Appellant, Argos Resources, Inc., appeals from a judgment in favor of appellee, May Petroleum Inc. We find no merit in any of Argos’ eight points of error. Accordingly, we affirm.
May sued Argos on an oilfield operating agreement dated October 21, 1981. The agreement provided that May, the operator, would commence drilling of a well on or before December 31, 1981. Argos was required to pay 15% of the costs and liabilities May incurred in drilling the well. On or about December 31, 1981, Argos paid May $32,925.00, 15% of the estimated drilling cost. May actually did not begin drilling the well until January 24, 1982. Fifteen percent of the actual cost of drilling the well turned out to be $49,735.66, $16,-810.66 more than the amount Argos had already paid. May sued Argos for what it considered the balance due for the actual drilling costs. The trial court entered a judgment awarding May $16,810.66.
We first note that Argos has cited no authority under its points of error three, four, six and seven. Argos has consequently waived these points of error.
Hatch v. Davis,
In its first point of error, Argos contends that the trial court erred in finding that time was not of the essence. Argos’ apparent position is that since May failed to begin drilling by December 31, 1981, May cannot recover, given the principle that when time is of the essence of a contract a party must perform in strict compliance within the time prescribed to be entitled to any relief.
Neco Engineering Co. of Texas v. Lee,
In support of its position, Argos cites
Investors Utility Corp. v. Challacombe,
We conclude, rather, that the most relevant authorities indicate that time is
not
necessarily of the essence in an oilfield operating agreement.
See Matador Drilling Co., Inc. v. Post,
Argos’ second point of error is that the trial court erred in finding that May had satisfied all conditions precedent so as to require Argos to pay for its proportionate share of the well drilled on January 24, 1982. Argos argues that May failed to satisfy a condition precedent by failing to drill on or before December 31, 1981. The clause in the contract which stated that May was to begin drilling on or before December 31, 1981, would have had the effect of a condition precedent only if time had been of the essence. We have held that time was not of the essence in this agreement. We overrule Argos’ second point of error.
Argos’ fifth point of error, in substance, is that May cannot recover because it failed to plead or prove estoppel, waiver, ratification, modification of the contract, or entitlement to recovery under quantum meruit. Argos' argument in its brief reveals that this point of error is grounded on the assumption that May cannot recover on the operating agreement because time was of the essence of that agreement. Since we have rejected that assumption, we overrule this point of error.
In its eighth point of error, Argos contends that the trial court erred in finding that all offsets and credits due Argos were credited and that after all offsets and credits, Argos owed May $16,810.66. Argos contends further that “all evidence shows” that Argos is entitled to an offset of $5,179.16 for casing costs which, according to Argos, May wrongfully concealed from Argos. Argos does not, under its eighth point of error, refer this court to the evidence which allegedly shows that May concealed casing costs from Argos. However, under its sixth point of error, Argos argues that a May representative admitted that May knew that additional casing costs would increase the original cost estimate by more than 10% in December 1981, but that May failed to send to Argos and the other participants a supplemental cost estimate, or “authority for expenditure,” until July 1982, when May had already plugged and abandoned the well. We conclude that this evidence does not permit a determination by this court that the trial court’s finding that all offsets had been credited
*666
was either incorrect as a matter of law or against the great weight and preponderance of the evidence. We reach this conclusion because failure to send the supplemental cost estimate might have been merely negligent or justified by some other circumstances. Furthermore, this court is not required to search the record for further evidence to support Argos’ contention.
Saldana v. Garcia,
Affirmed.
