138 P. 699 | Cal. | 1914
This was originally an action by the wife and minor daughter of Edwin M. Pollard, deceased, to recover damages against the defendants for his death. Prior to the trial the minor died and under stipulation the action was dismissed as to her and continued with Ruby Pollard, her mother, as the only plaintiff. A verdict for the sum of seven thousand five hundred dollars was returned in favor of the said plaintiff and an appeal was taken by the defendants from the judgment based thereon. This court transferred the cause to the district court of appeal, where, upon suggestion that Ruby Pollard had died after the perfecting of the appeal, George R. Andrews, who had been appointed administrator of her estate, was substituted in her stead as the party plaintiff. The district court of appeal sustained the judgment and denied the motion to transfer the cause to this court. The motion was in part based upon the contention that this court alone had jurisdiction to make the order of substitution of a party plaintiff in an appeal of which the supreme court had original jurisdiction. Another ground for the motion was that the action had abated by reason of the death of the plaintiff. This latter contention was correctly held of no *13
avail upon the authority of Fowden v. Pacific Steamship Co.,
The all-important question upon this appeal is whether or not the evidence discloses without contradiction such a state of facts as shows deceased to have been guilty of contributory negligence sufficient to preclude recovery on the part of his heirs.
Pollard was employed as a workman on a certain ice house which was in process of construction by the Valley Ice Company on the line of the Southern Pacific Railroad in the vicinity of the city of Fresno and near the transmission lines of the San Joaquin Light Power Corporation. These lines, carrying powerful electric currents, passed within a few inches of the corner of the building. The evidence shows that Pollard received the deadly shock through a ruler which he held in his hand, and appellants contend that the accident occurred while he was acting entirely outside of the necessary line of his employment, contrary to the instructions of the foreman under whose orders he worked and after he had been warned of the danger necessarily incurred in approaching near to the heavily charged transmission wires.
The building in course of construction was located near, but slightly at an angle with the street along which the transmission lines were stretched upon poles. The concrete wall of the building had been erected and the power lines were at about the same height from the ground as the top of it. The roof-timbers were in place, resting upon the top of the wall, and the ceiling of the building, upon which the foreman and Pollard had been standing while at work just before the accident, was eighteen inches or two feet lower than the top of the wall. The gable-end of the roof was open toward the electrically charged wires, but owing to the relative angles of the *14 building and the wires, the point of nearest approach between them was at the northwesterly corner of the building. This corner, when completed, would have been about eighteen inches from the wires, but the roof extended a foot or more beyond the wall so that the nearest point of the wall itself to the wires was about two and one-half feet or a little more. The only witnesses to the death of Pollard were Gronlund, the foreman, and Stephenson, a fellow workman, and it will be necessary to quote quite copiously from the record to convey any adequate idea of the facts to which they testified. They were both called as witnesses for the plaintiff. Gronlund testified that he took the measurements for the north gable end of the roof and gave Pollard orders to help him cut the corrugated iron and put it in place. Pollard helped the foreman take the measurements. Then Gronlund laid out a piece of the corrugated iron for Pollard to cut. Upon cross-examination he testified as follows: "Q. How did the gable end of this building front, as compared with the main line of the Southern Pacific Railroad that runs by there, which way did it run, the gable on which this corrugated iron was to be placed? A. Well, the building runs parallel with the S.P. road. Q. Then theend was at right angles with the road, fronting up toward town? A. Yes sir. Q. And the corrugated iron was to be put on under the roof, was it? A. Yes, sir. Q. On the end of the building, under the roof? A. Yes, sir. Q. How far down was it to come? A. Well, it came down about a foot and a half below the top of the joists. Q. That would be about a foot and a half below the gable, down on to the wall, about a foot and a half? A. Well, three inches below the joists, but the joist is sixteen inches. Q. But you sent him up there, didn't you, and then went up after him, after Mr. Pollard? A. Yes sir. Q. When