This is a complex contract action relating to the construction of an experimental plant in Stuttgart, Arkansas, for the combustion of rice hulls in a pollution-free manner with the production of steam and a commercially valuable ash as by-products. The basic issue in this appeal is whether the district court
Background
Alchemy possessed the rights to a new process for the combustion of rice hulls that had been developed by Norman Pitt and his company, Normán Pitt, Inc. In 1972, Alchemy and Arkansas Rice Growers Cooperative Association, d/b/a Riceland Foods (Riceland) entered into a contract for the construction of a factory in Stuttgart that would burn rice hulls and a separate but related contract regarding the marketing of the ash by-product. The construction contract provided that Alchemy should enter into a contract with Pitt, Inc. under which Pitt, Inc. would provide Riceland with “the necessary engineering plant layout and equipment design and the onsite engineering supervision and start up engineering services necessary for the construction of a hull by-product facility capable of reducing a minimum of 7V2 tons of rice hulls per hour to an ash and producing a minimum of 48 million BTU’s per hour of steam at 200 pounds pressure.” The contract further provided that Riceland would construct the facility at its sole expense and would operate the facility in accordance with the instructions and procedures provided by Alchemy. Under the ash marketing agreement, Riceland granted to Alchemy the exclusive right to obtain all ash produced at the Stuttgart facility and
After Pitt, Inc. furnished Riceland with plans for the design of the facility, Rice-land, acting as its own general contractor, began construction of the facility in August 1974. The facility was completed in December 1975, and Riceland commenced operation of the plant. Although the plant was designed to operate every day on a twenty-four hour basis, it never performed as anticipated by the parties. The plant was repeatedly shut down because of a build up of hulls in the furnace and an inability to comply with state air pollution control standards. Although the plant was intended to operate on rice hulls alone, the desired consistency of the ash could not be achieved without the use of fuel oil in addition to hulls. After unsuccessfully attempting to operate the plant for three years, Riceland closed the plant in September 1978.
Riceland filed suit against Alchemy and Pitt, Inc. in 1978 for breach of contract and negligent design, claiming $3,017,500.00 in damages. Riceland also brought suit against certain individuals (the “individual defendants”)
We will not attempt here to detail the extensive evidence set forth by the district court. Instead, we initially analyze the district court’s conclusion that Alchemy and Pitt, Inc. breached the construction contract and then determine whether the evidence supports the district court’s findings and conclusions on this issue. We thereafter take up (1) the determination of damages attributable to Alchemy and Pitt, Inc., and (2) the liability of the individual defendants.
I. Liability of Alchemy and Pitt, Inc. for Breach of Contract
Pursuant to the express terms of the contracts, California law governs all questions of state law. It is well settled that the construction and legal effect of a contract are questions of law subject to de novo review. E.g., Osborne v. Cal-Am Financial Corp.,
The district court’s findings regarding the liability of Alchemy and Pitt, Inc. for
The district court recognized that not all of the plant’s problems were attributable to Alchemy and Pitt, Inc. Most notably, much of the equipment supplied by Polutrol, Inc., (Polutrol) the company selected by Riceland to supply the boilers and the air pollution control system, was inadequately designed and poorly manufactured. The parties agree, and the district court found, that the air pollution control system supplied by Polutrol did not allow the facility to operate in compliance with the state air pollution control regulations as required by the construction contract. Moreover, Polutrol failed to take the abrasive quality of the ash into account when manufacturing the boilers, and the boilers thus deteriorated and were in need of replacement at the time Riceland permanently shut down the plant. The district court determined, however, that although Alchemy and Pitt, Inc. were not responsible for the damage or loss caused by the defective Polutrol equipment, the evidence established that Pitt, Inc.’s design would not have produced a plant capable of achieving the performance criteria even had the Polutrol equipment not been defective. As to the non-erosion problems caused by the boilers, such as the difficulty of controlling the water levels in the boilers and its system-wide repercussions, the district court found that Alchemy and Pitt, Inc. were responsible. The court explained that because Pitt, Inc. had approved the water-tube boiler design suggested by Polutrol, the water-tube boilers had become a part of Pitt, Inc.’s design.
