Andrew R. Mancini Assoc., Inc. v Mary Imogene Bassett Hosp.Andrew R. Mancini Assoc., Inc. v Mary Imogene Bassett Hosp.
v
Mary Imogene Bassett Hospital, Respondent, et al., Defendant.
—[*1] Hinman, Howard & Kattell, L.L.P., Binghamton (Harvey D. Mervis of counsel), for appellant.
Persun & Heim, P.C., Mechanicsburg, Pa. (Matthew E. Hamlin of counsel), for respondent.
Egan Jr., J. Appeal from an order of the Supreme Court (Dowd, J.), entered January 11, 2010 in Otsego County, which granted defendants’ motions for summary judgment dismissing the complaint.
In July 2002, defendant McCarthy Building Companies, Inc. contracted with defendant Mary Imogene Bassett Hospital (hereinafter Bassett) to be the general contractor with respect to an expansion project at Bassett‘s hospital located in the Village of Cooperstown, Otsego County. That same month, McCarthy, in turn, retained plaintiff to perform certain work on the project for the sum of $1,360,971. Thereafter, in August 2002, prior to the execution of a written subcontract, plaintiff commenced work on the project on a “time and materials” basis, whereupon plaintiff would submit invoices for payment for work done. Between September and October
In 2005, plaintiff instituted this action claiming breach of contract, unjust enrichment, quantum meruit and account stated seeking $445,537.77 in damages. The crux of plaintiff‘s claim is that it performed work for Bassett outside the scope of its subcontract with McCarthy, on a “time and materials” basis, submitted invoices for that work, and has not been paid. Defendants each moved for summary judgment dismissing all claims by plaintiff, among other relief. Supreme Court granted the motions, and plaintiff now appeals.2
Subcontractors cannot maintain actions for breach of contract against parties with whom they are not in privity (see IMS Engrs.-Architects, P.C. v State of New York, 51 AD3d 1355, 1357 [2008], lv denied 11 NY3d 706 [2008]; Robert H. Finke & Sons v Sears Oil Co., 256 AD2d 868, 869 [1998]; Barry, Bette & Led Duke v State of New York, 240 AD2d 54, 56 [1998], lv denied 92 NY2d 804 [1998]; Bubonia Holding Corp. v Jeckel, 189 AD2d 957, 958 [1993]). Thus, plaintiff cannot maintain a breach of contract action against Bassett for its work under the subcontract with McCarthy, and its breach of contract action against Bassett can only be sustained, if at all, on allegations of work performed for Bassett that was outside the scope of, and in addition to, the subject matter of its contract with McCarthy (see IMS Engrs.-Architects, P.C. v State of New York, 51 AD3d at 1357; Robert H. Finke & Sons v Sears Oil Co., 256 AD2d at 869; Graystone Materials v Pyramid Champlain Co., 198 AD2d 740, 741 [1993]).
“The proponent of a summary judgment motion must make a prima facie showing of entitlement to judgment as a matter of law, tendering sufficient evidence to demonstrate the absence of any material issues of fact, and the evidence produced by the movant must be viewed in the light most favorable to the nonmovant, affording the nonmovant every favorable inference” (Rought v Price Chopper Operating Co., Inc., 73 AD3d 1414, 1414 [2010] [internal quotation
In opposition, plaintiff failed to present sufficient evidence to create a question of fact (see Zuckerman v City of New York, 49 NY2d at 562). While plaintiff‘s chief executive officer asserted that plaintiff was not paid for “time and materials” work alleged to be performed for Bassett outside the scope of the subcontract with McCarthy, he conceded in his deposition that all such “time and materials” work was billed in invoice Nos. 4393, 4430 and 4431, and that there were no other invoices incorporating any other “time and materials” work. The chief executive officer, plaintiff‘s president and plaintiff‘s secretary/treasurer all acknowledged that these three invoices were paid. As plaintiff failed to contradict Bassett‘s evidence that plaintiff was paid for the specific work placed at issue in this case and also failed to submit proof that it performed any other work for Bassett outside the scope of—and in addition to—the subject matter of its subcontract with McCarthy, Supreme Court properly granted summary judgment in Bassett‘s favor dismissing plaintiff‘s claim for breach of contract.
Likewise, given that plaintiff failed to specifically articulate any work performed outside the scope of the subcontract for which it has not been paid, its claims for unjust enrichment and quantum meruit also fail (see IMS Engrs.-Architects, P.C. v State of New York, 51 AD3d at 1358; Clifford R. Gray, Inc. v LeChase Constr. Servs., LLC, 31 AD3d 983, 988-989 [2006]; Conklin v City of Saratoga Springs, 267 AD2d 841, 842 [1999]; Graystone Materials v Pyramid Champlain Co., 198 AD2d at 741). Finally, based on the absence of “an agreement between parties to an account based upon prior transactions between them with respect to the correctness of the account items and balance due” (Jim-Mar Corp. v Aquatic Constr., 195 AD2d 868, 869 [1993], lv denied 82 NY2d 660 [1993]), and because plaintiff‘s claim was promptly disputed, summary judgment dismissing plaintiff‘s claim for account stated was proper (see Joe O‘Brien Investigations v Zorn, 263 AD2d 812, 815 [1999]; Jim-Mar Corp. v Aquatic Constr., 195 AD2d at 870).
Cardona, P.J., Spain, Kavanagh and McCarthy, JJ., concur. Ordered that the order is affirmed, with costs.