*1
FOSHEIM,
WUEST,
conclude, therefore,
C.J.,
that
the trial
Circuit
We
Acting
Justice,
holding
January
Judge,
Supreme
as
in
that the
Court
court erred
by
specially.
agreement
par-
concur
was intended
support.
child
to fix the amount of
ties
WUEST, Acting
(concurring spe-
Accordingly,
the order inas-
we reverse
cially).
modify
attempted
as it
the child
much
ease,
I
with
concur
the result in this
decree in
support portion of the divorce
agree
contempt
cannot
to col-
be used
interpreta-
accordance with
trial court’s
past
housing
due
lect the
allowance be-
January
agreement.
of the
tion
entered,
cause no order was
which has
however,
mean,
This does not
could,
However,
been violated.
the court
be
upon remand Sharon should
entitled to
opinion,
my
in
enter an
order based
agreement
January
enforce the
January
supplemental agreement
by
contempt
action
of a
the divorce
means
which,
violated,
later
appro-
if
could under
above,
pointed
proper
As
out
citation.
priate
by
circumstances be enforced
con-
rights
ty
parties
by
fixed
were
tempt.
terms of the 1979
decree. There
divorce
agree
majority opinion regard-
after, any
rights
those
modification of
ing
attorney
future allowances for
fees. A
only
by way
agree
occur
could
bilateral
past
judges
pos-
decision indicates
are
parties
ment of the
as manifested
a
special expertise
fixing
sessed
attor-
agreement.
Inasmuch
valid contractual
as
Hetland,
ney fees. See
Scott v.
S.D.
interpreted
January
we have
that;
552,
reasonable fees incurred note, however,
ing appeal. this We that no fees,
separate motion for attorney nor an thereof,
itemized statement in support appeal. been filed in this connection with CO., INC., ARCON CONSTRUCTION a upon we have little which to Corporation, Hardrives, Minnesota any appellate attorney base award of fees. Inc., Corporation, a Minnesota Plain- Accordingly, we will limit our award to Appellees, tiffs and $500.00. Following the date of the remittitur DAKOTA DEPARTMENT OF SOUTH action, in this we will not consider a re TRANSPORTATION, Defendant quest attorney appeal fees on domes Appellant. tic relations cases unless there submitted No. 14510. separate motion, accompanied by to us counsel's verified statement of itemized Court Supreme of South Dakota. legal costs incurred and services rendered. Argued Feb. 1985. appealed The order from is reversed and April 3, Decided the case is remanded to the circuit court. HENDERSON, JJ.,
MORGAN and con-
cur. *2 Schmidt, Schroyer,
Ronald G. Schmidt of Zinter, Pierre, plaintiffs Colwill & appellees. Groseclose, Wayne
Chester A. Jr. and F. Gilbert, Gen., Sp. Attys. Pierre, Asst. appellant; defendant and Mark V. Meier- Gen., Pierre, henry, Atty. on the brief. WUEST, Acting Justice. appeal money judgment
This is an from a against the South Dakota Transportation (Department) arising from a road performed by construction contract (Arcon). Arcon Company Construction We affirm. May 30, 1978,
On
Arcon entered into a
contract with
for the construc-
tion of nine and one-half miles of U.S.
Highway
“Brown-Spink
as the
known
Project.” Arcon then contracted with the
(Plant)
South Dakota Cement Plant
for the
8,900
delivery
approximately
tons of ce-
job
per-
ment to the
site
truck. Plant
they
sonnel told Arcon
intended to deliver
the cement to
via the
Aberdeen
Milwaukee
Railroad, and truck it from the Aberdeen
job
terminal to the
site. The construction
completion
contract carried a
date of No-
1, 1978,
vember
and Arcon received notice
project
proceed
to
on the
on June
1978.
Plant, however,
The Cement
was unable to
deliver the cement called for under its con-
Arcon
of a cement
tract with
because
shortage. The failure of Plant to deliver
the cement rendered Arcon unable to com-
plete
project
Recognizing
1978.
paving
completed
could not be
charge any working
Department did not
“Brown-Spink Project” during
days to the
construction season. Arcon re-
the 1978
quested
completion
a new
date of Novem-
1, 1979,
project. Department
for the
ber
granted
71-day
them a
extension commenc-
4, 1978,
ing April
1979. On December
expected
it
advised
begin paving
“Brown-Spink Project”
15,1979,
approximately
requested
June
any delivery problems
that it be advised of
during the 1979
On
construction season.
