Armentano v. Broadway Mall Properties, Inc.Armentano v. Broadway Mall Properties, Inc.
Ordered that the order is reversed insofar as appealed from, on the law, with one bill of costs, the motion is denied, and the cross motion is granted.
On its cross motion, CCM established, prima facie, that it only coordinated the different subcontractors, created work schedules, and prepared progress reports for the instant construction project. This authority does not rise to the level of supervision or control necessary to make CCM a contractor liable for the injured plaintiff‘s injuries pursuant to