These appeals are from two orders of the bankruptcy court. 2 The first order, dated May 7, 1998, sustained an objection by Debt- or, Payless Cashways, Inc. (Payless), to Claim Number 5116 filed by Amteeh Lighting Services Company (Amteeh). The second, dated July 17, 1998, denied Amtech’s motion for reconsideration. The effect of the bankruptcy court’s orders was to allow Am-tech an unsecured claim in the sum of $1,733,449.84, but to deny Amteeh secured status on that claim. We affirm.
FACTS AND PROCEDURAL HISTORY
A. The Agreement
Payless was engaged in the retail sales business. Before it filed for bankruptcy it was doing business in at least twenty states. Amteeh designs, builds, and maintains internal and external lighting systems for businesses.
This dispute arises out of an Agreement dated April 1, 1995, between Payless and Amteeh (the Agreement). Under the Agreement, entitled “Lighting Retrofit and Maintenance Agreement,” Amteeh agreed to retrofit or relamp ceiling-mounted lighting fixtures at 164 Payless locations in twenty states. These services were identified as “Initial Services.” Amteeh was also to provide continuing maintenance services, which included inspecting all locations for burned out bulbs and replacing inoperative lights, ballasts, lamp holders, and wiring on a regular and on an emergency basis. These services were identified as “Continuing Services.”
Payless did not pay cash for the initial installation, and it did not borrow money from others to do so. Instead, the parties agreed to a credit arrangement whereby the cost of the retrofitting and relamping would be amortized over a forty-eight month period. These costs were spread out to each of the 164 Payless locations. In addition, for each location, Payless would pay a monthly charge for the continuing maintenance services, as well as extra charges for replacement lightbulbs, lamps, and supplies. Under Paragraph 6 of the Agreement, Payless had the right to terminate the contract without cause as to any or all stores on sixty days’ notice. Under Paragraph 7, either party
5. If Customer [Payless] terminates the Agreement pursuant to Paragraphs 6, 7, or 8 then Customer [Payless] shall pay to the Contractor [Amtech] an amount equal to 100% of unaccrued Initial Services for the number of months remaining on the Agreement for each Store that has received an Initial lighting retrofit and that is being serviced under the Agreement at the effective date of the notice. This is not a penalty, but represents initial costs, overheads, and profits for work completed by Contractor in providing labor and materials for Initial lighting retrofit. If Customer terminates the continuing service portion of this agreement pursuant to the provisions of PARAGRAPH 7 ONLY (Breach of agreement or default by Am-tech Lighting Services), it is agreed that the unaccrued initial services may still, at the customer’s option, be amortized over the term of the agreement under the established terms and conditions.
There was conflicting evidence regarding whether the Initial Services and the Continuing Services portions of the contract were segregable. A Payless witness testified that Payless’s obligation to pay for the original installation and its obligation to pay for the continuing maintenance services were seg-regable, and Payless could cancel the continuing maintenance portion at any time. Amtech’s witness testified that he viewed the continuing maintenance services as an integral part of the overall contract. He pointed, particularly, to his view that the energy savings the Agreement was designed to generate could be diminished if the wrong replacement light bulbs were installed after the original installation. He opined that he doubted Payless would have canceled because of the practical difficulties of bringing in a new maintenance contractor.
Amtech completed all initial installation work at all locations over a period of approximately twelve months. The bankruptcy court found, and the parties agree, that Am-tech completed the initial installations in Minnesota on August 29, 1995; Nevada on December 20, 1995; Oklahoma on February 9, 1996; and, Texas on April 8, 1996. Am-tech also provided routine maintenance and repair services at all 164 locations. For a while, things went smoothly. Amtech finished the initial installation work at all locations, and Payless paid both the monthly amortized per-location installation charge and the monthly service charge for the continuing maintenance services at each such location. In addition, while not specifically covered by the Agreement, from time to time Payless would request and Amtech would perform additional upgrade work, such as installing an additional outdoor parking light or replacing a lighting pole knocked down accidentally.
