12 Daly 149 | New York Court of Common Pleas | 1883
In the testimony, which is voluminous, there is considerable contradiction upon many points, such as the extent, nature and value of omissions and changes, the circumstances under which they occurred, the statement of the architect as to the reasons why he refused to give the last certificate, and other matters, in respect to all of which it must be assumed that the referee believed the plaintiff’s witnesses and discredited those of the defendant, where they were in conflict. The conclusions of the referee as to the facts where the testimony is thus conflicting will have to be taken as correct. We have the right to review a referee’s findings upon questions of fact where he has found on conflicting evidence; but we do so only in extreme cases, where it is clearly manifest to the appellate court that he was wrong; and this is not one of those cases. He saw the witnesses, heard them testify, and, by consent of the parties, inspected every part of the building in respect to which evidence had been given. He had, therefore, advantages in passing upon disputed questions of fact which an appellate court cannot have.
A material circumstance in this case is that by the contract the plaintiff was to erect the buildings in conformity with the drawings and specifications made by Morell, the architect, “in a good, workmanlike and substantial manner, to the satisfaction and under the direction of the architect,” to be authenticated by a certificate in writing. The work was to be paid for in nine payments, in certain stages, as it progressed; and it was further provided that “ in each of the said cases ” or stages of the work, when the payments
Unless something, such as above stated appears, the certifi-. cate is conclusive, and the inquiry as to non-performance is limited to what was required to be done to entitle the plaintiff to the last payment, the architect having refused to give a certificate to entitle the plaintiff to receive that payment;
The architect testifies that a list was kept by the defendant and himself of the omissions, &c., the main portion by the defendant. He says: “ All along, during the progress of the work, we had an express understanding that that should be done; and when the defendant objected to certain things, my answer was that ‘ everything may be adjusted at. the last under the clause in the contract of omissions and deviations, and I think you will have no difficulty in doing it,’ or something to that effect; ‘ we will keep a list as the work goes on; ’” and that the defendant did so; and that he, the architect, also kept a list as to some things.
If anything remained to be done in compliance with the contract, the architect was right in refusing to deliver the certificate; but the testimony in the case,.and which, we must assume the referee believed, is that his refusal was not put on this ground, but because the defendant had told him. not to give it; and that he could not do it, because the defendant was a friend of his ; that the defendant held a good deal of property, was a man of influence ; and if he gave the certificate it would break friendship between them. This was said when Barnett, the plaintiff’s attorney, demanded the certificate for the last payment. Barnett testified that the architect admitted that the plaintiff had subtantially completed his contract; that there were, however, some little things to be done. When the attorney told him that it was his duty to elect whether he should do his
The delay in completing the buildings within the time contemplated was fully explained by the plaintiff’s witnesses. It arose from changes made in thé plans, by extra work, delay caused by the plumber (which was one of the controverted points in the evidence), bad weather, during which it was impossible to plaster, and other circumstances; the fact also being, as found by the referee, that the defendant was present nearly every day at the buildings during the progress of the work, overlooking it with great care and particularity, and yet he never complained of or made any objection as to the delay—for the obvious reason, it may be assumed, that he was himself cognizant of the cause of the delay, as he knew what took place from day to day. Under
In adverting, in the last cited case, to the difficulty of complying with entire exactness, in this class of contracts, as the reason why the apparent rigor of the general rule has been so far relaxed as to make a substantial compliance sufficient, the court say, in interpretation of the general rule as so modified, that there must not be wilful or intentional departure; the defects must not pervade the whole work, or be so essential that the object which the parties had intended—a specified amount of work, performed in a particular manner—is not accomplished. And this test fully meets the nature of the omissions or deviations in this case. Nor does it vary the application of this rule, that the work was to be done under the direction and to the satisfaction of an architect (Nolan v. Whitney, 88 N. Y. 648; Smith v. Brady, 17 N. Y. 176; United States v. Robeson, 19 Pet. 319; Glacius v. Black, 50 N. Y. 153) ; for, as was held
Where there have been defects and omissions of this kind, the question whether there was or was not a substantial performance is a question of fact for thd referee upon the whole evidence (Nolan v. Whitney, 88 N. Y. 648 ; Johnson v. DePeyster, 50 N. Y. 666 ; Glacius v. Black, Id. 145), with whose conclusion an appellate court will not ordinarily interfere.
The omissions or deviations in this case amounted, in value to only $380.20 in a contract where the plaintiff was to receive $12,650 for erecting the buildings, and the amount allowed was not such as to show that the finding of a substantial performance was erroneous. In Phillips v. Gallant (supra), the defects were found to be of the value of $75, where the amount to be paid for the work was but $800, and it was held that the court could not say, as matter of law, that because of the allowance of that sum the contract was not substantially performed. They declared it to be a question of fact, upon which the decision of the referee was conclusive.
The defendant called witnesses to examine the buildings after their erection, whose estimate of the extent and value of the omissions appears to be greater than this amount. But this also was a question of fact for the referee, in view of the statement of the architect himself, of the omissions to which, as he testified, he called the attention of the plaintiff ; and his statement, which he did not contradict, that there were only a few small matters remaining, of which he would, and did, give a list. His further statement, also, that there were no fatal defects in the buildings; that they would serve the purposes for which they were built; that
A question arose upon the extra work, whether the plaintiff was bound to go below ten feet from the curb in laying the foundation, it having been discovered when they had reached that depth that, in consequence of the sandy nature of the soil below, they would have to go deeper to build the foundation. This was a contingency that the plaintiff had not assumed. The provision in the contract was that he was to excavate to a depth of not less than ten feet, and the building of the foundation from this additional depth was work for which no provision had been made in the contract, the nature of the soil at that depth being unknown to both. The referee held it to be extra work, for which the plaintiff was entitled to recover, which I think was correct.
By the terms of the contract, if any dispute arose as to the value of the extra work or of the work omitted, it was to be settled by arbitration. There being such a dispute, each party selected an "arbitrator, but the lawyers" of the respective parties could not agree in the' framing of the agreement under which the arbitrators were to act. The plaintiff’s attorney prepared it, but the defendant’s attorney struck out the clause allowing witnesses to be produced before them, saying that if witnesses were to be called, there was no use in having an arbitration ; that it was better at once to have a suit brought and have a reference, to which the plaintiff’s attorney did not agree. The plaintiff was not bound by this clause in the agreement to have the
It may have been necessary to show or explain by them the nature of the extra work, or otherwise to settle the dispute respecting that work.
The arbitration, therefore, did not fall through by the act of the plaintiff alone. It was mainly the act of the defendant or of his attorney. Both must be regarded as acquiescing in its abandonment, and the question had to be decided in this action. The case is a very different one from Altman v. Altman (5 Daly 436). ■
The objections taken by the defendant to the admission or the exclusion of testimony are not of sufficient importance to be reviewed specifically. It is enough to say generally that none of them were sufficiently material to call upon us to set aside this report and order a new trial. ¡
The judgment entered upon the referee’s report, fore, should be affirmed.
J. F. Daly and Beach, JJ., concurred.
Judgment affirmed.