103 Misc. 388 | New York Court of Claims | 1918
On June 13,1912, the claimant and the state of New York entered into a contract for the improvement of the highway, known as the Boonville Town Line-McKeever State Highway, Division No. 3, Highway No. 5248, in the counties of Oneida and Herkimer, according to the plans and specifications made a part of the contract.
The contract was made under the provisions of chapter 30 of the Laws of 1909, and chapter 646 of the Laws of 1911, and the acts amendatory thereof and' supplemental thereto. The claimant completed the contract and performed all the work to the satisfaction of the state, and was paid the sum of $248,414.60.
The contract, plans and specifications provided for the construction of a two-course macadam highway, each course to be built of crushed stone; known as “ run of the crusher.”
The claimant began work in July, 1912, and continued until about September 1, 1912, when he began the laying of stone pursuant to the contract. Thereupon he was halted by the state engineers in charge of the work, and was ordered and directed not to use ‘ Í run of the crusher ’ ’ stone merely, but to grade it in separate bins, or pockets, according to size, and to place in the bottom course three-inch stone, to be filled with dustless screenings and rolled. The provision of the specifications for said course reads • “A layer of broken stone consisting of the run of the crusher from dust approximately three inch stone.” He also was ordered to construct the top course of two-inch stone and one-inch stone, only. The specification for said course reads: “ The run of the crusher from screenings to and including two inch stone.” He further was ordered to place upon the top of the two courses so constructed a coat of bituminous asphalt, upon which should be placed one-inch stone, and upon top of the one-inch stone should be placed a second coat of asphalt, upon which should be spread a wearing
The claimant called the attention of the engineer to the provisions of the specifications, and protested against these directions and against complying with them. The engineer replied, in substance: “ This is the way we have got to have it; this is the way it must be done,” and refused to permit the work to be done, except pursuant to these directions, whereupon the claimant complied, and completed the work as directed.
This resulted in a very great increase in expense to the claimant. It compelled him to furnish 40,906 cubic yards additional of stone, of the value of one dollar and seventy cents per cubic yard, which was the unit price fixed by the contract for crushed stone.
During the course of the work, the claimant performed various other services, and furnished certain other materials, incident to the construction of the road, not provided for, or contemplated, by the contract, plans or specifications. It does not appear that they were performed or furnished under any contention by the state that the contract, plans or specifications required them, or that the claimant was compelled by any representative of the state to perform or furnish them, over his opposition or protest. Bather, the inference from the testimony is that these items in the nature of extra or additional work were performed by the contractor willingly, and by arrangement, or agreement with the state. Certainly, it appears from the evidence that these items were clearly and probably outside of any provisions of the contract, plans or specifications. They consisted of earth and rock excavation, iron and steel, sub-base construction, relaying drain pipe, and pipe railing and they aggregate in amount $8,720.72.
This provision will not defeat recovery by the claimant for the loss inflicted upon him by the directions of the engineer, in relation to the crushed stone, and the claimant’s compliance with them. The state misapprehends the nature of the claim in this respect, and the theory upon which it is predicated. The claimant does not sue for compensation for extra or additional work or materials. If he did, we agree that the statute would bar recovery, in the absence of a provision in the original, or in a supplemental, contract, executed by the commission, pursuant to which the same was done, or furnished. This item of the claim is for damages for breach of the originál contract, due to the action of the state’s representatives in compelling the claimant to grade and apply the stone in a manner not within the obligation of the contract. This action by the state was conceded on the trial.
In the case of Gearty v. Mayor, 171 N. Y. 61, a contractor was ordered by the city’s engineer to take up
“ The important question is whether a second remedy is open to the contractor, such as is invoked in this case. The plaintiff did not choose to put himself in the attitude of refusing to obey the directions of the commissioners, thereby assuming the position of a defaulter under a contract with the city, but preferred to perform it as best he could, accepting under the final certificate such amount as the city admitted to be due him, subject to reservation of his rights under oral protests and the written release under seal, to which reference has already been made. * * ' *
“ It is insisted on behalf of the city that the plaintiff, by obeying the orders of the engineer of construction, requiring him to take up and relay the alleged improper work, without making any claim for extra compensation at the time the changes were ordered or made or without making a new contract, has waived any claim, if he was entitled to any, to extra compensation.
“As we have seen, by oral protests and by the written release, the plaintiff carefully reserved his rights. ’ ’
In the Gearty case, the question involved was one of waiver, but the reasoning and the conclusion are applicable equally here. The court held that the action was for breach of contract, and that there was no waiver, but that the plaintiff was entitled to elect his remedy, and had done so.
It is clear from the phraseology of the claim, and the attitude and evidence of the claimant at the trial, that this claim, likewise, is for breach of the original contract, and is identical in nature with that in Gearty v. City of New York. If it is for breach of the original contract, then, of course, no supplemental contract is necessary, because the original contract, executed by the commission, is the basis of the claim.
The Gearty case is the leading case in our state, on this subject. It grew out of the determination of the courts to obviate the palpable injustice of requiring a contractor to decide, at his peril, every close and debatable contention over the construction of his contract, or the plans and specifications accompanying it. Were it not for this attitude of the courts, the contractor, in every instance, would be obliged to submit to the construction of the contract insisted upon by the engineer, to his loss, and, by compliance, waive all his rights in
The principle which we have in mind has been applied in many other cases, to a few of which reference may be made. Dwyer v. City of New York, 77 App. Div. 224, 230; Beckwith v. City of New York, 148 id. 658; Ryan v. City of New York, 159 id. 105.
We conclude that the items of the claim, in reference to the stone, in the sum of $69,540.20, fall within the limitations of the principle, as defined in the case of
The foregoing discussion demonstrates that the various other items of this claim, aggregating the sum of $8,720.72, do not constitute any basis for recovery. If we consider them as extra work or materials for which recovery is sought as such then it is barred by the provision of the Highway Law, to which we have referred, because none of these items was provided for, or agreed upon, in the original, or in any supplemental, contract executed by the commission. If the claimant’s theory as to these items is the same as to the stone item, for which we have decreed recovery, and we believe it to be, then he has waived his rights, in
The foregoing discussion relates to the legal principles involved in this claim. In morals and common honesty, there can be no doubt whatever of the absolute right of the claimant to recovery for every item of his claim. The state was in the position, at the trial, of admitting this and of apologizing for the “ wrong ’ ’ which it was seeking to impose on the claimant. It was frankly admitted that the claimant had performed or furnished all of the items, for which he claims, pursuant to the demands of the state, and that his claim was reasonable and honest in quantity and amount. It seems, however, that between the time when the demands were made upon and complied with by the claimant, and the time for payment, there was a change in the personnel of the highway commission, and the new commissioner refused to assume responsibility for what had preceded his regime, to the extent of executing a supplemental agreement, for any of the items of this claim, or to take any of the necessary steps to compensate the claimant for the work and materials, of which the state unquestionably has had the benefit. The claimant was told that he would “ have to go to
Ackerson, J., concurs.
Judgment accordingly.