AQUATIC PLANT MANAGEMENT, INC., Appellant,
v.
PARAMOUNT ENGINEERING, INC. and American Safety Casualty Insurance Company, Appellees.
District Court of Appeal of Florida, Fourth District.
*601 Douglas J. Roberts of Leiby Stearns and Roberts, P.A., Fort Lauderdale, for appellant.
Guy W. Harrison, Jeff Geller and Edward Etcheverry of Etcheverry Harrison LLP, Fort Lauderdale, for appellee American Safety Casualty Insurance Company.
STEVENSON, J.
The issue in this appeal is whether an unpaid subcontractor on a public project can state a claim against the issuer of the statutorily-required payment bond when the materials for which the subcontractor seeks recovery were neither delivered to the site nor incorporated into the project, but were nevertheless "specially fabricated" for the job. Because the legislature has made persons furnishing labor, services or materials who may qualify as claimants under the public project payment bond law (chapter 255) consistent with those who qualify as lienors under the mechanics' lien law (chapter 713), and since specially fabricated materials are an exception to the delivery or incorporation requirements for those persons under chapter 713, we answer the question in the affirmative. We therefore reverse the order dismissing the subcontractor's claim against the payment bond.
In March 2004, the City of Coral Springs entered into a contract with Paramount Engineering, Inc., for the construction or creation of the "Coral Springs Sportsplex Wetland Creation Project" on publicly-owned property in Broward County. Paramount subcontracted with Aquatic Plant Management, Inc. The contract between Paramount and Aquatic required that Aquatic install a drainage system, and provide and install certain plants. The contract provided that any delays to planting beyond six months would result in maintenance fees to the contractor.
*602 In October 2005, Aquatic brought suit against Paramount and American Safety Casualty Insurance Company, the issuer of the payment bond required by section 255.05, Florida Statutes (2006). Counts I and III of the Amended Complaint stated a claim against Paramount for breach of contract and unjust enrichment/quantum meruit, respectively, alleging the failure to pay Aquatic for the plant materials and the maintenance of these plants when they were not installed as contemplated by the contract. Count II sought relief against both Paramount and American under the payment bond.
American filed a motion to dismiss count II, arguing that Aquatic could not state a claim for recovery under, the payment bond because section 255.05 requires "incorporation" of the materials into the improvement and, while Aquatic alleged the plant materials were "specially fabricated," there was no "specially fabricated" materials exception to chapter 255's "incorporation" requirement. Alternatively, American argued the claim was barred by the statute of limitations. The trial court granted the motion to dismiss without prejudice, finding that Aquatic was a subcontractor; that the "goods manufactured" by Aquatic did not constitute "specially fabricated" materials; and that the goods were not incorporated into the improvement.
Aquatic filed a Second Amended Complaint, adding factual allegations to support its claim that the materials were "specially fabricated," i.e., the contract required it to grow and maintain plants that were not available on the open market, specific to the project, and not suited for use in another project. American again sought dismissal, raising the same arguments advanced in its earlier motion. This time, the court dismissed the claim with prejudice finding "incorporation" of the materials into the improvement is a predicate to claim under section 255.05. The court declined to address American's alternative argument concerning the statute of limitations.
The issues raised here are ones of law, i.e., the dismissal of a claim for failure to state a cause of action and the construction to be afforded section 255.05, and thus subject to de novo review. See Am. Honda Motor Co. v. Cerasani,
Chapter 713, Florida Statutes, governs mechanics' liens on privately-owned property and provides for a lien in favor of those "who perform labor or services or furnish materials constituting an improvement." See § 713.02(3)-(4), Fla. Stat. (2006). These classes of persons, including "materialman," "laborer," and "subcontractor" are defined by chapter 713. A materialman is one who furnishes materials but not labor, and a laborer furnishes labor but not materials. See § 713.01(15), (19), Fla. Stat. A "subcontractor" is one who is contractually obligated to perform a specific part of the contractor's contract, i.e., labor, services, or the furnishing of materials in accordance with the specifications of the primary contract. See § 713.01(27), Fla. Stat.; see also § 713.06(1). Moreover, to "furnish materials" means to "supply materials which are incorporated in the improvement . . .; or specially fabricated materials for incorporation in the improvement." § 713.01(12), Fla. Stat. *603 (emphasis added). As a consequence of these definitions, under chapter 713, in order for one who has furnished materials to have a lien, the materials must either be "specially fabricated" or actually incorporated into the improvement. See Dublin Co. v. Brady Sales, Inc.,
Chapter 713, though, expressly exempts from its scope property owned by the state and its subdivisions. See § 713.01(22), Fla. Stat. Thus, to protect those who work on public projects, the legislature enacted chapter 255. See Fla. ex rel. Westinghouse Elec. Supply Co. v. Marvin,
American insists the answer is "no," citing Clutter Construction Corp. v. Florida ex rel. Westinghouse Electric Corp.,
This, then, leaves us with the language of the statute: "Such bond shall be conditioned upon the contractor's performance of the construction work in the time and manner prescribed in the contract and promptly making payments to all persons defined in s. 713.01 who furnish labor, services, or materials for the prosecution of the work provided for in the contract." § 255.05(1)(a), Fla. Stat, (emphasis added). Subcontractors are persons defined in section 713.01 and may perform labor and services or furnish materials. See §§ 713.01(27), 713.06(1), Fla. Stat. And, under section 713.01(12), "furnish materials" means either to supply materials that are incorporated into the improvement or to supply "specially fabricated" materials.
Having first viewed the text of the relevant statute and finding its meaning less than clear, we must next look to discern legislative intent as it is the "polestar" which guides our statutory construction analysis. See State v. J.M.,
As for American's alternative statute of limitations argument, a motion to dismiss may be granted on statute of limitations grounds "`where the facts constituting the defense affirmatively appear on the face of the complaint and establish conclusively that the statute of limitations bars the action as a matter of law.'" Bott v. City of Marathon,
Reversed and Remanded.
SHAHOOD, C.J., and BELANGER, ROBERT E., Associate Judge, concur.