The district court also found against Alchemy on its counterclaim for breach of contract against Riceland. Alchemy had urged at trial that Riceland had breached both the construction contract and the marketing contract because Riceland closed down the plant and thus did not pay Alchemy royalties for the use of Pitt, Inc.’s process as promised in the construction contract or provide Alchemy with the ash as provided in the marketing agreement. Moreover, Alchemy asserted, the failure of the plant to operate as anticipated was due to the defective equipment provided by Polutrol for which Alchemy claimed Riceland was responsible. In rejecting Alchemy’s counterclaim, the district court relied on the findings it had made in connection with Riceland’s claim against Alchemy and Pitt, Inc. The district court first noted that Polutrol’s errors were limited to the abrasion-erosion problems of the boilers and the air pollution control system. Even had these problems been corrected, the district court stated, the plant could not have achieved the performance criteria because of the design deficiencies attributable to Alchemy and Pitt, Inc. The district court further held that although Polutrol’s errors in designing and constructing certain equipment could be used as a partial defense to Riceland’s action against Alchemy and Pitt, Inc., justifying a reduction of damages, Polutrol’s errors could not be
In contesting the district court’s allocation of liability under the contracts on appeal, the defendants seek to prevail on Riceland’s claim against them by prevailing on Alchemy’s counterclaim against Rice-land. More specifically, defendants argue that the district court erred in determining that Riceland is not responsible for the deficiencies in the Polutrol equipment. Defendants contend that Alchemy and Pitt, Inc. were only responsible for providing the furnace and the general requirements for the other equipment. As general contractor, defendants argue, Riceland was responsible for providing equipment that met the general requirements. Because Polutrol’s equipment did not meet the general requirements of Pitt, Inc.’s design, defendants contend, Riceland committed a material breach of the construction contract. Defendants then argue that since Riceland breached the contract first, Riceland may not recover against the defendants for breach of contract under California law, regardless of whether the defendants also breached the contract. In short, defendants contend that Riceland’s failure to construct a facility that conformed to Pitt, Inc.’s design breached its contracts with Alchemy. Concomitantly, Alchemy and Pitt, Inc.’s obligation to render the plant operational according to the performance criteria never arose because Riceland never completed the construction of such a facility-
We have carefully reviewed the trial court’s findings of fact and the contracts entered into by the parties, and we conclude that the district court did not err in placing liability on Alchemy and Pitt, Inc. for the failure of the plant to operate as anticipated by the parties. The construction contract obligated Alchemy and Pitt, Inc. to provide “the necessary engineering plant layout and equipment design and the onsite engineering supervision and start up engineering services” for the construction of a hull-burning plant capable of achieving the performance criteria. Alchemy and Pitt, Inc. thus warranted that a plant constructed according to Pitt, Inc.’s design was capable of achieving the performance criteria. See United States v. Spearin,
We also agree with the district court, for the reasons discussed above, that Alchemy may not recover on its counterclaim against Riceland. The marketing contract expressly provides that Riceland assumes no responsibility for the quality of the ash produced as a result of following Alchemy’s directions. The district court found, and we agree, that Riceland at all times operated the plant according to Alchemy’s and Pitt, Inc.’s instructions.
