Argоnaut Insurance Company appeals from a judgment rendered against it in favor of ABC Steel Products Co., Inc.
ABC agreed to sell and install steel warehouse doors to C. T. Lambert & Associates, Inc., a general contractor, for use in the construction of a mini-warehоuse project in Richardson, Texas. Argonaut, pursuant to Tex.Rev.Civ.Stat.Ann. art. 5472d (Supp. 1978-1979), executed a statutory payment bond for Lambert which guaranteed the payment of all claims for labor and materials furnished Lambert in the construction of the project. ABC and Lambert’s contract provided for a price of $133.34 per door. The contract further stipulated that Lambert would have a “25% cash discount for payment by 15th of month after installation (making your net discounted price $100.00 per door inch applicable taxes).” ABC furnished and installed the doors as it agreed to do in the contract, but Lambert failed to pay for them. ABC then perfected its claim against Argonaut pursuant to the provisions of the payment bond it had made for Lambert. Argonaut tendered ABC the sum of $10,752.92, which represented only the net discounted price of $100.00 per door for the doors installed, plus interest and attorneys’ fees accruing to the date of the tender. ABC refused the tender on the ground it was entitled to the full contract price for the doors, rather than the discounted price, and it then filed suit against Argonaut and Lambert. The case first went to trial before the court, but after a day and a half a mistrial was declared. The second trial was to a jury which answered special issues to the effect that:
(1) The agreed price of the doors was $133.34 each unless pаyment was *886 made on or before the 15th day of the month following installation, in which event the price would be discounted 25% (Special Issue No. 1).
(2) The fair market value of the doors installed at the time of installation was $110.00 per door (Special Issue No. 3).
(3) The 25% discount did not constitute interest (Special Issue No. 4).
(4) ABC was entitled to the sum of $16,-000.00 as reasonable and necessary attorneys’ fees (Special Issue No. 2).
The district court disregarded the jury’s finding that the fair market value of the doors was $110.00 each and rendered judgment for ABC for $133.34 for each doоr furnished, plus interest and attorneys’ fees as found by the jury. Lambert did not appeal.
Argonaut’s principal contention on appeal is that, for the purpose of measuring its liability as surety for Lambert, the value of the doors was the discounted price, and that the offer of that amount to ABC constituted a lawful and sufficient tender which precluded an award for interest accruing after that date or for attorneys’ fees incurred by ABC in bringing suit on its claim.
In the absence of contractual provisions to the contrary, a surety’s liability is measured by the liability of the principal.
O’Neil Engineering Co. v. First National Bank,
Argonaut advances several reasons to support its argument that the legal principals just enunciated should not govern this case. One is that under Article XVI, Sec. 37 of the Texas Constitution, which provides that mechanics, artisans and material men shall have liens for “. . . thе value of their labor ... or material .”, the reasonable or fair market value of the materials determines the extent of the supplier’s lien rather than the contract price. One answer to that contention is that no lien is involved here. ABC is not seeking to perfect or enforce a lien against Lambert or against the owner of the improvements. It is seeking to recover from Lambert’s surety the contract price of the materials it furnished. As Lambert was obliged to pay ABC $133.34 per door, and Argonaut was liable for the debt of its principal, it was obligated to pay that price for the doors. The payment bond is intended as protection for the material men in lieu of a lien.
Trinity Universal Insurance Company v. Barlite, Inc.,
It is also contended that the “relation back doctrine” which applies in Texas to mechanic’s liens, and the provisions of the lien statutes to the effect that an indebtedness shall be considered to have accrued on the 10th of the month following the furnishing of the materials, require that Argonaut’s liability be limited to the cost of the doors if paid for by the 10th of the month after installation. We cannot accept that proposition. The relation back doctrine merely determines the priority of the liens which may be filed.
University Savings & Loan Association
v.
Security Lumber Co.,
Under its payment bond Argonaut was obligated to pay what its principal owed for the materials furnished. As Lambert did not entitle itself to the discount for prompt payment, it became liable for the full contract price. Upon Lambert’s failure to pay that price, Argonaut was bound to do so, and consequently its tender of an amount less than what was due was ineffectual. 55 Tex.Jur.2d Tender, Sec. 9, p. 220 and cases cited.
The appeal also asserts that the district court improperly disregarded the jury answеr which found that the fair market value of the doors was $110.00 each. The construction contract between the landowner and Lambert provided for a “turn-key” price of $201,000.00. In another section the contract provided that any extras or additional work could “be figured on a unit cost” as set forth in a schedule. Included in the schedule was “8" X 8" doors, @ $110.00 each.”
The trial judge correctly disregarded the jury’s finding. Regardless of the unit price stipulated by the owner and the general contractor, the price which the general contractor аgreed to pay ABC was $133.34 per door unless the discount was earned. Any other price or value was immaterial in determining the surety’s liability for the debt of its principal.
The point is raised that there is no evidence or insufficient evidence to support the jury’s finding that the 25% discount did not constitute interest. First, it should be noted that this issue was one on which Argonaut had the burden. Therefore, it cannot successfully attack the jury’s finding by showing that it is not supported by sufficient evidence. It must demonstrate that the 25% discount, as a matter of law, constituted interest.
Tex.Rev.Civ.Stat.Ann. art. 5069-1.01 provides that interest is the compensation allowed by law for the use or forbearance or detention of money. However, a seller of products may lawfully exact one price for his goods if they are paid for in cash or payment is made promptly, and he may demand a larger price if the sale is for credit or the cash payment is delayed, and the difference is not interest.
Anguiano v. Jim Walter Homes, Inc.,
Argonaut next complains of the trial court’s failure to grant its motiоn for new trial on grounds of jury misconduct. The motion was supported by the affidavits and testimony of two jurors to the effect that an unidentified juror stated during the jury’s deliberations that he personally receives invoices annually totaling millions of dollars, and that a cash discount of 25% is nоt unusual. Other testimony adduced at the hearing, however, reveals that several of the jurors promptly rebuked the juror who made the comment, and the foreman admonished the other jurors not to consider the remark because they were not allowed to go into such matters. No further discussion or comment upon the subject was had after the rebukes and the admonishment, even though at least five more votes were thereafter taken.
Misconduct of the jury is not grounds for a new trial unless it is established that (1) the improper act in fact occurred; (2) it was material; and, (3) the misconduct probably resulted in injury to the complaining party. Tex.R.Civ.P. 327;
Barrington v. Duncan,
Finally, Argonaut asserts that the jury’s award to ABC for attorneys’ fees is excessive. We agree.
This cause has been tried twice, once before the court for a day and a half, after which the court declared a mistrial, and again for approximately two and a half days before a jury. ABC was represented throughout the proceedings by two firms acting through three attorneys. Testimony was adduced that the attorneys spent 130 hours preparing the case for trial the first time and then spent an additional 200 or more hours on the case between the first and second trial. On the basis of this testimony the jury awarded $16,000.00 as attorneys’ fees.
*889
Attorneys’ fees, where recoverable by law, must be reasonable under the particular circumstances of the case and must bear some reasonable relationship to the amount in controversy.
Republic National Life Ins. Co. v. Heyward,
IT IS SO ORDERED.