The monthly charges for the continuing maintenance and for any additional installation work ordered after completion of the original installation were billed and paid for promptly; they are not part of these appeals. It is the amount still due and owing for the Initial Services at the time of the bankruptcy filing that is in contention. At the date Payless filed for bankruptcy relief, Amtech had taken no steps to perfect a mechanics’ lien in any of the several states. By failing to do so it exposed itself to the argument that Payless makes in these appeals, i.e., that Amtech is not entitled to mechanics’ liens for the unpaid amount for the initial installation work because it failed to timely perfect.
B. The Payless BankRuptcy
On July 21, 1997. Payless filed for relief under Chapter 11 of the Bankruptcy Code. On September 27, 1997. Payless advised Amtech that, pursuant to 11 U.S.C. § 365, it would reject the contract effective October 1, 1997. On October 13, 1997, Amtech filed Claim Number 5116 for $1.733.449.84, which represents the remaining amount due for the initial installation work done at locations in four of the twenty states covered by the Agreement: Minnesota ($214.883.39). Oklahoma ($197,914.24), Nevada ($158,450.00), and Texas ($1,162,201.45). Amtech’s claim asserted that it was secured, and in subse
On November 19, 1997, the bankruptcy court confirmed a Plan of Reorganization, which is expected to pay unsecured creditors pennies on the dollar. Between November 24, 1997, and December 18, 1997. Amtech took steps to perfect mechanics’ liens for sixty-one stores located in Minnesota, Oklahoma, Nevada, and Texas. While Payless ' agrees that Amtech has an allowable unsecured claim for all amounts still owed for the initial installation work for all stores in all states, it has objected to the secured status of such a claim.
C. The BanKruptcy Court Decision and the First Appeal
Following an evidentiary hearing, the bankruptcy court rejected Amteeh’s claim to mechanics’ lien rights. The court held that, on its face, the contract was divisible into two parts, one consisting of initial design and installation work (Initial Services) and one consisting of ordinary maintenance and repair services (Continuing Services). It noted that the initial installation work by far represented the greater percentage of each monthly bill for each location. 3 The court held, in essence, that the Agreement had two components: 1) installation of a new lighting system, the charges for which were payable over forty-eight months, unless, under Paragraph 5, they became immediately due and payable by reason of termination of the Agreement, and 2) ordinary maintenance and repair, the charges for which were billed on a monthly basis.
The bankruptcy court separately analyzed the law in Minnesota, Oklahoma, Nevada, and Texas. Because it was undisputed that all initial installation was completed in late 1995 and early 1996, the bankruptcy court held that, in all four states, the time to perfect had long since passed. The bankruptcy court also rejected Amtech’s argument that, because Payless was promptly paying each month, Amtech would have risked a suit for slander of title if it had attempted to perfect a mechanics’ lien earlier. The court noted that parties cannot extend by contract the statutory time limit to perfect a mechanics’ lien and that Amtech could have protected itself by treating the transaction for what it was, a loan, and taken steps to perfect a security interest in the various states.
D. The Motion to Reoonsider, the Second Order, AND The Seoond Appeal
On July 2, 1998, while Amtech’s appeal from the order of May 8, 1998, was pending, Amtech filed a motion to reconsider the claim pursuant to 11 U.S.C. § 502(j). Amtech urged that, while preparing to appeal from the initial order, it hired Texas counsel who advised for the first time that the Texas Constitution provided Amtech a new alternative basis for asserting a lien.
The bankruptcy court denied Amtech’s motion. It held that Amtech had not shown that its neglect in failing to argue and prove this point at an earlier stage during the evidentiary hearing was excusable. Specifically, the court held that reconsidering the order posed a danger of prejudice to Payless and would substantially impact judicial economy because the court had already heard the evidence and decided the matter once. Although the court found that Amtech acted in good faith, it determined that the reason for delay in asserting the constitutional lien theory was its failure to retain knowledgeable counsel in the first place. On balance, the court found that these factors did not support a finding of excusable neglect. The court also held that establishing a constitu
APPEAL FROM THE MAY 8, 1998, ORDER
A. STANDARD OF REVIEW
We review findings of fact for clear error, while conclusions of law are subject to de novo review.
Forbes v. Forbes (In re Forbes),
A key question in the appeal from the May 8,1998, order is whether the Agreement is entire or divisible, that is, whether the parties intended one overall continuous contract. The bankruptcy court held that the parties intended two separate agreements. In all four states involved, a trial court’s determination of whether a construction contract is divisible is a question of fact reviewed for clear error.
