This is an action for declaratory relief with respect to a trust agreement.
Performance was commenced, and the work completed in September, 1930. Notice thereof was given to the plaintiff in May, 1931, and in June of that year the paving company served notice on the trustee to proceed to sell the property for nonpayment. Defendant Coryell objected, claiming that she was not in default. Defendant Ralph Strange claimed preferential rights under the agreement, and defendant Edith Strange claimed certain rights by assignment from Ralph Strange. The trustee then brought this proceeding, seeking to determine whether foreclosure should be had, and in such event, what were the interests of the respective parties. The cause was tried in April, 1933, and the court decreed that the sum of $107,217.90 was djie the paving company from defendant Coryell; that the property should be sold by the trustee; that the claim of the paving company should first be paid, then that of Ralph R. Strange, and
The position of defendants is that the paving company never became entitled to the money because it never completed the work in accordance with the contract; and they point chiefly to the fact that the pavement has since settled and cracked, and is in poor condition. Although the agreement provides that the engineer’s certificate of satisfactory completion shall be conclusive on all parties, and Kneese gave such certificate, the defendants contend that the provision is not binding because of the fraud of Kneese.
The evidence produced by defendants fails to support their position. There is no direct showing of fraud on the part of Kneese. Instead, defendants point to the present bad condition of the paving and assert that a certificate of satisfactory completion in such case must necessarily have been given with fraudulent intent, or by such culpable negligence as to amount to constructive fraud. This contention is manifestly unsound. It is entirely possible, for example, that the work was done in full compliance with the plans and specifications, and that the resulting pavement cracks and settlement were due to adverse soil conditions. This was, indeed, the purport of the testimony of a number of witnesses called by the paving company, who were familiar with the job from its inception. The witnesses for defendant Coryell, who testified that the cause of the defective paving was improper performance, were giving opinions based upon observation long after the job was completed. It might be possible, also, that the defective condition which was conceded to exist at the time of trial was in part a result of the complete lack of maintenance or care during the several years which followed the completion of the work. There is thus disclosed a substantial conflict in the evidence and several possible causes for the present defective pavement, and in this state of the record we cannot draw the inference of fraud which the trial court has refused to do.
There being no other evidence suggestive of fraud on the part of Kneese the contract provision making his certificate conclusive is a complete defense against defendant Coryell’s claim that the work was never completed in a satisfactory manner.
(Brown
v.
Aguilar,
No other points require discussion. The judgment is affirmed.
Curtis, J., Waste, C. J., Shenk, J., Preston, J., Thompson, J., and Seawell, J., concurred.
