Archer v. Milwaukee Auto Engine & Supply Co.

144 Wis. 476 | Wis. | 1911

Barnes, J.

The plaintiff was the owner of a boat and an engine. The defendant agreed to furnish the necessary connections and accessories and install the engine in the boat under a certain warranty as to material and workmanship, in consideration of $227.72. This action is brought to recover damages for breach of the warranty. The sixth question in the special verdict and the answers thereto were as follows:

“6. If the court should be of the opinion that the plaintiff is entitled to recover against the defendant in this action, what sum will reasonably compensate the plaintiff:
“(a) Eor the difference in value between the connections,, accessories and labor furnished, and that called for by the contract ?
“(b) Eor the expenses actually incurred by the plaintiff in putting the connections, accessories and installation work in the boat in a condition to correspond with the contract ?
“(c) Eor the reasonable value of the use of the boat after the 15th of August, 1907, during the boat season of 1907 2
“Answer: (a) 67.00 dollars.
(b) 96.00 dollars.
(c) 190.00 dollars.
353.00 dollars.”

*478Judgment was entered on the verdict for $353 damages and costs. Defendant appeals. Uo bill of exceptions was settled. The question is, Does the verdict support the judgment?

The rule of law fixing the measure of damages recoverable is well settled. Plaintiff was entitled to recover the difference between the value of the boat in the condition in which it was delivered and what its value would have been had the contract been complied with, as well as such special damages as were properly shown. Fisk v. Tank, 12 Wis. 276, 309; J. Thompson Mfg. Co. v. Gunderson, 106 Wis. 449, 458, 82 N. W. 299. The first subdivision of the question called for every item of general damages which plaintiff was entitled to. The second subdivision was improperly submitted to the jury for two reasons: Eirst, because the item of labor expense in putting the boat in the condition in which the defendant agreed to place it wasmovered by subdivision (a) of the question, and, second, because if it was desired to secure a second answer showing the damage suffered by plaintiff on account of had workmanship, the question should have called for the amount reasonably and necessarily expended in making the repairs. The plaintiff might have incurred an unreasonable and unnecessary expense in doing the work. But such a finding would not assist in determining the damage sustained in the absence of another directed to the damage resulting from the poor material furnished. The first question is not confined to the materials used, but covers the labor cost of making the repairs as well. There is no escape from the conclusion that damages were duplicated, if it be conceded that the second question could have any proper place in the verdict.

The damages covered by subdivision (c) of the question are special, and it is urged that such damages are not recoverable under the complaint. In the absence of a bill of exceptions we must presume that the complaint was properly *479amended, if amendment were necessary. Kane v. Williams, 99 Wis. 65, 74 N. W. 570. It is further urged that the special damages recovered were not fairly within the contemplation of the parties; that they were uncertain and speculative; .and that the defects in the boat could readily have been remedied, and that plaintiff was obliged to minimize his damages by using reasonable diligence to repair the defects. We have no means of knowing whether these contentions are well founded in fact or not. If, under any proof that might have been offered, it could be said that the damages assessed were within the contemplation of the parties, we must presume that such evidence was offered, and it is not difficult to imagine a state of facts which would render such damages entirely proper. So, too, we are not able to say that these damages were not made definite and certain by the evidence, because we do not know what the evidence was. Reither can we say that facts were not shown which excused the plaintiff from making the repairs sooner than he did, or that it did not affirmatively appear that it was impossible to make them sooner. In order to review these questions it is essential that the evidence be made a part of the record.

Our conclusion is that the item of $96 should be stricken from the judgment as of the date of its entry, and that as so modified the judgment should be affirmed.

By the Court. — The judgment appealed from is modified by striking therefrom the sum of $96, as indicated in the opinion, and as so modified the judgment is affirmed; costs to be awarded to the appellant in this court.