Geo, Sedgwick Heating & Air Conditioning Co. v. Riverwood Cos.,
B. GENERAL PRINCIPLES
As a general rule, a mechanics’ lien is the creation of statute, not of the common law.
Fisher Bros. v. Harrah Realty Co.,
It is further well accepted that parties may not by contract alter the statutory requirements with respect to the type of work that is lienable or the appropriate steps that must be taken to perfect. Because, until perfected, these liens are secret and work to the disadvantage of other creditors, a party claiming such a lien must meet the statutorily set criteria for attachment and perfection, regardless of whether the parties have agreed upon different terms.
See Industrial Structure & Fabrication, Inc. v. Amowhead
At times the question arises as to whether a series of activities is to be considered a continuing contract for purposes of determining whether a lien has been timely perfected. This commonly occurs when a contractor falls to timely perfect at the conclusion of initial construction work, performs additional work, and then perfects. Under the theory of “continuing contract,” if work is performed over a period of time, or in a series of steps, and the parties intend one continuous contract, the time for filing or perfecting such a lien does not commence until conclusion of the last step.
Kahle v. McClary,
C. The MechaNics’ Lien Law
In all four states involved, Amtech’s argument that it is entitled to mechanics’ lien protection under the doctrine of continuing contract fails for each of two reasons. First, even if the continuing contract theory were applicable, the bankruptcy court found as a matter of fact that the parties intended two separate agreements, one for the initial installation (Initial Services) and one for ongoing maintenance and repair (Continuing-Services). That finding was not clearly erroneous. Second, the continuing maintenance services Amteeh performed are non-lienable. In all four states, ordinary repair and maintenance is simply not protected by the mechanics’ lien statutes. The continuing contract theory does not apply where the continuing work is itself nonlienable.
1. Minnesota
In Minnesota, “Whoever ... contributes to the improvement of real estate by performing labor, or furnishing skill, material, or machinery for any of the purposes hereinafter stated ... shall have a lien upon the improvement, and upon the land on which it is situated or to which it may be re-moved_” Minn.Stat.Ann. § 514.01 (1990) (emphasis added). The lien expires “at the end of 120 days after doing the last of the work, or furnishing the last item of skill, material, or machinery,” unless within this period the party furnishing the improvements files a mechanics’ lien statement with the appropriate official office and notifies the owner, an authorized agent, or the person who entered into the contract. Id. § 514.08. Thus, successful assertion of a mechanics’ lien in Minnesota requires two things: first, that the work be an “improvement,” as the cases have defined and interpreted that statutory term, and, second, that the party claiming the lien timely filed and served the lien statement.
Amteeh did not perfect its mechanics’ lien within 120 days after completing the last of the initial installation work. It urges, however, that the Agreement was a continuous, indivisible contract that did not conclude until October 1, 1997. An early Minnesota case expressed the concept of continuing contract as follows:
Where work, distinct in its nature, is performed at different times, the law supposes it performed under distinct engagements, as where the work at one time is for building and at another for repairing. So, where distinct contracts are in fact made, as distinct contracts for different parts of the work, the work done undereach contract must be considered as entire of itself. But when the work, etc., is done or furnished, all going to the same general purpose, as the building of a house, or any of its parts, though such work, etc., be ordered and done at different times, yet if the separate parts form an entire whole, or are so connected together as to show that the parties had it in contemplation that the whole should form but one, and not distinct matters of settlement, the whole account must be treated as a unit, or as being but a single contract.
Fitzpatrick v. Ernst,
The following factors are viewed as important in determining whether the parties intended
one
contract or two: (1) the lapse of time following the last major work; (2) whether the subsequent work involved a trifling amount; and, (3) the general circumstances under which the work was done.
Geo, Sedgwick Heating & Air Conditioning Co. v. Riverwood Cos.,
Moreover, the continuing repair work Amtech provided is not lienable. This is important because nonlienable activities tagged onto the end of a contract for installation may not extend the time for perfection. The doctrine of continuing contract does not go that far. Improvement is a developed term of art in Minnesota, and elsewhere, meaning work that involves
both
enhancement of capital value of the realty and something permanent in nature.
