Armitage v. Mayor & Common Council of Newark

86 N.J.L. 5 | N.J. | 1914

The opinion of the court was delivered by

Garrison, J.

Clearly, the lowest bid did not get the contract. The lowest bid, under the invitation to bidders, ivas the aggregate of the lowest bids for separate items.

This hid was $16,488 lower than that of the successful bidder. The circumstance that this lowest bid ivas made up of the separate proposals that had been invited is not a lawful ground for discrimination against it; such proposals were made in strict compliance with the, terms of the advertisement for bids and under the statute the award must follow such advertisement or the contract will he invalid.

In extenuation of this violation of the statute it is said that it was within the discretion of the city authorities to decide *8that it was more advantageous to the city to have its work done by a general contractor than by the bidders for the separate items. True, it was not only the right but the duty of the city authorities to decide this question, but when and how often:' They liad exercised this right once when they publicly advertised that bids of either sort would be received and that the contract would be awarded to the lowest responsible bidder. If they may exercise it a second time it must be in such a way as not to violate the statute, which is clearly done if the change of heart takes place after the bids are opened and results in depriving the lowest bid of its statutory vantage, and the awarding of the contract contrary to the statute. If, after the bids were'received, the city decided that it would be better to contract only with a general contractor, it was open to the city to reject all bids and to readvertise for bids by general contractors only. Common fairness, as well as statutory obligation, require such a course and condemn the one that was actually pursued in this ease which violated not only the letter but the spirit of the statute in every essential respect. Nothing would so fatally discourage bidders as a well-founded suspicion that contacts are not awarded to the lowest bidder who complied with the conditions of the public advertisement; and to encourage competitive bidding was one of the main purposes of the statute in question. By the express terms of the statute, therefore,' the contract “let” in the present case is “invalid.”

If, however, we are wrong in reading this statute as it is written and in deeming that it means just what it says, and if the correct view is that the 'city after discovering that the bidders on separate items are the lowest bidders, may change its advertised scheme and decide that the competition shall be limited to bidders for the doing of the entire work in a single contract, then and in that case the present award is invalid, because if any such decision was made the lowest bidders under the public advertisement for bids were entitled to be heard upon that question before it was decided against them. The siatus of the lowest bidders carrying with it this right, is legally indistinguishable from that accorded to such bidders *9iii McGovern v. Board of Public Works, 57 N. J. L. 580, and Faist v. Hoboken, 72 Id. 361.

This last-cited case also disposes of the notion that the statute can he evaded under color of the rejection “of any and all bids.”

For the reasons stated the contract in the present case is invalid and must be set aside.

There is another flaw in these proceedings that ought not to be passed over merely because no demonstrable harm has come of it in the present case. I refer to the requirement of the advertisement that each bidder must specify the number of days lie will require to finish the work. According to all our cases, if this element of time is to enter into the competitive scheme. ¡I should be the same for all, not left for each bidder to fix for himself and thereby estimate Ms bid npon a basis different from that of any other bidder. The general vice of this course is that no common standard for the competition is set up, and as was said by the Conrt of Errors and Appeals in Browning v. Bergen, 79 N. J. L. 494, “where no common standard is set up no competition is proposed.”

“'No contract,” said Mr. Justice Van Syckel, in Van Reiper v. Jersey City, 58 N. J. L. 262, “can be properly upheld under proposals which do not require competitive bids upon the same definite basis.”

Of this definite basis time is as much an element as is the number of men to be employed or the wages to be paid, which if required to be specified by each bidder would destroy any semblance of competition as to price.

In a recent case in this court we expressly held that unless the length of Lime was alike for all bidders there could be no such competition as the law requires. Johnson v. Atlantic City, 85 N. J. L. 145.

The mischief to be apprehended is not that contracts will lie awarded to the bidder who will take the least time rather than to him who will take the least money, i. e., to the lowest bidder, but that, owing to this multiple standard, it is impossible to tell who is, or rather would have been, the lowest bidder had there been a common standard of time alike for *10all: or, what amounts to the same thing, had the element of time been left out altogether.

Experience in dealing with evasions of this law teaches that it is better to keep the door wide open than to try to close one that is, perhaps purposely, left a little ajar.

At all events, upon both reason and authority, a contract based upon such non-competitive bidding is not a valid one under the law we are now considering.

It is claimed by the prosecutor that the delay > of bight months in awarding this contract will cost the taxpayers any-wheres from $50,000 to $80,000, owing to the drop in prices of material during that period. The result we have reached on the main question renders it unnecessary to pass also upon this one. This remark applies also io the claim that the entire proceeding is vitiated by the addition to the market-house of a second story not intended for market purposes, but by which it is claimed that upwards of $200,000 are added to the cost of the market building. And the same remark applies also to the “well” item and to all the other points made in the brief of counsel for the prosecutor., as to which wcl simply express no opinion, one way or the other.

Eor the specific reasons given, the contract brought up by this writ is set aside, with costs.