33 N.Y.S. 741 | N.Y. Sup. Ct. | 1895
This action was brought to foreclose a mechanic’s lien filed by Andrew Andersen, the plaintiff’s testator, against the property of the defendant. Anderson entered into a written contract with the defendant to erect for him a dwelling house according to certain plans and specifications for the sum of $3,200. The final payment was to be $1,300, and was to be made upon the completion and acceptance of the building. The lien was filed for the amount of the final payment. The action was defended on the ground that the work had not been performed in accordance with the drawings and specifications. The referee found that the contract was substantially performed, but that, by reason of defective work and defective materials used in the construction of the house, the defendant was entitled to deduct $300 from the balance of the contract price, and that the defects in the building were not substantial ones, and did not pervade the whole work, and that “they were not so essential that the object of the parties failed of accomplishment by reason thereof.” The referee has not found the particular defects in the building or materials for which he made the allowance of $300, and it is impossible for this court, from an examination of the evidence, to ascertain what matters were intended to be covered by that allowance. In response to requests to find, made by the de
“The rule of substantial performance should not be extended beyond the purpose in view when the relaxation of the strict performance was adopted, which was founded upon equitable considerations in furtherance of justice, and made applicable to cases of honest intention of contractors to fairly perform their contracts, and who shall in the main have done so, with only slight defects or omissions inadvertently and unintentionally caused and ap7 pearing in the work.”
If a contractor should «fail to perform some distinct or specific piece of work, which, by his contract, he had stipulated to do, the value of which was one-tenth of the contract price, there would,' I think, be no question that there was not a substantial performance of the agreemént. The rule still prevails that the plaintiff must show performance when that is a condition of payment. The relaxation of its strict application in cases arising under building contracts was not intended to permit courts and juries to substitute a money indemnity as an equitable compensation for unfulfilled covenants of the contract, but arose because of the difficulty of complying with entire exactness with all the particulars embodied in that class of agreements. Hence it has been repeatedly said in the decisions that it is only in cases where there has been no willful omission by the contractor, but he has honestly and faithfully performed the contract in all its substantial particulars, that he will not be held to have forfeited his remuneration by mere technical or unimportant omissions or defscts. The rule stated by Judge Church in Glacius v. Black, 50 N. Y. 145, and which has been frequently repeated in later decisions was that, if the defects or omissions are so numerous
It is claimed by the respondent that the defendant waived the defects in the performance of the contract. Waiver is largely a question of intention, and we do not think that the evidence before us would permit the conclusion that the defendant surrendered his right to have the plans and specifications complied with. The referee, however, made no findings upon this question, and it is not before us for review. The judgment must be reversed, the order of reference vacated, and a new trial granted; costs to abide the event. All concur.