See, e.g., Kloster-Madsen, Inc. v. Tafi’s, Inc.,
Indeed, the Minnesota cases cited and relied on by Amtech do not support its point. Rather, they establish the opposite. In each, the later work that the contractor used to argue the continuing contract theory was clearly lienable or was necessary for the
Shaw v. Fjellman,
The contract was divisible, and the continuing contract theory has no application. Accordingly, Amtech is not entitled to a lien in Minnesota.
2. Oklahoma
Under Oklahoma law, “[a]ny person who shall ... perform labor, furnish material or lease or rent equipment ... for the erection, alteration or repair of any building, improvement, or structure thereon or perform labor in putting up any fixtures, machinery in, or attachment to, any such building, structure or improvements ... shall have a lien upon the whole of said tract or piece of land, the building and appurtenances.” Oklahoma Stat. tit. 42, § 141 (1990). A mechanics’ lien statement must be filed “within four (4) months after the date upon which material or equipment used on said land was last furnished or labor last performed under contract_” Id. § 142. Amtech did not attempt to perfect its mechanics’ lien in Oklahoma until more than a year after it had finished the initial installation work in that state. Thus, once again, it is forced to argue that the contract was a continuing one that did not conclude until October 1, 1997.
Under Oklahoma law, for a contract to be viewed as one whole, “the terms, nature, and purpose [must] show that it is contemplated and intended that each and all of its parts, material provisions, and consideration are common each to the other and interdependent.”
Holden v. DuBois,
In addition, in Oklahoma as in Minnesota, ordinary repairs and maintenance are not lienable services.
Lewis v. Red,
And, as in Minnesota, there are an ample number
of
cases distinguishing nonlienable repair or maintenance from lienable initial construction work in the context of a continuing contract. In
Cushing Country Club v. Boardman Co.,
So, too, in Oklahoma, Amtech, having failed to perfect at the conclusion of the installation work, has lost any claim to the protection of a mechanics’ lien.
3. Nevada
The Nevada mechanics’ lien statute provides: “[A] person who performs labor upon or furnishes material of the value of $500 or more, to be used in the construction, alteration or repair of any building ..., has a lien upon the premises and any building, structure and improvement thereon....” Nev-Rev.Stat. § 108.222 (1997). “Every person claiming the benefit of [§ 108.222] must record his notice of lien ... (a) Within 90 days after the completion of the work of improvement; (b) Within 90 days after the last delivery of material by the lien claimant; or (c) Within 90 days after the last performance of labor by the lien claimant, whichever is later.” Id. § 108.226.
Amtech failed to file its lien within ninety days of the date of completion of the installation work in Nevada. Like the other states involved, Nevada recognizes the continuing contract theory, upon which Amtech relies to avoid loss of its rights, and it is described in similar fashion. 7
In Nevada, “[w]hether a contract is entire, or separable into distinct and independent contracts is a question of the intention of the parties, to be ascertained from the language employed and the subject-matter of the contract.”
Linebarger v. Devine,
Also, Nevada, like the other two states discussed, does not provide mechanics’ lien protection for ordinary repairs or maintenance.
See Schofield v. Copeland Lumber Yards, Inc.,
And, once again, the cases cited by Amtech disprove its point. Each involves work necessary to complete the original project. In
Peccole,
the court allowed a mechanics’ lien claim to be filed for varnishing done to a counter after a break in work. The court made clear, however, that the varnishing completed the project, and it would not have applied the continuing contract theory to the situation if the contractor had merely been repairing his prior completed work.
Peccole,
Amtech failed to timely perfect its lien in Nevada. It cites no authority, and we find none, which extends a continuing contract theory to a situation where the improvement work is completed (including touch up repairs required to finish the project), yet ongoing ordinary repairs and maintenance extend the time for filing of a mechanics’ lien. Accordingly, it has not perfected a mechanics’ lien in Nevada.
