ORDER
In this diversity action for breach of contract, plaintiff has moved to strike defendant’s first and second affirmative defenses as insufficient as a matter of law. In July, 1968, Anchor Hocking Corporation (‘Anchor Hocking’), the plaintiff, entered into a requirements contract for electricity with the City of Jacksonville, Florida. On October 1, 1968, pursuant to Florida Laws 1967, Chapter 67-1569, the Jacksonville Electric Authority (‘JEA’) was established, to which the City of Jacksonville transferred its contract with Anchor Hocking; and JEA assumed the correlative contractual obligations. Florida Laws 1967, Chapter 67 — 1569, § 6. Thereafter, Anchor Hocking and JEA, the defendant, continued performing their respective duties under the contract.
Section 2 of the contract required a mandatory one-year effective life, after which there was reserved to either party a right to terminate the contract unilaterally upon ninety days’ notice. Section 3 of the contract established a scale of monthly rates for electricity which JEA would charge Anchor Hocking, depending on the amount of kilowatts used. In addition, a formula was provided by which JEA could adjust upward or downward monthly its energy charges to Anchor Hocking, on a one-to-one ratio, for all costs that exceeded or fell below the agreed upon limits of a sliding twelve-month average of fuel costs to JEA. Finally, Section 3 allowed for a direct, one-to-one adjustment upward of energy charges by JEA for all increased taxes on JEA, ad valorem or non-ad valorem, that are allocable either to JEA’s property that is used for electrical utility service, or to its production of electrical utility service.
The question presented by Anchor Hocking’s motion to strike JEA’s first affirmative defense is whether the contract between them, which is the subject matter of this action, is unenforceable because it is void. The question is purely one of law. There are three different legal principles, exemplified by three groups of cases under Florida law, that are involved in answering this question.
First, if the Florida Legislature has delegated, by general statute, its inherent, plenary authority over utilities’ services to a city, any subsequent contract between that city and a utility that would bind the city inflexibly and unreasonably, preventing the exercise of its delegated power, is ultra vires and therefore void ab initio. The progenitor of later Florida decisions is
City of Tampa v. Tampa Waterworks Company,
On the city’s appeal from a judgment for the water company, the Supreme Court of Florida held that the pre-existing provision of the State Constitution subjected every subsequent contract involving the State or a municipality to it. The provision became an implicit provision in any subsequent contract, denying the right of any contract to bind the State or a municipality from the obligatory exercise of the power recognized under that provision.
Id.
Consequently, insofar as the particular contract between the city and the water company purported to bind unalterably the city for thirty years, the contract was ultra vires and void from the outset. There was, therefore, no valid contract to be impaired. The United States Supreme Court,
Tampa Water Works Company v. City of Tampa,
City of Clearwater v. Bonsey,
. continuing duty to revise rates to enable the water system to be financially selfsufficient while maintaining a rate structure which operates in an equitable manner. The rate contract in this case operates as a bar to this requisite flexibility ... Id. at 204.
As a result, the county lacked the power to bind itself to a thirty year contractual rate, since such a contract would preclude the necessary exercise of discretion required by the Special Act in order to maintain the economic self-sufficiency of the water system. Id. at 203. Being ultra vires, the contract was void from its inception.
Recently, in
Southern Bell Utilities, Inc. v. City of North Miami Beach,
. is presumed to have been made with full knowledge of the inherent reserved power of the State to alter the contract regarding rates at such time as the Legislature deems it appropriate to assert the power under the Constitution. It also follows that when the parties enter into such a contract they do so with the full realization that the contractual provisions are ineffective to preclude subsequent legislative action in the exercise of the State’s police power. Id. at 843-44.
To the extent that the city’s contract conflicted with it, the contract was abrogated and voided by the Legislature’s legitimate exercise of the State’s police power.
In
Merritt Island Sanitation, Inc. v. E. L. Green,
Third, if a contract between a city and a utility provides a formula for annual (or other reasonable, periodic) revision of rates, and is reasonably terminable as well, it will be flexible enough to facilitate any exercise of State police power whether delegated or not that is necessary to preserve the fiscal solvency of the city; and it will therefore remain enforceably valid.
City of Safety Harbor v. Pinellas County,
In
City of Daytona Beach v. Stansfield,
Recently, the Second District Court of Appeal clarified the distinction between enforceable contracts and voidable or void ab initio contracts for utility service. In
Pinellas County
v.
City of Pinellas Park,
The court held that the contract containing the formula for annual rate revision not only was not an unreasonable restriction on the county’s power and duty, but rather it affirmatively promoted “the performance of that duty by providing a known schedule periodically” to revise the rates. Hence, the contract was “a valid, reasonable and enforceable one.”
