This is a suit by a furnisher of material to recover on a contractor's bond for the default of a subcontractor. The plaintiff appealed from a judgment in its favor on the ground that the recovery was not adequate.
Defendants Boone, Eason Wood (hereinafter called the contractors) constructed the Mercer County courthouse in 1930-1. Defendant Fidelity Deposit Company was surety on their bond. They sublet the marble, tile and terrazzo work and the slate window stools to R. N. Vanderberry for $15,000, without any bond from him to secure them, and with the following provision in the contract as to payments: "The monthly payments on contracts in course of execution shall be made within fifteen days after the submission of estimates for payment and shall be based on 90% of the value of the work set in place up to the date of the submission of the same, plus 85% of the set value of all material delivered at the *Page 308 building, whether installed or not. Final payment in full shall be made within thirty days from the completion and acceptance of the * * * work."
Vanderberry purchased from the plaintiff the marble required at a total cost of $5,624.64. None of this amount was paid and the subcontractor has been adjudicated a bankrupt. There were two main shipments of marble, one on April 23, 1931, amounting to $2,500.00 and the other on May 7, 1931, amounting to $2,870.00. Small shipments for replacements were made in June and July of 1931, amounting to $254.64. There is no dispute as to any of these items.
On May 1, 1931, the contractors were allowed an estimate of $13,000.00 exclusively on the work of Vanderberry and were paid 85% of that estimate by the county. On that day they paid Vanderberry $3,000.00. On May 7th they mailed the plaintiff a letter which is in part as follows: "We will be pleased to have you advise us the amount of your account and how you wish us to handle this in order that we may know that you are paid for this material." On that same day the plaintiff wired the architect in charge of the construction, "Satisfactory with us to pay Vanderberry on estimates when due." The architect forthwith delivered the telegram to the contractors. Following which they made further payments to Vanderberry of $2,000.00 on May 8th, $2,500.000 on May 11th, and $1,000.00 on May 22nd. On May 24th they received from plaintiff a letter written on May 22nd, which charged its delay in answering the contractors' letter of May 7th to the dalliance of Vanderberry, notified the contractors of the shipments of April 23rd and May 7th, and requested them to protect its interest. The contractors also received from the architect on May 24th a copy of a letter to him from plaintiff directing him to disregard the telegram of May 7th. No further payments were made to Vanderberry after May 24th. On June 1st the architect made the contractors a further estimate of $4,000.00 on Vanderberry's work. He abandoned his contract the early part of June, and it was then completed by the contractors.
The contractors did not answer plaintiff until June 18th, when they wrote that Vanderberry's balance with them as of that date was approximately $5,500.00, subject to be reduced *Page 309 by "the payroll" and by some cement they had furnished him, and that they would hold the balance, etc. Some other letters were exchanged during the summer months of 1931, in which the plaintiff kept demanding that the balance due the subcontractor be paid to it, and the contractors kept postponing such payment, at first because plaintiff had not secured an order from Vanderberry for the balance, and later because the building was not yet completed. On September 15, 1931, the contractors notified plaintiff that the balance due Vanderberry then was $2,314.41, which they offered to pay to plaintiff, if it would guarantee them against any action of any of his creditors against them, and would also assign to them its claim against them and their surety arising out of the subcontractor's default. The tender was not accepted and plaintiff sued for its entire claim of $5,624.64. The circuit court found in its favor for the above balance of $2,314.41.
The law applicable to this case is well settled and it is mainly a problem in mathematics. There is no evidence on the correctness of the estimates of the architect or of the entire cost of the Vanderberry work. One would infer that the estimates were too liberal or that the work cost more than $15,000.00, the contract price. Be that as it may, the bond herein obligates the contractors and the surety (under Code 1923, ch. 75, sec. 12) to pay in full for all materials used in the construction of the courthouse, irrespective of loss to them through the default of a subcontractor. It makes no difference whether the materials are furnished to the principal contractors or to a subcontractor. Hibner v. Ebersbach,
This case does not call for a determination of which party is the more innocent in order to cast the loss on the other, as the brief of the contractors contends. The rule we must apply comes not from equity but from the statute. Under the *Page 312 statute the contractors could not prefer themselves to a materialman. They could not escape loss at the expense of the plaintiff. Besides, we find no equity in favor of the plaintiff relating to the $5,404.80.
The mechanic's lien law, Code 1923, chapter 75, section 6, releases a building from the lien of a materialman if he fails to furnish the owner of the building an itemized statement of materials furnished within ten days after receiving a written request from the owner for such statement. We held inRhodes v. Riley,
The brief calls attention to a letter from plaintiff to the contractors dated July 14, 1931, asking only for the balance due Vanderberry after the completion of the job. It seems from the correspondence that plaintiff was misinformed both as to the amount of the balance and as to its legal rights. The letter of July 14th was not received until after the job was virtually completed and its offer therein was never unequivocally accepted by the contractors. No prejudice to the contractors from the letter is pointed out in the brief, and we perceive none. We are therefore of opinion that the plaintiff is not estopped by the offer.
The decree of the circuit court is accordingly reversed and the cause remanded.
Reversed and remanded. *Page 313