4. Texas
The Texas Property Code provides the statutory basis for a claim to a mechanics’ hen. Texas law provides: “(a) A person has a lien if: (1) the person labors, specially fabricates material, or furnishes labor or materials for construction or repair in this state of: (A) a house, building, or improvement ... and (2) the person labors, specially fabricates the material, or furnishes the labor or materials under or by virtue of a contract with the owner or the owner’s agent, trustee, receiver, contractor, or subcontractor.” Tex. PROp.Code ANN. § 53.021 (West 1995). However, Texas law approaches the time within which liens must be filed in a distinct manner. All persons who claim a lien “must file an affidavit with the county clerk of the county in which the property is located ... not later than the 15th day of the fourth calendar month after the day on which the indebtedness accrues.” Id. § 53.052(a). In an effort to clearly provide protection both for original contractors and also for subcontractors and materialmen, the law distinguishes each of their filing deadlines by defining “accrual” differently depending on which type of contract is involved. 8 For subcontractors and materialmen, indebtedness accrues “on the last day of the last month in which the labor was performed or the material furnished.” Id. § 53.053(c). Indebtedness to an original contractor, such as that involved in this case, accrues “on the last day of the month in which the original contract has been completed, finally settled, or abandoned.” Id. § 53.053(b)(2). Texas also provides for a “retainage lien.” During the progress of work, an owner must retain ten percent of the contract price or the value of the work to secure payment for materialmen and subcontractors. Id. §§ 53.101-53.102. A retainage lien must be filed not later than the 30th day after the work is “completed.” Id. § 53.103. “Completion” is defined to mean “the actual completion of the work, including any extras or change orders reasonably required or contemplated under the original contract; other than warranty or repair work.” Id. § 53.106(e).
Amtech 9 asserts that the Texas statute, which allows a contractor who has an original contract with an owner to delay filing its lien until the contract is “completed,” is designed to encourage such contractors to wait until their contracts are fully completed before they take steps to perfect. Accordingly, Am-tech urges that Texas public policy, as well as the language of the statute itself, require a much more restrictive view of whether a contract such as this one may be found divisible. Amtech also asserts that, using this more restrictive view of the fact finder’s license, the trial court’s finding on the issue was clearly erroneous. Finally, while asserting that the issue is irrelevant, Amtech takes the position that in Texas, ordinary repairs of the type performed by Amtech are lienable. According to Amtech, “[T]here is no ‘enhancement test’ under the Texas Property Code.” Amtech cites no Texas authorities for these rather remarkable arguments.
Texas accepts the general view of divisible contracts: no one test or rule of law is determinative as to whether a contract is entire or divisible.
Johnson v. Walker,
As discussed above, the bankruptcy court did not clearly err in finding that the Agreement was divisible. The language and the subject matter of the Agreement suggest the parties intended a divisible contract because of the clear distinction between the initial services and the continuing services. In addition, the price is apportioned between the two separate parts of the Agreement, which also indicates a divisible contract.
See Walker,
We also find no support for Am-tech’s argument that there is no “enhancement” test for successful assertion of a Texas statutory mechanics’ lien. In Texas, ordinary repairs and maintenance are not lienable activities. “A mechanic’s lien is defined as a lien created by law on real estate, and the improvements thereon, to secure persons who, within the intent of the law, have labored or furnished material, machinery, fixtures, or tools to erect or repair the improvements.”
Efficient Energy Systems, Inc. v. J. Hoyt Kniveton, Inc.,
A case closely on point is
TDIndustries, Inc. v. NCNB Texas Nat’l Bank,
Thus, while the Texas statutory mechanics’ lien provides a slightly more complicated sequence for perfection, Texas is similar to the other three states. The time for timely perfecting commenced at the completion of the initial installation. Amteeh did not timely perfect. The continuing maintenance services do not extend its time for timely perfection.
D. ConClusion as to First Appeal
In conclusion, we find no clear error in the bankruptcy court’s finding that the parties intended a divisible contract, one for installation and one for ongoing ordinary repairs and maintenance. The bankruptcy court correctly determined that Amteeh failed to timely perfect a mechanics’ lien in Minnesota, Oklahoma, Nevada, and Texas. The court properly held that parties may not, by contract, alter mechanics’ lien statutory requirements. To allow Amteeh to prevail on a theory of continuing contract under the facts presented would allow it to expand by contract the statutory parameters of the mechanics’ lien laws in each of those states. Finally, we agree with the bankruptcy court’s view of Amtech’s argument regarding a potential suit for slander of title. Amteeh could have easily protected itself by obtaining mortgages.