April
personnel met with
employees
purpose
for the
of discuss-
project during
Arcon then commenced suit
De-
ing shipments to Arcon’s
recover,
alia,
again
partment seeking
inter
in-
1979 season. Arcon
advised
begin paving
creased
rates and fuel
intended
Project”
alleging
that its total claim
“Brown-Spink
on or about June
$70,249.44
originally
of which
action,”
“separate
had been awarded in a
similarly-
April
In
on a
bid
*3
therefore entitled
the dif-
to
runway
a
at the
project
paving
sized
for
$32,076.44.
ference of
Arcon later amend-
airport. The Sioux Falls air-
Sioux Falls
$59,154.05which,
lawyer
ed its claim to
its
completion
port project had a
date of Octo-
explained,
sought
the full amount
in
was
damages
liquidated
It had a
ber
case,
amount
including
the
the
Plant
$11,000.00
provision
per day,
for
whereas
case,
approximately
awarded in that
less
Project”
provision
a
“Brown-Spink
the
had
$11,000.00
represented the “claim of
which
per day.
liquidated damages
for
of $500.00
another subcontractor.”
18, 1979,
May
until
From
October
very
judicial
the
The trial
took
performed
Arcon
little work on
court
this case
transcript
pleadings
“Brown-Spink Project.” The contract be- notice of the
prior
tween
and Arcon contained a Plant’s case. Twice
to trial and
evidence,
provision
again
Depart-
Arcon of
at the
for reimbursement
close of the
costs, including freight
increased
rates and ment moved to dismiss this case on the
costs,
unexpected
grounds
estoppel, urging
fuel
were
at the
of collateral
which
bidding.
provi-
already
time of
It also contained a
the issues raised
this case had
if
completion
sion for extension of the
date
been tried in the
case. The motions
delay
there
as the result were denied. The same motion
re-
was
work
was
unanticipated delays, beyond
subsequent
In
the con- newed
to trial and denied.
control,
action,
delivery
present
tractor’s
of critical
the
used the
Plant, i.e.,
as
material.
same defense
that Arcon’s
timely completion
failure of
was due to the
Department, believing the contract had
equipment
fact that their
was committed to
timely performed,
liqui-
not been
assessed
airport job.
the Sioux Falls
Arcon’s claim
damages against
dated
the sum of
non-delivery
cases
both
of ce-
$40,500.00
delay
completion
for
timely comple-
ment caused the failure of
contract.
jury
tion. The
returned a verdict for Arcon
Arcon sued Plant for failure to deliver
liquidated
for the
assessed as
the cement under their contract.
Ar
See
damages
freight
and the
rates and fuel
con
v.
Constr. Co. South Dakota Cement
asked, $57,-
in the amount
Plant,
(S.D.1984).
349
407
N.W.2d
Arcon n 164.05.
sought recovery
liqui
from Plant for the
Department claims that
the trial
damages
by Department
dated
assessed
for
failing
apply
court erred in
the doctrine
complete
failure to
con
construction
estoppel.
must,
of collateral
There
how
freight
tract on time and also for increased
ever,
judgment
a final unreversed
be
or
surcharges.
rates and fuel
Plant defended
competent jurisdiction
decree of a court of
claims,
alleging
these
that Arcon’s
judicata,
the doctrines of
before
res
collat
assumption
airport
of the Sioux Falls
estoppel,
preclusion apply.
eral
or issue
subsequent
project
equipment
schedul
Jewelry Mfg.
Black Hills
v. Felco Jewel
ing decisions were the reasons Arcon was
Ind.,
(S.D.1983);
South cement in Eastern South Da-
transporting altogether matter. different is an kota pre- issue
Therefore, estoppel or collateral inapplicable as the issues these
clusion readily distinguishable. cases are two
WOLLMAN, (dissenting). majority opinion makes abundant-
As the clear, sought recovery in the
ly Ce- liquidated case for the dam-
ment for failure to
ages assessed on time the construction contract
complete freight rates
and also increased surcharges. was awarded noth-
fuel damages claim liquidated
ing on the
only on the increased fuel claim. did
rates and respect file a notice review
not Accordingly, however infeli-
those issues.
citously dispositive paragraph worded opinion
in our the Cement case *5 been,
may have 349 N.W.2d not have re-
fact remains we could judgment respect those hold
two issues. would precluded by judgment
Arcon was relitigating Plant case from and
the issues case at bar would from. judgment appealed
reverse
I am authorized to state joins in this dissent.
MORGAN Evans, Evans, Davenport, E.
Edwin Falls, Smith, plaintiff & Sioux Hurwitz CO., TAYLOR REALTY a South Schaffer, Dav- J. appellant; Michael Corporation, Dakota Plaintiff Smith, Evans, & Sioux enport, Hurwitz Appellant, Falls, on brief. Cadwell, Sanford, & W. Sanford Steven HABERLING, Bill Defendant Deibert, Falls, ap- for defendant and Sioux Appellee. Cadwell, Garry, of San- pellee; William C. No. 14113. Falls, Deibert, on brief. ford & Sioux Supreme Court Dakota. of South MARTIN, Judge. Circuit on
Considered Briefs Jan. Plaintiff, Realty Company, ap- Taylor April 10, 1985. Decided peals from from a subse- denying order its motion for a new quent damages. We affirm. trial issue