II. Damages
After a supplementary trial on damages, the district court issued a second memorandum opinion explaining its damage determination. In general, the district court allowed Riceland to recover the costs of constructing the plant, less the costs attributable to Polutrol’s errors and a few other deductions, but not the expenses of operating the plant. More specifically, the court deducted from Riceland’s estimate of the overall construction costs the cost of the air pollution control system, one third of the cost of the boilers, and fifteen percent of the cost of boiler-related items. The trial court also deducted from Riceland’s estimate of the total construction costs financing charges, the cost of a hull storage tank, the cost of certain back up equipment, and the estimated salvage value of the plant and equipment. Finally, the district court allowed Alchemy and Pitt, Inc. a twenty percent deduction of the amount remaining after the above deductions to reflect the adverse effects of the defective Polutrol equipment on the operation of the
Neither party disputes on appeal the district court’s basic approach to the determination of damages. Instead, Alchemy and Pitt, Inc. argue that there is no factual basis for the district court’s determination of the percentages it deducted from the overall construction costs. In reviewing the defendants’ contention, we initially note that a district court has wide discretion in determining the amount of damages to award for breach of contract under California law. Distillers Distributing Corp. v. J. C. Millett Co.,
III. Liability of the Individual Defendants
Article seven of the construction contract provides that
Alchemy shall provide to Riceland financial assurances either in the form of personal guarantees satisfactory to Rice-land or in the form of a line of credit from a bank or other financial institution, in an amount equal to the cost of the facility to be designed by Norman Pitt, Inc., based upon the cost of such facility (estimated prior to construction) plus ten percent (10%) thereof. Such guarantees or line of credit shall remain in effect for a period of twelve (12) . months following the date that the facility becomes operational.
Riceland agreed to accept $500,000 in financial assurances. According to the undisputed evidence, twenty-two individuals executed personal guarantees to Union Bank in California, which then issued a letter of credit to Riceland guaranteeing Alchemy’s performance of the contract.
Because the determination of whether the personal guarantees run in favor of Riceland may affect the question of personal jurisdiction over the individual defendants, we initially assume for the purposes of argument that the guarantees run in favor of the bank and Riceland. The facts relevant to the personal jurisdiction issue are as follows. Structural Materials Partnership, a California limited partnership that possessed the rights to Norman Pitt’s design for the hull-burning facility, began negotiations with Riceland in the summer of 1972 for the construction of the hull-burning facility in Stuttgart. In October 1972, Structural licensed Pitt, Inc.’s design to Alchemy, a corporation formed by some of the Structural partners. Alchemy continued the negotiations with Riceland for the hull-burning facility, and Riceland and Alchemy executed the construction and marketing contracts discussed above in December 1972. In April 1973, Alchemy sent Riceland a list of twenty-four individuals, all residents of California, who would sign the guarantee contract. Twenty-two of those twenty-four executed guarantees on May 1, 1973.
In 1979, the district court
The district court’s assertion of personal jurisdiction over the individual guarantors rests on several erroneous factual findings. The substantive identity of the guarantors, Alchemy, and Structural, on which the district court premised its finding of jurisdiction, simply does not exist. Contrary to the district court’s findings, only nine of the guarantors were partners in Structural, and although there is some overlap in identity of the Structural partners and the Alchemy shareholders, the two entities are by no means identical. Of the twenty-nine partners in Structural in August 1972, only thirteen were among Alchemy’s approximately seventy shareholders. The lack of identity between the Structural partners and the guarantors also demonstrates the error in the district court’s finding that Margolis, Pitt, and Kahan went to Arkansas as agents of the guarantors, subjecting the guarantors to the jurisdiction of the Arkansas courts.
In concluding that the assertion of jurisdiction over the guarantors would not offend due process, the district court also relied on the fact that Alchemy had provided Riceland with the financial statements of the prospective guarantors in August 1972 and that Riceland entered into the construction and marketing contracts with Alchemy in reliance on this information. The evidence shows, however, that the financial statements Riceland received in August 1972 were those of the Structural partners. Riceland thus had the financial statements of only nine of the eventual twenty-two guarantors when it entered into the construction and marketing contracts.