Id. Cf. Belcher’s Sugar Refining Co. v. St. Louis Grain Elevator Co.,
It is clear that JEA seeks the Court to apply the first or second principles to the contract in this case, holding it unenforceable. It is equally clear to the Court, however, that the contract in this case exemplifies those held valid and enforceable under
For an interim period during the life of the contract, its obligations became less desirable to JEA. Nonetheless, JEA had two choices readily available under the provisions of the contract: (1) JEA could have exercised its right to terminate the contract unilaterally upon ninety-days’ notice; or (2) it could have continued to adhere to the terms of the contract, with a possible recovery under the contractual formula of its initial losses. If under those circumstances, however, JEA could simply ignore the provisions of the contract, impose new rates on its own, and proclaim the contract void, then the worth of any contract with JEA would be limited to the value of the paper on which it is written. The law of Florida will not countenance such conduct. The Court holds that the contract between JEA and Anchor Hocking was a reasonable and flexible one, and that it remained enforceable against both parties until terminated. The Court therefore further holds that JEA’s first affirmative defense that the contract was void ultra vires or voided by pre-emptive, superseding law, is legally nonexistent.
JEA’s second affirmative defense is that the increased electricity rates that it began charging in November, 1973, were authorized under the provisions of the contract. Specifically, JEA contends that the increased rates correspond to its increased fuel costs which, in turn, are attributable to corresponding taxes imposed by the government of Venezuela. In short, JEA argues that, to the extent that its increased rates exceed those allowable under the contractual formula, they represent taxes against JEA that may be directly passed on to Anchor Hocking under § 3 of the contract. In opposition, Anchor Hocking argues that JEA’s suddenly increased rates do not represent taxes imposed against JEA, and directly recoverable under § 3 of the contract; instead, they represent increases in the purchase price of, and thus JEA’s cost basis for, fuel oil for its generators.
The question presented by the motion to dismiss JEA’s second affirmative, defense, then, is also purely one of law. It is a question of interpreting § 3 of the contract under Florida law as it relates to increased rates and the putative taxes that they allegedly represent. The specific question presented is whether the increased tariffs which the government of Venezuela imposed on the oil that it exports are taxes against JEA that may be passed on, and recovered, immediately by increased electricity rates under § 3 of the contract.
To begin with, under Florida law there are two kinds of taxes: direct and indirect.
City of Deland v. Florida Public Service Comm’n,
It is therefore clear to the Court that the same two kinds of taxes under Florida law were anticipated by § 3 of the contract. Section 3 provided for the adjustment of rates to reflect any allocable “ad valorem taxes which may hereafter be 'assessed against and payable by the utility on the properties of its electric system”. Unmistakeably, that clause anticipates direct, ad valorem taxes on the assessed values of JEA’s property. Similarly, § 3 of the contract allows adjustment of rates to reflect
. any other taxes or assessments imposed by any government authority . whether levied on the basis of meters or customers or the price of or revenue or income from electric energy or service sold or the volume of energy generated or purchased for sale or sold .
Although JEA argues that this clause anticipates the increased Venezuelan export tariffs, the language of the clause is that of indirect excise taxation under Florida law. Compare the language of City of Deland v. Florida Public Service Comm’n, supra at 738.
The increased tariffs on oil exported from Venezuela resulted from an increased income tax, under Article 41 of the Venezuelan Income Tax Law, upon a taxpayer-exporter who exports petroleum crude oil and petroleum derivatives. Affidavit of Charles D. Evans at 1-2, 4. Because the exporter is taxed by Venezuela according to a fixed income level, the only way he can recover the increased tax that he must pay the Venezuelan government is to be sure that his prices for petroleum at least keep pace with the new, increased tax on him. Hence, the price of petroleum crude oil has increased. The American importer paying an increased purchase price to the exporter, in turn, increased his prices to utility companies, like JEA; and they, in turn, incurred increased cost bases for their fuel which they could receive only from increased rates, subsidies, or some other source.
It is clear to the Court, nonetheless, that the Venezuelan tax does not qualify as a tax anticipated, and allowed for, under § 3 of the contract. The tax is not one of the two kinds of taxes recognized under Florida law, and thus it could not have been anticipated that such a tax might be imposed on JEA. Furthermore, the tax was not imposed against JEA. It is at least two middle-men removed from JEA. Having been imposed on the income of the Venezuelan exporter its effect upon the export-import-retail chain is increased prices. The impact on JEA occurs eventually through higher cost bases-debts-incurred by JEA in its obligation to pay the purchase prices under various supply contracts.
The burdens of the two kinds of taxation under Florida law do not arise from contractual obligations. Neither are they “debts” in the ordinary commercial meaning of that term.
Kathleen Citrus Land Co. v. City of Lakeland,
In considering these motions to strike, under Fed.R.Civ.P. 12(f), the facts have been assumed to be as set forth in JEA’s answer,
Kelly v. Kosuga,