APPEAL FROM THE JULY 17, 1998, ORDER
Finally, we turn to Amtech’s appeal from the bankruptcy court’s order denying reconsideration of the claim. Amteeh sought reconsideration of the May 8, 1998, decision disallowing it a secured claim in Texas because Amteeh discovered a new theory of recovery that it wanted to establish.
A. The Texas ConstitutioNal Lien
The Texas constitutional lien is not obscure.
10
It is announced in very basic treatises on the subject of Texas mechanics’ lien law. The Texas constitutional lien is distinct from and exists independent of the statutory mechanics’ lien.
Ralph M. Parsons Co. v. South Coast Supply Co. (In re A & M Operating Co.),
When it filed its claim and tried its case, Amtech did not assert that it was entitled to a constitutional lien. It tried its case and introduced its evidence on a wholly different theory. Because Payless is a bona fide purchaser, see 11 U.S.C. § 544(a)(3) (1994), the parties agree that, if the lien applies at all, it can only apply as to personalty that is not permanently affixed to the realty. Now, having “discovered” this new way of asserting a lien, Amtech insists that it should have a constitutional lien for loose light bulbs and other personalty delivered to the Texas locations and for any of the installed lamps, ballasts, and similar materials that it initially installed and that could be removed without damage to the realty. Amtech introduced no evidence on the possible value of any unaf-fixed personalty nor any evidence as to the extent, if at all, that the installed lamps, fixtures, ballasts and similar supplies could be removed without damage to the realty. While it suggests that proof of the value of this portion of the initial work would not be extensive, that seems doubtful, and, in any event, it assumes that successful assertion of the constitutional hen would require reopening discovery and holding a new hearing to deal with valuation.
B. Section 502(j)
Section 502(j) of the Bankruptcy Code provides, in relevant part: “A claim that has been allowed or disallowed may be reconsidered for cause. A reconsidered claim may be allowed or disallowed according to equities of the case.” 11 U.S.C. § 502(j);
see also
Fed.R.Bankr.P. 3008. Reconsideration of a claim may be requested at any time.
Employment Sec. Div. v. W.F. Hurley, Inc. (In re W.F. Hurley, Inc.),
When a motion to reconsider is made after expiration of the time to appeal, as in this case, it is treated as a motion for relief from judgment under Federal Rule of Bankruptcy Procedure 9024.
Abraham v. Aguilar (In re Aguilar),
We review
the
denial of a motion for reconsideration under an abuse of discretion standard.
See, e.g., Halverson v. Estate of Cameron (In re
Mathiason),
D. Exousable Neglect
The seminal case on excusable neglect is
Pioneer Inv. Servs. v. Brunswick Assocs. Ltd. Partnership,
From
Pioneer,
we derive the following rules. First, excusable neglect encompasses both simple, faultless omissions and omissions caused by carelessness.
Pioneer,
The Eighth Circuit has interpreted the standards articulated by
Pioneer
on at least three occasions. In the most recent,
Johnson v. Dayton Elec. Mfg. Co.,
Jones Truck Lines, Inc. v. Foster’s Truck & Equip. Sales, Inc. (In re Jones Truck Lines, Inc.),
Finally,
Harlow Fay, Inc. v. Federal Land Bank (In re Harlow Fay, Inc.),
We now turn to an application of the Pioneer factors, as interpreted and developed in this circuit’s case law. In this case, the fourth Pioneer factor, Amtech’s good faith is not questioned. However, the parties dispute the applicability of the remaining three Pioneer factors.
For both of the first two Pioneer factors, prejudice to the nonmoving party and impact on efficient judicial administration, the bankruptcy court concentrated on the fact that it had already heard and decided the matter once. Although the doctrines of res judicata and collateral estoppel do not strictly apply in a motion for reconsideration, 12 the bankruptcy court did not abuse its discretion in finding that the principles underlying these doctrines were relevant and that rehearing the matter would prejudice both the Debtor and efficient judicial administration.
This is not the typical case where courts find a lack of prejudice when a default judgment has been entered or a filing deadline has been missed.