you got up there, what was Mr. Pollard doing? A. I can't exactly state, but he was picking out some of the iron, material. Q. The material that was to be put on the gable end of the building? A. Yes, sir. Q. Now did you see him commence to put any of that material on the gable end of that building before he was killed? A. No sir. Q. Now after you got up there, what was the first thing that he said to you, or you said to him? A. Well, laying out the first starting point for the work. Q. Well, did you and he make any measurements? *15 A. Yes sir. Q. What were the measurements and where did you make them? A. I took the measurements close to the northwest corner. Q. And where was Mr. Pollard at the time you were taking the measurements close to the northwest corner? A. Well he was aboutthe same place I was, I was hanging on the side of the building,and he was on the top. Q. How close was the wall of the buildingat that time to these wires? A. About two feet and a half. Q. About two feet and a half. That would be at the corner? A. At the wall, yes. Q. From the wall, about two feet and a half? A. Yes sir. Q. Now did you get through with that work and get away from there, the corner? A. Yes sir. Q. Where did you go? A. I went over where the iron laid, and laid out a piece ready to put on. Q. Now where was Mr. Pollard when you started to go over to lay this iron out? A. Right there, where we were measuring it. Q. How far was that from the corner? A. About five feet. Q. About five feet? And at that point how far was he from the wire? A. Well, it would be about the same, a little more. Q. A little more than five feet? Now when you started to take the corrugated iron over, away from the corner, were you and he both through with the measurements? A. Yes sir. Q. And what did you say to him as to coming there and getting out the corrugated iron? A. I told him to come there and cut it as I measured it. Q. Where would that take him as to the wires, toward them or away from them? A. Away from them. Q. Now did you turn around to go over to where you were to cut the iron? A. Yes sir. Q. And told him to come with you? A. Yes sir. Q. Now then, what was the next thing you saw or heard, about Mr. Pollard? A. I saw him fall, the next thing I saw him fall. Q. And that was how long after you turned around, just a moment, or any length of time? A. I just had time to turn around. Q. And the last thing you had said to him was to come there and you and he would cut out the corrugated iron? A. Yes sir. Q. These measurements were for the purpose of putting the corrugated iron on the wall, were they? A. Yes sir. Q. Did they have anything to do with the wires? I say did the measurements have anything to do with the wires or the distance to the wires from the building? A. Well, not particularly, no. Q. Well, I say, were you measuring the distance from the building to the wires, or anything *16 of that kind? A. No sir. Q. And your measurements related, exclusively, then, to the places where you put the corrugated iron on the building? A. Yes sir. Q. And you had finished that work before Mr. Pollard was killed, all the measurements? A. Yes sir. Q. And you had turned and told him to come with you, back to the ceiling of the building to cut the iron? A. Yes sir. Q. That was the last order you gave him, was it? A. Yes sir. Q. Last time you saw him until he was shocked? A. Yes, sir. Q. Did you tell Mr. Pollard whether he was to take the corrugated iron to the corner, or leave it off — A. Leave the last sheet off. Q. Youtold him to do that, did you, to leave the sheet off? A. Yes,sir. Q. He was not to put that on until the wires were removed?Is that what you told him? A. Yes." Witness was then taken for further examination by one of counsel for the plaintiff and testified as follows: "Q. Did you tell him that, that you were not going to put the last sheet on until the wires were removed? Were you going to remove the wires? A. Yes sir. Q. Did you know that? A. Yes sir. Q. Who told you that? A. It was necessary to get the building completed. Q. What? A. Get the building completed? Q. You couldn't get the building completed without removing the wires? A. Not altogether. Q. Why? A. Too close. Q. The wires were too close to the building and had to be removed? A. Yes sir. Q. Had anyone told you that, or did you just know that, yourself? A. Oh, I could see it. Q. You could see it, anybody up there could have seen it, that the wires were too close, that you couldn't complete the building without removing them? A. Yes sir." Gronlund further testified upon cross-examination: "Q. Had the roof been put on, the corrugated iron of the roof, had it been put on at that time? A. No sir. Q. How much closer would the roof come to the wires than the corrugated iron on the building, how much closer would it extend? A. About two feet and a half. Q. Were you engaged at all in putting on the roof at that time? A. No