MEMORANDUM AND ORDER
This matter is before the Court on plaintiff’s motion for a preliminary injunction. The motion will be denied.
FACTS
Plaintiff Ames Construction Company is a Minnesota corporation engaged primarily in earth work, excavation, heavy highway work and site development. The present action arises out of Ames’ involvement in *503 the construction of the 1-394 construction project in Minneapolis. Ames successfully bid on an earth-moving job for the 1-394 project, and subcontracted with four trucking firms to deliver granular fill material to the site. The Davis-Bacon Act, 40 U.S.C. § 276a, et seq., requires that government contractors pay “prevailing wage rates” at federal or federally-assisted construction projects for work performed “on site.” The four firms with whom Ames subcontracted for hauling sand and gravel to the site, however, paid their truck drivers less than “prevailing wages” when they delivered material to the site, on the grounds that this work was not covered by Davis-Bacon because it was not “on site.” Ames claims that it, in preparing and submitting its bid on the 1-394 project, and the trucking firms in setting the wages for their truckers, relied upon specific representations concerning the applicability of Davis-Bacon to the trucking operations made by the Minnesota Department of Transportation (MnDOT), on a well-established policy of the Federal Highway Administration, as well as on specific guidelines of the Department of Labor Field Operations Handbook.
After plaintiff began work on the 1-394 project on March 11, 1985, the Department of Labor (DOL) began an independent investigation of Ames’ payroll records to determine whether the trucking firms were complying with the Davis-Bacon Act. The Wage and Hour Division of the DOL determined that the four trucking firms owed their employees approximately $530,614.20 under the provisions of Davis-Bacon, as well as the Contract Work Hours and Safety Standards Act. After the DOL notified each individual trucking firm of their respective back wage assessments, and after each of the firms refused to pay these assessments, the DOL sent Ames a letter demanding that Ames either commit to paying the $530,614.20 in back wages by July 19, 1989 or face immediate suspension of contract funds earned on the 1-394 project. On August 11, 198.9, the regional director of the DOL’s Wage and Hour Division wrote to the contracting officer of MnDOT ordering him to withhold the funds from Ames’ next pay request on the 1-394 job. On September 11, 1989, the MnDOT officer responded by stating that the funds would be withheld on November 1, 1989. 1
On October 5, 1989 plaintiff brought this action claiming that withholding funds due Ames for work performed on the 1-394 project prior to providing a hearing on Ames’ liability for Davis-Bacon violations would be a deprivation of property without due process of law. Ames seeks an order preliminarily enjoining the MnDOT and the DOL from withholding funds until a hearing on the alleged violations has been held. DISCUSSION
The test for whether preliminary injunctive relief should issue is set forth in
Dataphase Systems, Inc. v. C L Systems, Inc.,
(1) the threat of irreparable harm to the movant;
(2) the state of balance between this harm and the injury that granting the injunction will inflict on other parties litigant;
(3) the probability that movant will succeed on the merits; and
(4) the public interest.
Dataphase,
The key issue under the Dataphase factors is whether Ames is likely to prevail at a trial of the merits of its claim that it will be denied due process by the prehearing suspension of funds. Section 1(a) of the Davis-Bacon Act, the provision under which the DOL ordered suspension of the funds, provides that every contract to which the Act applies must contain a stipulation that:
there may be withheld from the contractor so much of accrued payments as may be considered necessary by the contracting officer to pay [employees on the contract] the difference between the rates of *504 wages required by the contract ... and the rates of wages received____
40 U.S.C. § 276a(a). Regulations promulgated pursuant to this provision require that payments under the contract shall be withheld for failure to comply with the Act:
In the event of failure or refusal of the contractor or subcontractor to comply with labor standards clauses contained in section 5.5 in the applicable statutes ... a federal agency, upon its own action or upon written request of an authorized representative of the Department of Labor, shall take such action as may be necessary to cause a suspension of the payment, advance or guarantee of funds____
29 C.F.R. § 5.9. The Act provides that following notification of alleged violations, a contractor may, within thirty days, make a written request for hearing. 29 C.F.R. § 5.11(b)(2). Upon receipt of a contractor’s request, the matter is referred to the chief ALJ for designation of an ALJ to conduct hearings. 29 C.F.R. § 5.11(b)(3). The hearing is to be conducted according to the rules of practice for administrative proceedings as set forth in 29 C.F.R. Part 6. While these administrative procedures are pending, contract funds are held in a deposit account. The provisions do not require a hearing prior to suspending contract payments, nor do they contain a deadline by which the government must provide a hearing following suspension.
