183 A.D.2d 1055 | N.Y. App. Div. | 1992
Appeal (transferred to this court by order of the Appellate Division,
Plaintiff and defendant AARK Construction Corporation (hereinafter defendant) entered into a written contract under the terms of which plaintiff was to dredge material from the bottom of the Hudson River in connection with the development of the area as a marina. Compensation was fixed at $250 per hour of operation in pumping, moving pipelines or equipment related to dredging, or servicing the dredging plant. The contract also provided for a maximum or "upset” price of $75,000 for the area described as "Phase I” and $60,000 for "Phase II”, and stated that in the event the cost computed on an hourly basis was less than the upset price, the parties would share the savings equally. Plaintiff began its dredging operations on December 22, 1988 and worked continually until March 3, 1989, when defendant directed that it discontinue operations due to lack of funds. Plaintiff subsequently commenced this action to recover for defendant’s breach of the contract. The matter ultimately came on for a nonjury trial, following which Supreme Court rendered judgment in favor of plaintiff in the amount of $105,724, together with interest from April 3, 1989. Defendant appeals, challenging only Supreme Court’s award of damages.
Had plaintiff been permitted to complete the contract, computation of its damages would have been an easy matter. The total number of hours expended on the project would be multiplied by $250, and the product (hereinafter the hourly price) would be compared to the total upset price. If the hourly price was equal to or exceeded the upset price, then the upset price would be paid. If the hourly price was less than the upset price, then plaintiff would be paid the hourly price plus one half of the difference between the upset price and the hourly price, to permit an equal sharing of the savings. However, with the contract only partially completed, Supreme Court was faced with the difficult task of prorating the upset price to the work actually performed.
Determining that plaintiff’s invoices furnished the most credible evidence on the issue (see, Dobert Constr. Corp. v Holser Excavating, 36 AD2d 1002, 1003), a finding which the record amply supports, Supreme Court first considered plaintiff’s February 8, 1989 invoice for the period December 28, 1988 to January 31, 1989, which showed that plaintiff had expended 228 hours of work and completed approximately
The contention that plaintiff failed to come forward with prima facie evidence of damages is primarily based upon the fundamentally erroneous premise that plaintiff’s damages may be established only by evidence of the actual volume of fill removed from the river bottom. To the contrary, because the contract provided for compensation on the basis of the hours of work performed, subject only to the upset price, there was no reason for plaintiff to have measured or maintained a record of the volume of material removed. We also disagree with defendant’s reliance upon the contract’s provision that monthly requisitions be paid on the basis of the percentage of work satisfactorily completed. The mode of submitting invoices and calculating intermediate payments became irrelevant at the time of defendant’s breach of the contract, when plaintiff became entitled to immediate payment for the work that had been performed and lost profits on the balance of the job (see, 36 NY Jur 2d, Damages, § 47, at 80-81).
In our view, Supreme Court made the best of a very difficult situation and formulated an award of damages which reason
We have examined defendant’s remaining contentions and find them to be without merit.
Mikoll, J. P., Yesawich Jr., Crew III and Casey, JJ., concur. Ordered that the judgment is modified, on the law, with costs to plaintiff, by reducing the award of damages to $104,704, together with interest from April 3, 1989, and, as so modified, affirmed.
Supreme Court made mathematical errors in two of its computations. The cumulative effect of arriving at a quotient of $2,985 instead of $2,965 and at a product of $8,614 instead of $7,614 was a $1,020 overstatement of damages. Supreme Court’s judgment must be modified accordingly.