sir. Q. Hadn't started on that at all? A. No sir. Q. What you were doing was getting ready to put the corrugated iron on the end of the building, and that was two and one-half feet further away than the roof would be? A. Yes sir, about two or three feet. Q. And you had instructed Mr. Pollard not *17 to put the piece on next to the corner, on the gable end? A. Yes sir." From this testimony it appears that all of the measurements had been made before the accident and that there was no occasion for Pollard to go to the corner and to use his rule there as he evidently did because it was found by his side, when his corpse lay on the ground and the rule was burned and marked with the deadly current that had passed through it into his body. It is uncontradicted testimony that Gronlund, after giving orders to Pollard to follow him and help with the cutting of the metal which was located far beyond any possible danger from the electric current, turned toward the pile of corrugated iron and it was then that Pollard, without necessity and contrary to orders, approached a place of great danger and extended his ruler within the malign power of the electric current. But it is argued that the testimony given by Gronlund at the coroner's inquest contradicts that which is quoted above. The material part of his testimony before the coroner was as follows: "As the foreman, I instructed Mr. Pollard to put on some iron on the gable end of the building. I came up there after a while, and took a measure out to measure a sheet of iron, and was going to have it cut, and I turned back, from where Mr. Pollard was, on a platform he had built, to cut that iron, and the same time, Mr. Pollard turned back the other way, to get some more measures, and I heard the flash of the fire from the wire. I turned back and saw the fire all around Mr. Pollard's head, and before I could step a step, he was half way to the ground. Q. Now these wires come along this point of the building from six to ten inches? A. Yes sir. Q. Then you think that Mr. Pollard was there in the act of taking measurements on this point? A. Yes sir. Q. Is this rule his? A. Yes sir. Q. This cut is marked on it — E.P., is that it? A. Yes sir. Q. Did you ever see this rule before his death? A. I saw the rule in his hands, but I never noticed it before. Q. Ever notice the burned part before? A. No sir." When confronted with this testimony at the trial he said, by way of explanation: "I suppose that he was taking measurements, because I never gave him orders to, and it wasn't necessary." We do not find any serious conflict or indeed any conflict at all between the testimony of Gronlund at the inquest and that given at the trial. His statement that Pollard was taking *18 measurements was an expression of opinion amply justified by the circumstances of the latter's death, but he did not testify to anything at the coroner's inquest in contradiction to the testimony afterward given that there was no necessity for further measurements and that Pollard had been ordered to do work well without the sphere of danger. While the testimony given at the inquest was less full and explicit than that elicited from Gronlund at the trial, both statements may be perfectly true and yet entirely free from inconsistency.
Clark Stephenson, the only other witness who was near Pollard at the moment of the fatality, testified in part as follows: "We were working downstairs on some other business in connection with the ice plant, until about eleven o'clock, and then Mr. Gronlund directed us to go on up there and put this corrugated iron on the gable. . . . He told us to go up on the gable end on the northwest corner of the building, that is, right adjacent where these power lines run. We were to put this corrugated iron on the gable end. The cement comes up to the roof, and then from there up on the gable is corrugated iron; that is, under the roof. None of that corrugated iron had been put on the gable at that time. That part of the roof was not covered yet either, but I think the other part had, a section back. There might have been some twelve or fourteen feet back, or twenty feet, I don't remember just now. There was quite a space left there. When we received these instructions from Mr. Gronlund we went up there to the gable. That was about eleven o'clock in the morning. After we got up there, Mr. Pollard paid attention to the iron, and at that time I think when we had the instructions, Mr. Gronlund said that one of us should take a line with us, Mr. Pollard I think he said didn't have any line, and so I took my line, I was starting a line at that time for the bottom part of this corrugated iron, and Mr. Pollard and Mr. Gronlund were cutting the first sheet next to the corner. This would be the second sheet from the corner. They were fitting the bevel for the roof. Q. And on which side was that of the building? A. That was on the south, or the east