appellants’ counsel is that, the fact being established by the verdict that the contract was not fully performed by plaintiff, the conclusion of law that he was entitled to recover is erroneous. The principle invoked is that where a contract provides for payment of a specified sum for constructing a building, payable upon its completion, full performance is a condition prece
Error is assigned on the finding of the jury that the building was substantially completed before the lien was filed. Whether such finding was warranted by the evidence or not is immaterial. It follows, from what has preceded, that plaintiff is entitled to recover the contract price, less deductions for expense of remedying the defects, so far as that was practicable without unreasonable expense, and for the
Error is assigned on the instructions respecting the sixth question, which covers the deductions from the contract price to which appellant was entitled for failure of plaintiff to fully complete the building; but, as no exceptions to the charge were preserved in the bill of exceptions, we must presume that the jury was correctly instructed. It appears that evidence in the record supports all the findings of fact as made by the jury, not heretofore referred to; that such findings cover all the issues of fact in the case; that judgment was entered in accordance therewith; and that there are no reversible errors.
By the Court.— The judgment of the circuit courtis affirmed.