211 F. 50 | 9th Cir. | 1914
(after stating the facts as above).
The court below, upon the consideration of the conflicting testimony of witnesses heard in open court, having found two important facts against the appellant, the only question for consideration here is whether the findings or the conclusions of law are based upon a mistaken view of the law, or an obvious error in applying the evidence. The appellant contends that, in finding that the lien notice was not filed within 30 days from the completion of the building, the court took the erroneous view that, because work upon the building had ceased and the building was occupied, it was completed, although a heating plant had not been installed therein and in other respects the building had not been finished. The lease provided that the building should be equipped with steam heat and radiators, “said steam heat to be either furnished by a boiler in the building or from and through steam pipes from outside the building.” The court below found that, after the execution of the lease, McCauley and Palmer, the lessees, abandoned the plan of installing a heating plant and other features in said building, as provided in said lease, “and adopted different plans, in accordance with terms and plans set out in the written contract with Goodall.” If this were a finding reached upon a consideration of conflicting evidence, it would be conclusive here. But it is not. The court- assumed from the fact that the heating plant was not included in the contract which the lessees made with Goodall, a carpenter and builder, for the construction of the building, and from the fact that the lessees postponed the installation of the heating plant, that the agreement between the lessees
The Mechanic’s Lien Law of Alaska is adopted from the lien law of Oregon, and before its adoption the Supreme Court of Oregon had held, in Avery v. Butler, 30 Or. 287, 47 P. 706, that: “When work demanded by the terms of the original contract has been omitted, the final completion of the structure dates from the time such omissions are sup
And in Crane Co. v. Ellis, 58 Or. 299, 114 P. 475, in a case where the building contract provided that the building should be completed by December 1, 1906, and the work of construction was completed in February, 1907, except for the laying of a cement floor in the basement which, on account of the dampness of the ground was not put in until August, 1907, the date of the laying of the cement floor was taken by the court as the date of the completion of the building.
But the appellee contends that, if the building was not completed when the lien notice was filed, the notice was ineffective and void for the reason that it was filed prematurely and not within 30 days after the completion of the building, and cites decisions of courts which so hold. We are not disposed to follow those decisions, based as they are upon a narrow and technical construction of the lien law. There is no prejudice to any substantial right of the owner of the building in the filing of a lien at any time after the material is furnished, and before the completion of the building. In Wills v. Zanello, 59 Or. 291, 117 P. 291, it was held that this may be done, and that a lien filed before the completion of the building is not filed prematurely. The same was held by the Supreme Court of Nevada in Self & Sellman Mill & Bldg. Co. v. Savage, 123 P. 333. The Supreme Court of Oregon has repeatedly ruled that the Mechanic’s Lien Law should be liberally construed, and this court, in Russell v. Hayner, 130 F. 90, 64 C.C.A. 424, expressly affirmed that doctrine in construing the Mechanic’s Lien Law of Alaska. In Hooven, Owens & Rentschler Co. v. John Featherstone Sons, 111 F. 81, 49 C.C.A. 229, Judge Sanborn said: “Labor and material once bestowed lose all"their value to the laborer or materialman. He cannot take them back. They enhance the value of the property upon which they are placed, and its owner and those who take under him receive all the benefits of the labor and of
We hold that the lien notice in the case at bar was filed in due time.
Assuming, as found by the court below, that within three days from the commencement of the building Borden posted a notice in a conspicuous place thereon that he would not be responsible for any material or work furnished in the construction thereof, the question remains whether he thereby defeated the appellant’s claim of lien. The Code of Alaska, section 262 of chapter 28, Civ.Code, gives a lien to every contractor, lumber merchant, etc., who furnishes material in the construction of a building, for work or labor done or material furnished “at the instance of the owner.” Section 265 provides that every building constructed on any lands with the knowledge of the owner “shall be held to have been constructed at thé instance of such owner,” and that his interest shall be subject to any lien filed in accordance with the provisions of the Code, unless he shall, within three days after he shall have obtained knowledge of the construction, give notice that he will not be responsible for the same by posting a notice in writing to that effect, in some conspicuous place upon the land or in the building. The provisions of section 265 are for the benefit and protection of the owner in cases where the work is not done and the material is not furnished at his instance, or at the instance of his agent. It is not the intention of the law, nor is it the purport thereof, that when in fact the work is done, and the material is furnished at the owner’s instance, he may prevent a lien upon his property by posting the notice referred to in that section. We think that in the case at bar it should be held that the materials supplied by the appellant were furnished at the instance of the owner. On February 17, 1910, he executed a lease of the property for a term of five years to Mc-Cauley and Palmer, in consideration of their agreement to pay $75 per month as rental and to commence and fully finish a building on the premises at their expense, and as a preliminary to the erection of the building he agreed to grade the lot and'put in at his own expense “a good,
It is the general rule that where a lease contains a provision authorizing the lessee to make improvements “by deducting the cost thereof from the rent, or where part of the consideration of the lease is the making by the lessee of improvements which become a part of the realty, or that the improvements made by the lessee shall revert to the lessor, a mechanic’s lien may attach to the property for works done or materials furnished, pursuant to a contract with the lessee.” 27 Cyc. 58; Kremer v. Walton, 16 Wash. 139, 47 P. 238; Shaw v. Spencer, 57 Wash. 587, 107 P.
In Crandall v. Sorg, where the owner of vacant premises leased the same for 99 years at an annual rental, and by contract the tenant was to construct upon the premises a building at a cost of $300,000, of which $100,000 was to be contributed by the lessor, and by the contract it was provided that the property should be insured, and in case of loss the amount' recovered should either be used in reconstruction or be paid to the lessor, it was held that the lessor’s interest was subject to a mechanic’s lien, notwithstanding that the contract provided that there should be no lien thereon.
The decree is reversed, and the cause remanded to the court below for further proceedings and with instructions to enter a decree for the appellant in accordance with the finding as to the amount due it.