side — east. Q. Next to the wires? A. Yes sir. Q. That is what we would call the west side, I think? A. Yes, that is the west side, I am a little changed around. I mean the side next to that power line, next to the Southern Pacific Railroad. The *19 building was situated along East Avenue, it came corner ways to East Avenue, and I remember was next to the wires. Mr. Pollard and Mr. Gronlund were fitting that first sheet of corrugated iron, and of course I couldn't say what he was doing exactly. I was paying attention to this line. I was striking a chalk line to make a mark for a point. I was not paying attention very much to Mr. Pollard and Mr. Gronlund then. Mr. Pollard was standing right inside of the rafter, I think, nearly at the corner of the building. He was not exactly at the corner, nearly, within a few feet of it, and I think he was standing on the inside wall. Where the joists come there is the rafter comes up some three or four feet above the wall, above the top part of the wall, the way the building is made. He was standing on the portion of the wall that projected up, I think on the cement wall, but I couldn't just exactly say what he was doing at that particular time, I was not looking at him. I couldn't say whether he had any rule out, or anything of that kind. I don't know much about the accident. I wasn't looking at him when the accident occurred. I was sideways, about sideways, and I heard this noise, sizzing noise, that electricity makes when it hits anything. I looked around and he was toppling over. . . . Q. Had you seen Mr. Pollard that morning while you were up on the roof on this gable making these measurements? A. I wasn't paying any attention. Yes, Mr. Gronlundand him were making these measurements on this first sheet ofiron. Q. As you didn't see him the exact moment when he got his electric shock, you don't know what it was that he touched, or what touched him? A. No, I couldn't say as to that. I couldn't say how he came in connection with the wires there. I didn't hear any conversation between them just before the accident. I couldn't say how Mr. Pollard came in contact with the wires. These measurements were being taken to get the slope of the roof, and the base of the corrugated iron, so that it could be cut to fit in the gable, to get the bevel. The measurements they were taking all pertained to the wall of the gable." Upon redirect examination the witness said: "Where Mr. Pollard was working his body would be five or six feet from the wires, somewhere along there, I should judge. If he was bending over with his face fronting to the interior of the building, his body would come out very much closer to the wires." This *20 testimony is corroborative rather than contradictory of that given by Gronlund. That the foreman had turned his attention to the corrugated iron before the accident appears from what Stephenson says as well as from Gronlund's statement. Stephenson could not hear what conversation passed between the foreman and Pollard. His testimony therefore does not contradict the foreman's story that Pollard had been directed to work far from the zone of danger. Indeed Stephenson's testimony is not of great value in placing Pollard just before the accident, for he said, "I wasn't looking at him just before the accident occurred."
We are forced to the conclusion, after a careful perusal of all the evidence, that, even if we fully grant the power of the jury to reject any part of the testimony of a witness and to accept any other part, there are no selected portions of the narratives of these two principal witnesses which will support the verdict. No serious attack is made upon their stories, but as appellants' counsel aptly say, were they discredited as to any part of their testimony, that would "avail plaintiff nothing, because there is no other testimony." Plaintiff's own counsel, as we have shown in the quotations made above, brought out by leading questions, in his examination of Gronlund, that anybody could have seen that the building could not be completed without removing the wires. This statement from plaintiff's own witness, so elicited, would show that the deceased, who had worked for years around buildings under modern conditions, must have known the danger of getting near highly charged wires. Dangers from such a source are presumed to be familiar to men of average intelligence. (Shade v.Bay Counties Power Co.,
While undoubtedly it was the employer's duty to furnish a safe place for Pollard to work in, that duty did not extend to his protection beyond the limits of the space allotted to him and in which he was ordered to assist the foreman. (Kennedy v. Chase,
Nor does the evidence herein bring the cases within the rule of temporary, excusable forgetfulness announced in such cases asGiraudi v. Electric Imp. Co.,
The judgment is reversed.
Shaw, J., Henshaw, J., Lorigan, J., and Angellotti J., concurred. *22