Architectural Builders, Inc. v. PollardArchitectural Builders, Inc. v. Pollard
Appeal from an order of the Supreme Court (Rumsey, J.), entered September 8, 1998 in Tompkins County, which granted defendants’ motion for summary judgment dismissing the complaint.
In June 1994, plaintiff submitted proposals for three separate phases of renovation which defendants desired to be made to their home to improve its usefulness as a bed and breakfast facility. Each proposal contained a fixed price for the anticipated work and a provision indicating that extra work and/or change orders would be discussed, authorized and paid upon completion of work upon invoice, either at an agreed price or time and materials, plus overhead. One of the proposals had attached to it a document entitled “Provisions of the Agreement” which contained, inter alia, a requirement that any action related to the project brought by either party against the other must be brought within six months of the completion of work. Each proposal contained a statement “contract to follow”. Although no other contracts were prepared, and despite the fact that defendants never signed the proposals, plaintiff completed the work on December 24, 1995.
On November 13, 1996, plaintiff brought this action to recover sums allegedly due and owing for work performed for defendants. Following joinder of issue and substitution of counsel for the defendants, defendants’ motion to amend the answer to include the affirmative defense of the Statute of Limitations was granted by order of Supreme Court on March 12, 1998. Following the completion of examinations before trial, defendants moved for summary judgment dismissing the complaint on the basis of the contractually shortened Statute of
Initially, we note that the propriety of Supreme Court’s grant of leave to defendants to amend their answer to include the affirmative defense of the Statute of limitations is properly before us. The order entered September 8, 1998 which granted defendants’ motion for summary judgment dismissing the complaint was, in effect, a final order which brings up for review the earlier nonfinal order of March 12, 1998 (see, CPLR 5501 [a]; see also, Herrmann v Bilka,
Next we turn to the propriety of Supreme Court’s dismissal of the complaint premised upon the contractual Statute of Limitations defense. Paragraph VI (b) of the “Provisions of the Agreement” states: “Attorney’s fees: If either party becomes involved in litigation arising out of this [ajgreement, the court shall award costs/expenses, including attorney fees to the party justly entitled to them”.
Supreme Court found it was inconsistent for plaintiff to seek to recover counsel fees pursuant to this paragraph and at the same time deny the existence of the contract for other purposes, including the shortened Statute of Limitations. Accordingly, Supreme Court determined that the three proposals, including the “Provisions of the Agreement”, “became the enforceable contract binding on the parties”. We believe, based on this record, that this determination is correct. Nevertheless, we must reverse the dismissal of the complaint.
The aggregate amount due under the three proposals was the sum of $114,645.01. However, the complaint claims that
The proposals anticipate further agreement between the parties as to extra work and/or change orders. If such work was not within the scope of that called for by the contract, the terms and conditions of the contract would have no application (see, Savin Bros. v State of New York,
Cardona, P. J., Mikoll, Crew III and Yesawich Jr., JJ., concur. Ordered that the order is reversed, on the law, with costs, and motion denied.