Under these circumstances, we hold that there are insufficient contacts between the guarantors and Arkansas to subject the guarantors to the jurisdiction of the Arkansas courts. The mere fact that the individual defendants guaranteed an obligation to an Arkansas corporation does not subject the guarantors to jurisdiction in Arkansas. See Arkansas Poultry Cooperative, Inc. v. Red Barn System, Inc.,
The fact that three of the guarantors— Norman Pitt, Ben Margolis, and Robert Kahan — went to Arkansas on one or more occasions does not change our holding that there are insufficient contacts between the guarantors and Arkansas either as to the guarantors in general or as to those three particular guarantors. The law is clear that a corporate officer or agent who has contact with the forum state only with regard to the performance of corporate duties does not thereby become subject to jurisdiction in his or her individual capacity. See, e.g., Escude Cruze v. Ortho Pharmaceutical Corp.,
Conclusion
For the reasons set forth above, we affirm the judgment for breach of contract against Alchemy Industries, Inc. and Norman Pitt, Inc. We vacate the judgment against the individual defendants for lack of personal jurisdiction.
Notes
. The Honorable Garnett Thomas Eisele, United States District Judge for the Eastern District of Arkansas.
. The facts surrounding the guarantee and the individual defendants involved in this count of Riceland's complaint are set out more fully in Part III.
. The defendants also argue that the trial judge erroneously refused to recuse himself. Finding this contention utterly without merit, we do not address this issue here.
. The district court determined that Riceland was the third-party beneficiary of the contract between Alchemy and Pitt, Inc., pursuant to which Pitt, Inc. agreed to provide the engineering and design services necessary for the construction of the plant. Pitt, Inc. does not dispute this finding.
. As we note in our discussion of damages, however, see Part II, the construction contract expressly precludes Riceland from recovering for the failure of the plant to comply with the air pollution control regulations because Rice-land chose to depart from Pitt, Inc.’s design for the air pollution control system.
. The indemnification clause in the construction contract and the marketing contract, although not specifically relied on by the district court, also supports the district court’s conclusion. The indemnification clause provides that Alchemy will "hold Riceland harmless from liability, loss or damage resulting from the failure of the facility to perform in accordance with the requirements of this Agreement."
. Riceland brought suit against Union Bank in California for failure to honor the letter of credit. The California proceeding is apparently stayed pending outcome of the liability determination in this case.
. Riceland initially brought suit against twenty-four individuals who Riceland contended had signed guarantees. The district court found that two of those defendants did not sign a guarantee and thus dismissed them from the case. Riceland did not appeal this dismissal.
The twenty-two remaining individual defendants are: Sol Balkin, Janelle Balkin, Seymour DiMatoff, Eleanor DiMatoff, Robert Kahan, Dorothy E. Kahan, Stanley Fleishman, Doris Fleishman, Ben Margolis, Valerie Margolis, Florence Ain, Milton London, M.D., Leah London, Murray J. Goldberg, Genevieve Goldberg, Meyer Zeiler, M.D., Floria Zeiler, Eddie Allee, Leta Allee, Robert Brock, Marjorie Brock, and Norman Pitt.
. The Honorable Oren Harris, Senior United States District Judge for the Eastern District of Arkansas, initially presided over the proceedings before the case was transferred to Judge Eisele.
. The Arkansas long arm statute allows Arkansas courts to assert jurisdiction over any nonresident who, acting directly or by an agent, transacts any business in Arkansas or contracts to supply services or things in Arkansas as to a cause of action arising from such conduct. Ark. StatAnn. § 27-2502 C(l)(a), (b) (1979).
. Because the Arkansas long-arm statute was intended to expand the jurisdiction of Arkansas courts to the modern constitutional limits, the district court primarily considered whether there were sufficient "minimum contacts” between the nonresident guarantors and Arkansas such that the assertion of personal jurisdiction over the guarantors would not offend due process. See Mountaire Feeds, Inc. v. Agro Impex, S.A.,
. Judge Eisele relied on Judge Harris’ opinion in denying the guarantors’ later request for reconsideration of their motion to quash service. Judge Eisele also relied on Judge Harris’ opinion in finding jurisdiction over the guarantors in his memorandum opinion on liability.
. Even assuming that the wives of the Structural partners who were themselves guarantors had the same financial statements as their husbands, Riceland had the financial statements of only seventeen of the twenty-two guarantors when it signed the contracts in December 1972.