Plaintiff does not question the constitutionality of the suspension provisions per se, but rather disputes the DOL’s application of them through suspension of contract payments prior to providing plaintiff with an opportunity to be heard on the alleged Davis-Bacon violations. By failing to provide such a pre-suspension hearing, Ames alleges that the DOL has deprived it of property without due process of law in violation of the fifth amendment.
I. The Deprivation Inquiry
A due process claim has two elements: (1) deprivation of a protectible interest, and (2) denial of adequate procedural protections.
Goldberg v. Kelly,
Much of the existing wealth in this country takes the form of rights that do not fall within traditional common law concepts of property. It has been aptly noted that
“[sjociety today is built around entitlement. The automobile dealer has his franchise, the doctor and lawyer their professional licenses, the worker his union membership, contract, and pension rights, the executive his contract and stock options; all are devices to aid security and independence. Many of the most important of these entitlements now flow from government: subsidies to farmers and businessmen, routes for airlines and channels for television stations; long term contracts *505 for defense, space, and education; social security pensions for individuals. Such sources of security, whether private or public, are no longer regarded as luxuries or gratuities; to the recipients they are essentials, fully deserved, and in no sense a form of charity.”
Id. n. 8, quoting Reich, Individual Rights and Social Welfare: The Emerging Legal Issues, 74 Yale L.J. 1245, 1255 (1965).
In
Fuentes v. Shevin,
The appellants who signed conditional sales contracts lacked full legal title to the replevied goods. The fourteenth amendment’s protection of “property,” however, has never been interpreted to safeguard only the rights of undisputed ownership. Rather, it has been read broadly to extend protection to “any significant property interest,” including statutory entitlements.
Id.
at 86,
This reading of Sniadach and Goldberg reflects the premise that those cases marked a radical departure from established principles of procedural due process. They did not. Both decisions were in the mainstream of past eases, having little or nothing to do with the absolute necessities of life but establishing that due process requires an opportunity for a hearing before a deprivation of property takes effect. In none of these cases did the court hold that this most basic due process requirement is limited to the protection of only a few types of property interest____ Nor did they carve out a rule of necessity for the sort of non-final deprivations of property that they involved. That was made clear in Bell v. Burson,402 U.S. 535 [91 S.Ct. 1586 ,29 L.Ed.2d 90 ] holding that there must be an opportunity for a fair hearing before mere suspension of a driver’s license. A driver’s license clearly does not rise to the level of “necessity” exemplified by wages and welfare benefits. Rather, as the court accurately stated, it is an “important interest,” Id. at 539 [91 S.Ct. at 1589 ] entitled to the protection of procedural due process of law.
Fuentes,
Defendant does not argue that payments due under a government contract cannot constitute a form of property. Defendant points to the fact that property interests “are defined by existing rules or understandings that stem from an independent source such as state law — rules or understandings that secure certain benefits and that support claims of entitlement to those benefits.”
Board of Regents v. Roth,
The Court finds that the government’s suspension of payments to Ames does constitute a deprivation of property subject to the due process clause of the fifth amendment. At least one of the courts upon which the government relies expressly refused to find that because a contractor was required to sign a contract authorizing the suspension, the contractor could not claim a constitutionally-protected deprivation of property:
In the ordinary case, a distinction is drawn between constitutional questions and simple matters of contract. Parties may contractually agree to what would otherwise be a constitutional deprivation. Where a statute peremptorily requires certain clauses to be inserted, however, as is the case, such clauses are not binding if the statute is found unconstitutional. Thus, the constitutional issue in this instance is not extinguished by plaintiff’s voluntary entry into a contractual arrangement.
Winzeler Excavating Co. v. Brock,
II. The Due Process Inquiry
Due process is a flexible doctrine and calls for such procedural protections as a particular situation demands.
Morrissey v. Brewer,
First, the private interest that will be affected by the official action; second, the risk of an erroneous deprivation of such interest through the procedures used, and the probable value, if any, of additional or substitute procedural safeguards; and finally, the government’s interest, including the function involved and the fiscal and administrative burdens that the additional or substitute procedural requirement would entail.