See, e.g., Johnson v. Dayton Elec. Mfg. Co.,
Further, in considering the third factor, the reason for the delay, we must focus heavily on the blameworthiness of the moving party.
Johnson,
In sum, the bankruptcy court did not abuse its discretion in finding that three of the four Pioneer factors weighed against finding excusable neglect. Thus, Appellant did not establish the cause necessary to reconsider the claim under § 502(j). 13
CONCLUSION
ACCORDINGLY, the decision of the bankruptcy court is AFFIRMED.
Notes
. The Honorable Arthur B. Federman, United States Bankruptcy Judge, Western District of ' Missouri.
. For example, at one store in Texas, the monthly contract amount was $919.02, $836.82 of which represented the amortized payment amount for the initial installation and $82.20 of which represented the monthly maintenance fee.
. The statute allowed a lien to be filed "for the erection, alteration, repair, or removal of any house ... or other building or appurtenance.” Ch. 90, § 6229, 1894 Minn.Laws 1681.
. Ch. 69, § 3505, 1905 Minn.Laws 701 (emphasis added). While the statute has been amended many times since, it has at all times referred to “improvement.” See Ch. 69, § 7020, 1913 Minn. Laws 1521; Ch. 285, § 1, 1917 Minn.Laws 421-22; Ch. 229, § 1, 1921 Minn.Laws 280-81; Ch. 69, § 8490, 1923 Minn.Laws 1166; Ch. 274, § 1, 1925 Minn.Laws 323-24; Ch. 69, § 8490, 1927 Minn.Laws 1690-91; Ch. 247, § 1, 1973 Minn. Laws 482-83; Ch. 381, § 1, Minn.Laws 683 (each providing a lien for "whoever contributes to the improvement of real estate ...”).
. It is well settled in this state that, where material is furnished or labor performed for the same general purpose, as in the construction of a building ..., although the material be ordered or labor performed at different times, yet, if the separate parts form an entire whole and are so connected as to show that the parties regarded the separate items furnished, at different times, as being part of the entire account, and not separate accounts, the furnishing of the material or tire performance of labor in this manner will be considered as a single contract....
Clark, 288 P. at 936.
. When work or material is done or furnished, all going to the same general purpose, as the building of a house or any of its parts, though such work be done or ordered at different times, yet if the several parts form an entire whole ot-are so connected together as to show that the parties had in contemplation that the whole should form but one, and not distinct matters of settlement, the whole account must be treated as a unit, or as being but a single contract.
Tonopah Lumber Co. v. Nevada Amusement Co.,
. See Eldon L. Youngblood, Mechanics’ and Materialmen's Liens in Texas, 26 S.W.L.J. 665, 666 (1972). In its attempt to protect subcontractors and materialmen as well as original contractors, "the procedures prescribed by the current statutes, particularly procedures for perfecting the subcontractor's lien, have become vastly more complex and unwieldy.” Id.; see also Sara E. Dysart, USLTA: Article 5 “Construction Liens” Analyzed in Light of Current Texas Law on Mechanics’ and Materialmen’s Liens, 12 St. Mary’s L.J. 113, 116 (1980).
. Actually, Amtech deferred this portion of the appeals to Amicus, International Association of Lighting Management Companies, which made the arguments on behalf of Amtech.
. During oral argument on the motion to reconsider, counsel for Amteeh attributed his failure to learn of the constitutional lien to inadequate research conducted by the second year associate who had been assigned to research the Texas law, and to the fact that the two "treatises” he looked to, Martindale Hubbel’s Texas Law Digest and the Commerce Clearing House Secured Transactions Guide, did not mention it. These were the only "treatises” he had in his law library.
. At one point below the parties argued over whether the bankruptcy court even had jurisdiction to consider the motion to reconsider while the first appeal was pending. The pending appeal from the May 8, 1998 Order disallowing the claim did not divest the bankruptcy court of jurisdiction to hear the motion to reconsider. While an appeal is pending, such a motion may be considered on its merits and denied.
Brode v.
Cohn,
. Amtech cites
In re Yagow,
. We note that the circumstances of this case do not present the type of situation where consideration of an issue for the first time on appeal is appropriate.
Singleton v. Wulff,
