431 Mass. 763 | Mass. | 2000
Annese Electrical Services, Inc. (Annese), brought suit against the city of Newton (Newton), claiming that it was
1. Background facts. We summarize the material facts which are undisputed and present only a question of law.
*765 Company Base Bid
Campbell Electric, Inc. $496,000
The Sentry Corporation $620,000
James Galvin Electrical Contracting Corp. $675,000
Annese Electrical Services, Inc. $855,000
CNM Electrical Construction, Inc. $883,000
The bids, including limitations as to use by general contractors, were placed on a list and sent to “every person on record as having taken a set of plans and specifications,” conformably with G. L. c. 149, § 44F (3).
On June 14, 1995, the general bids were opened. Later that day Campbell Electric, Inc. (Campbell), and James Galvin Electrical Contracting Corp. notified Newton that they had made errors in their bid calculations and requested withdrawal of their bids. Newton determined that each subcontractor had made a bona fide clerical error of a substantial nature in its bid and returned their bid deposits.
On July 7, 1995, Newton awarded
On August 10, 1995, Newton and TLT executed the general contract, which contained a clause stating that Sentry was entitled by statute to withdraw its bid, that Newton intended to rebid the electrical work, and that the parties agreed to amend the contract to reflect the bid price of the lowest responsible and eligible electrical subbidder in the second round of bidding. On August 21, 1995, the second round of electrical subbids were opened, the results of which were as follows:
Company Base Bid
CNM Electrical Construction, Inc. $663,000
Annese Electrical Services, Inc. $696,000
James Galvin Electrical Contracting Corp. $805,000
In the interim, on August 11, 1995, Annese protested the second solicitation for electrical work to the Commissioner of Labor and Industries (commissioner), pursuant to G. L. c. 149, § 44H. The protest was heard by the Attorney General, the commissioner’s designee.
2. Overview. General Laws c. 149, §§ 44A-44H, is known as the competitive bidding statute. It provides comprehensive and detailed requirements for public agencies that award building contracts estimated to cost more than $25,000. G. L. c. 149, § 44A (2). “We construe G. L. c. 149, §§ 44A-44[H], as we must, in light of the legislative objectives which were served by its enactment so as to effectuate the purpose of the framers.” John T. Callahan & Sons v. Malden, 430 Mass. 124, 128 (1999), quoting Interstate Eng’g Corp. v. Fitchburg, 367 Mass. 751, 757 (1975)." The purposes of the competitive bidding statute are “to ensure that the awarding authority obtain the lowest price among responsible contractors” and “to establish an open and honest procedure for competition for public contracts.” John T. Callahan & Sons v. Malden, supra, quoting Modern Cont. Constr. Co. v. Lowell, 391 Mass. 829, 840 (1984), and James J. Welch & Co. v. Deputy Comm’r of Capital Planning & Operations, 387 Mass. 662, 666 (1982). The statute “places all general contractors and subbidders on an equal footing in the competition to gain the contract.” John T. Callahan & Sons v. Malden, supra. Interstate Eng’g Corp. v. Fitchburg, supra at 757-758. “The statutory procedure facilitates the elimination of favoritism and corruption as factors in the awarding of public contracts and emphasizes the part which efficient, low-cost operation should play in winning public contracts.” John T. Callahan & Sons v. Malden, supra. Interstate Eng’g Corp. v. Fitchburg, supra.
3. Newton’s discretion to resolicit bids. Annese argues that because Newton had “received” five bids in response to the first solicitation it was not entitled to resolicit subbids for the electrical work. General Laws c. 149, § 44E (1), provides that “[i]n inviting sub-bids ... the awarding authority shall reserve the right to reject any sub-bid on any sub-trade, if it determines that such sub-bid does not represent the sub-bid of a person competent to perform the work as specified or that less than three such sub-bids were received and that the prices are not reasonable for acceptance without further competition” (emphasis added). Annese further asserts that, because the third
Implicit in Armese’s argument is the notion that a subbid is “received” when it is delivered to the awarding authority, without regard to its validity. A subbid may be delivered but subsequently rendered invalid under any of several methods set forth in the competitive bidding statute. For example, a subbid may be rejected for failure to “conform with [§§ 44A-44H], inclusive, or which is on a form not completely filled in, or which is incomplete, conditional or obscure, or which contains any addition not called for.” G. L. c. 149, § 44F (3). See J. & J. Elec. Co. v. Government Center Comm’n, 349 Mass. 172 (1965) (construing identical terms of former § 44H). A subbidder may be rejected for lack of competence. See G. L. c. 149, § 44F (4) (b), (c). See also Rudolph v. City Manager of Cambridge, 341 Mass. 31 (1960) (construing identical terms of former § 441 [2] and [3]). A subbid may be withdrawn because of “death, disability, bona fide clerical or mechanical error of a substantial nature, or other unforeseen circumstances affecting any such sub-bidder.” G. L. c. 149, § 44B (4). Subbids which are not available for any of these reasons are considered “invalid.” See Paul Sardella Constr. Co. v. Braintree Hous. Auth., supra at 242-243. If emphasis is placed on the meaning of the word “received,” as Armese urges, and if at least three subbids are received in a subtrade, then an awarding authority can never count on having at least three subbids from which a selection
Subcontractors who have been permitted to withdraw their subbids pursuant to G. L. c. 149, § 44B (4), have removed themselves from the competition for the contract and extinguished any chance of meeting the basic statutory requirement of being able to perform the work at the price bid. They are not competitive within the meaning of G. L. c. 149, §§ 44A-44H, because they are not on an “equal footing” with those who remain in the competition for the contract and they have no chance of ever becoming an “responsible and eligible” low bidder on the project. They are not available to be selected as sub-bidders, so their bids need not be considered “sub-bids . . . received” within the meaning of G. L. c. 149, § 44E (1). Construed in this manner, § 44E (1) retains its viability in effectuating the purposes of the competitive bidding statute.