Mathews v. Eldridge,
In this case, the government correctly notes that the private interest at issue here is not a final deprivation of funds. Plaintiff will be afforded an administrative hearing before an administrative law judge (AU) to determine whether plaintiff has committed the alleged violations before the contract payments will be held to be finally forfeited. Rather, plaintiff’s interest is in the temporary deprivation of the use of its funds. The key issues are the latter two Mathews factors, i.e., the risk of an erroneous deprivation and the value of additional procedural safeguards. The government contends that a hearing is never constitutionally required before an individual is temporarily deprived of property. This argument, however, ignores the plain holdings of Fuentes and other cases in which a hearing was held to be necessary prior to a temporary deprivation of property. As the Court held in Fuentes:
It is now well settled that a temporary non-final deprivation of property is nonetheless a “deprivation” in terms of the fourteenth amendment.
*507
In
Fuentes,
the Supreme Court adopted a three-part test to determine when the government may seize property prior to notice and opportunity to be heard. First, the government must prove that the seizure is “directly necessary to secure an important governmental or general public interest.” Second, there must be a “special need for very prompt action.” Third, the seizure must be initiated by an official after determining that the action was necessary and justified in the particular instance under the standards of a narrowly-drawn statute.
Fuentes,
To date, the three courts that have considered whether the government may withhold funds from a contractor for suspected violations of the Davis-Bacon Act prior to a hearing have all affirmed the practice.
Fry Bros. Corp. v. HUD,
In
Fry Bros.,
a subcontractor on a federally-supported housing project brought an action for declaratory and injunctive relief after a dispute arose between it and the federal government under the Davis-Bacon Act. The Court sustained the district court’s dismissal of the complaint for failure to state a claim. In a brief opinion, the Court held that “the shut down and withholding of funds is provided for by statute, 40 U.S.C. § 276a(a), and the corporation had no right to the ‘hearing’ that it claims was wrongfully denied.”
Fry Bros.,
In
Winzeler,
a contractor sought declaratory and injunctive relief alleging that the withholding of government contract funds prior to a hearing on alleged prevailing wage rate infractions constituted a violation of due process. Plaintiff argued that the Davis-Bacon Act was unconstitutional not only because it failed to provide a hearing before the payment suspension, but also because it contained no provision for a prompt hearing
after
the suspension. The Court in
Winzeler
noted that plaintiff was forced to wait more than two years for a hearing and determination while funds were suspended. The Court therefore considered whether the failure to mandate a hearing within a specified time period made Winzeler’s deprivation more than a “temporary” loss of income. The Court declined, however, to impose timing restrictions upon the Department of Labor because to do so would “have a disruptive effect on the administrative process.”
Winzeler,
In
Blackhawk Mining Co. Inc. v. Andrus,
The Court finds that section 276a comports with the requirements of
Fuentes
for a prehearing seizure of property. The first issue under
Fuentes
is the importance of the governmental interest. The purpose of the Davis-Bacon Act is to assure that workers on public construction projects are paid prevailing wage rates established by private industry.
McDaniel v. University of Chicago,
The language of the [Davis-Bacon Act] and its legislative history plainly show that it was not enacted to benefit contractors but rather to protect their employees from substandard earnings by fixing a floor under wages on government projects____ On its face, the Davis-Bacon Act is a minimum wage law designed for the benefit of construction workers.
Id.
at 176-78,
As to the second element of
Fuentes,
the need for prompt action, the government argues that immediate suspension is necessary in order to guarantee that if the charges are sustained against the company, funds will be available to pay the employees who are ultimately found to be entitled to additional wages. Plaintiff contends that the bond which it was required to post as a condition for obtaining the 1-394 contract should serve as sufficient guarantee of its ability to satisfy the government’s
*509
claim should it be sustained on the merits. In
Blackhawk,
the court held that the government’s interest in prompt assessment and collection of civil penalties to assure compliance with the act was “substantial” and that the prepayment required as a condition of appealing violations of the Surface Mining Control and Reclamation Act were for the purpose of avoiding the “problem of the noncollection of fines and to discourage delay of the collection process through frivolous appeals.”
