The plaintiffs’ declaration (the claim) sought damages for the defendant’s alleged breach of contract in failing to remové fill from the plaintiffs’ gravel
On August 15, 1966, the plaintiffs, as sellers, and the defendant, as buyer, executed a one-page agreement, entitled “Contract Terms,” prepared by and on the letterhead of a broker, for the purchase and sale of 150,000 yards of fill at twenty cents a yard, the fill to be removed by the buyer from the plaintiffs’ pit at Easton, Massachusetts. There was provision that the buyer was in certain events to pay the wages of a checker; that the removal was under the sellers’ permit and removal by other contractors was not to be allowed for a period of four months after operations under the agreement had begun; that the buyer was to deposit $5,000, from which the sellers were to pay $1,500 to the named broker (with a pro rata refund by the broker if less than 125,000 yards of fill was purchased by the buyer); that the buyer was to pay the broker $2,000 within sixty days after removal began; and that, after the sellers had used up the balance of the deposit by reimbursing themselves for the first fill taken, they were to bill the buyer bi-weekly for further
It appears that the defendant took about 21,000 yards of fill from September 16 to October 21, 1966. The city of Brockton rejected the fill as unsuited to the particular job of preparing a site for a high school, the rejection being shown by a letter of September 30 from the Brockton clerk of works to the defendant. Thereafter the defendant declined to take any additional fill from the plaintiffs, and pointed to the agreement for termination above mentioned.
The plaintiffs contended that there was no such agreement; they also intimated that such an agreement could not in any event be given effect in the face of the written contract of August 15, that is to say, the contingency paragraph of the contract of August 15 so far “integrated” its subject matter as to exclude by reference to the paroi evidence rule the recognition of an agreement regarding acceptability of the fill to the Brockton authorities.
The parties have addressed themselves to these issues on the merits, and we do also, although, as will be seen below, there is much doubt whether they are properly presented for review.
1. Whether there was an integration as the plaintiffs contended was a question of the intention of the parties on which proof could be received ranging beyond the writing proper.
Carlo Bianchi & Co. Inc.
v.
Builders’ Equip. & Supplies Co.
The record does not contain any specific evaluation of this evidence by the judge, but we think that, considered on the preliminary issue of integration, see
Caputo
v.
Continental Constr. Corp.
But if it were held that there was an integration excluding an effective agreement outside the writing, the judge’s decision on the claim could still be supported. Paragraph 6 is not self-interpreting — no form of words is — and the evidence could be received and used to elucidate its meaning in context.
Robert Indus. Inc.
v.
Spence, ante
751, 753.
Imper Realty Corp.
v.
Riss,
2. It requires some charity toward the plaintiffs to assume that the substantial issues centering on the paroi evidence rule are here for review. The plaintiffs excepted to the denial of their motion for a new trial on the claim, the motion having assigned as reasons that the finding on the claim was against the evidence, the weight of the evidence, and the law; but in these circumstances the motion seems misused.
Scano, petitioner,
3. The finding for the defendant on the counterclaim was attacked by the new-trial motion as being against the law, but, passing the procedural difficulty, there was no basis for questioning that finding if the plaintiff failed on the claim. Thus the defendant is entitled to a return of the deposit of $5,000, which it paid in, but subject to the deduction of any charges that may be appropriate, such as charges found appropriate for the fill actually taken by the defendant. The record does not indicate whether such charges were analyzed nor does the finding mention any amount due. Perhaps this determination was left open until the time for entry of judgment.
The present exceptions are overruled. Within sixty days of the date of the rescript, either party may apply to the Superior Court for determination of the amount that may be owing on the counterclaim. Judgment shall be entered after this determination, subject to any fresh exceptions.
So ordered.
Notes
A defence based on alleged fraud of the plaintiffs need not be pursued here.
Paino also testified that the contract with the city of Brockton gave the defendant a choice between using free fill furnished by the city of Brockton subject to charges for hauling, and obtaining it elsewhere.
On the question of integration, it does not make an important difference whether acceptance of the fill by Brockton is seen as a condition of the formation of any contract between the plaintiffs and the defendant, or (as we think the more reasonable interpretation) a condition of performance by the defendant under a formed contract. See Corbin, Contracts, § 589 (note the treatment at pp. 546-547 of
Tilo Roofing Co. Ino.
v.
Pellerin,
The question inquired about the conversation between Antonellis and Paino in which Paino specified that if the material was not acceptable to the Brockton engineer the deal would have to he “cancelled.”