Newton did not abuse its discretion under G. L. c. 149, § 44E (1), in rejecting the subbids of Annese and CNM because it received less than three electrical subbids which it determined were • uneconomical without further competition. See Brisk Waterproofing Co. v. Director of the Div. of Bldg. Constr., 338 Mass. 784 (1958). It was then free to resolicit subbids for the electrical work.
4. Purpose of obtaining a lower price. Annese contends that “awarding authorities may not reject bids simply to obtain a lower price,” Petricca Constr. Co. v. Commonwealth, 37 Mass. App. Ct. 392, 396 (1994), because resoliciting bids on a project in order to obtain a lower price contravenes the stated purpose of placing all subbidders on an equal footing, “exposes the secret bid price to other potential bidders and may provide the means whereby a future municipal government can use this power of rejection to award contracts to persons of their choice.” Id. Specifically, Annese complains that its “secret price” exposed “the correct low number for the project,” thereby causing other electrical subbidders to cut their prices in order to meet or beat it in the second solicitation, “against the letter and spirit of the competitive bidding system.”
Annese’s rebanee on Petricca is misplaced. There, the award
In this case, Newton was left with two valid subbids after three subbidders were permitted to withdraw, and therefore received “less than three such sub-bids.” Id. Those two sub-bids, Annese’s at $855,000 and CNM’s at $883,000, were more than 75% greater than Newton’s cost estimate of $487,000. Such a substantial disparity in price, without other bids to establish the actual market price of the work, gave Newton adequate grounds for determining that the prices were not “reasonable for acceptance without further competition”
We also fail to discern the harm experienced by Annese in
5. Deference to Attorney General. Citing our decision in Modern Cont. Constr. Co. v. Lowell, 391 Mass. 829, 837 (1984), Annese also argues that the decision by the Attorney General was entitled to more respect and deference than that accorded by the motion judge in this case. Annese misconstmes our holding in that case. General Laws c. 149, § 44H, provided in relevant part that the commissioner or his designee “shall have all the necessary powers to require compliance [with §§ 44A-44H] including the power to institute and prosecute proceedings in the superior court to restrain the award of contracts and the performance of contracts . . . where, after investigation of the facts, he has made a finding that such award or performance has resulted in violation ... of the provisions of [§§ 44A-44H].”
Judgment affirmed.
The standard for reviewing the denial of a motion for summary judgment is whether the record shows that there is no genuine issue as to any material fact and whether the moving party is entitled to judgment as a matter of law. Greater Boston Real Estate Bd. v. Boston, 428 Mass. 797, 798 (1999). See Mass. R. Civ. R 56 (c), 365 Mass. 824 (1974). Contrary to Annese’s assertion, statutory interpretation is a question of law for the court to decide. Commonwealth v. Cintolo, 415 Mass. 358, 359 (1993).
General Laws c. 149, § 44F (1), provides that, when work in a certain statutorily specified subtrade must be performed in a public building project and the value of the work exceeds $10,000, a subcontractor must “file” its “subbid” to perform the work directly with the awarding authority.
Each subbidder on a public building project must submit a bid deposit in an amount equal to five per cent of the value of its bid. G. L. c. 149, § 44B (2). If a selected subbidder fails to execute a contract with the selected general contractor, its bid deposit shall become the property of the awarding authority as liquidated damages, provided that, in case of a “bona fide clerical. . . error of a substantial nature” in the subbid, the bid deposit shall be returned to the subbidder. G. L. c. 149, § 44B (4).
The “award” of a contract is an expression of an intent to enter a contract. It is not synonymous with the execution of a contract. See Paul Sardella Constr. Co. v. Braintree Hous. Auth., 371 Mass. 235, 241 (1976). See also G. L. c. 149, § 44F (4) (b).
General Laws c. 149, § 44F (4) (c), provides: “If a selected sub-bidder fails, within five days . . . after presentation of a subcontract by the general bidder selected as the general contractor, to perform his agreement to execute a subcontract . . . such general bidder and the awarding authority shall select, from the other sub-bids duly filed with the awarding authority ... the lowest responsible and eligible sub-bidder at the amount named in his sub-bid . . . and the contract price shall be adjusted by the difference between the amount of such sub-bid and the amount of the sub-bid of the delinquent sub-bidder.”
Section 44H was amended by St. 1996, c. 151, § 386, and by § 690 made effective July 1, 1996, giving enforcement powers directly to the Attorney General.
As the designee of the Commissioner of Labor and Industries (commissioner), the Attorney General had the power to enforce his decision by filing suit in the Superior Court, G. L. c. 149, § 44H, but enforcement was not pursued in this case for reasons not stated in the record.
Annese’s appeal is not moot. Annese has a continuing interest in pursuing its bid preparation costs. See Petricca Constr. Co. v. Commonwealth, 37 Mass. App. Ct. 392, 395 (1994).
There has been no showing of fraud, collusion, or bad faith on the part of Newton in its determination that the three subbidders had made bona fide clerical errors so as to warrant permission for withdrawal. See Pacella v. Metropolitan Dist. Comm’n, 339 Mass. 338, 347 (1959); Slocum v. Medford, 302 Mass. 251, 254 (1939).
The commissioner no longer has this enforcement power. See note 7, supra.