Blackhawk,
The final
Fuentes
requirement is that the seizure must be initiated by an official acting pursuant to the standards of a narrowly drawn statute after determining that the action was necessary and justified in a particular instance.
Fuentes,
The Court finds that it is reasonably clear that the DOL has sufficiently investigated the claimed violations to establish “probable cause” to believe that violations have occurred.
See Barchi,
A determination that Ames was not entitled to a pre-suspension hearing, however, does not fully resolve the due process inquiry. If Ames was not entitled to a hearing prior to the suspension, it is still entitled to a reasonably prompt post-suspension hearing. In two recent cases, the Supreme Court has elaborated on the amount of time following a governmental deprivation in which a hearing must be provided. In
Barry v. Barchi,
In these circumstances, it was necessary that Barchi be assured a prompt postsuspension hearing, one that would proceed and be concluded without appreciable delay. Because the statute as ap *510 plied in this case was deficient in this respect, Barchi’s suspension was constitutionally infirm under the Due Process Clause of the fourteenth amendment.
Id.
at 66,
Recently, the Court elaborated on
Barchi
in
Federal Deposit Insurance Corporation v. Mallen,
The Court began its discussion by noting that “an important governmental interest, accompanied by a substantial assurance that the deprivation is not baseless or unwarranted, may in limited cases demanding prompt action justify postponing the opportunity to be heard until after the initial deprivation.”
Mallen,
In sustaining the ninety-day period from request for hearing to decision, the Court applied the following analysis:
[E]ven though there is a point at which an unjustified delay in completing a post-deprivation proceeding would become a constitutional violation ... the significance of such a delay cannot be evaluated in a vacuum. In determining how long a delay is justified in affording a post-suspension hearing and decision, it is appropriate to examine the importance of the private interest and the harm to this interest occasioned by delay; the justification offered by the government for the delay and its relation to the underlying governmental interest; and the likelihood that the interim decision may have been mistaken.
Id.
Barchi and Mallen conclusively establish that plaintiff was not entitled to a pre-suspension hearing. If a hearing is not required prior to a deprivation no less serious than that of an individual’s right to pursue his profession, as was the case in Barchi and Mallen, it cannot credibly be argued that Ames has a right to a hearing prior to the suspension of payment of $530,000 due on a $40 million contract. The more troublesome question, however, is whether the statute may be held to violate Ames’ rights of due process by not providing fair assurance of a prompt hearing following suspension, as the Court held in Barchi. Plaintiff claims, and the government does not deny, that in a similar dispute arising out of Ames’ participation in a 1-494 construction project in which the DOL suspended funds for alleged Davis-Bacon violations, more than three years transpired without a hearing before an AU. Indeed, in the Winzeler case, plaintiff complained of a two-year delay before receiving a hearing before the AU. Ames also contends, again without dispute from the government, that it is not entitled to interest while its funds are with *511 held pending final determination on the merits.
Barcki
clearly stated that even where governmental interests justify prehearing deprivations of property, due process is violated if a post-deprivation hearing is so delayed that plaintiff is denied a meaningful opportunity to be heard. This issue, however, is not yet ripe for review. One court, in construing section 1(a) of the Davis-Bacon Act, held that the provision implicitly contained a promise of a “reasonably prompt” hearing.
Winzeler,
As in Winzeler, the Court interprets section 276a(a) as implicitly providing for a constitutionally “prompt” posi-suspension hearing. Thus, given the present posture of the case, Ames is unlikely to prevail on its claim that it has been denied due process, and a preliminary injunction will not be granted. 4
CONCLUSION
Based upon the foregoing, and upon all the files, records and proceedings herein,
IT IS ORDERED that plaintiff’s motion for a preliminary injunction is denied.
Notes
. At Ames’ request, the date for withholding to commence was moved to November 15, 1989.
. The Supreme Court has sustained contractual waiver of due process rights when made "voluntarily, intelligently, and knowingly,"
D.H. Overmyer Co. v. Frick Co.,
. Plaintiff correctly notes that this statement is dicta inasmuch as by the time of the Court’s *508 ruling, plaintiff had already received a hearing before an administrative law judge.
. Since Ames is at present unlikely to prevail on the merits of its due process claim it is not yet necessary to weigh the remaining Dataphase factors.
