274 F. 152 | 3rd Cir. | 1921
These cases, growing out of the same business failure, have as many angles as they have parties and subjects-matter. We shall endeavor to view them separately in so far as that is possible.
The questions concern the distribution of funds arising from a receivership in equity. Peoples Brothers, Inc., a Pennsylvania corporation, hereinafter called the Contractor, was under several contracts with the City of Philadelphia for the construction of public works. These contracts called for partial payments as construction progressed and for deferred payments pending completion.
Byberry Farms.
During the progress of the work the City retained 15 per cent, of the amount due, of which 10 per cent, was to be paid on the completion of the contract and 5 per cent, one year thereafter. After completing the contract the City paid the Surety Company $7,231.60, being the final payment less the 5 per cent, of the contract price to be retained for one year. Of this sum the receiver demanded $3,150.40, representing 10 per cent, of the work claimed to have been -completed by 'the Contractor according to the last certificate by the architect prior to stopping work. Contesting the claim of the receiver the Surety Company turned over this sum to the receiver to await the outcome of this litigation.,
The special master and the District Court recognized the surety's right under one bond to be reimbursed in full out of funds retained, and later paid, by the City for its cost of completing the contract, but denied the surety the right under the other bond to apply the balance of the money, so obtained from the City, on account of the amount it had expended in paying claims of laborers and materialmen. By its decree the District Court awarded this disputed balance to the receiver for the benefit of general creditors, thereafter treating the surety as a
Where a surety gives bond to a City for the payment of sub-contractors upon municipal work and pays their claims in full, is the surety not entitled to be reimbursed therefor out of retained percentages under the contract as against the receiver of the defaulting contractor?
This question was argued ou two theories, that of equitable sub-rogation and of assignment. The theory of equitable subrogation constituted the main contention and was argued by both parties with great vigor; and on that theory the case was decided. This issue had its rise in the written application made by the contractor to the Surety Company for the bond in question, which contained a paragraph of which the following is a part:
“VII. * * * And the Indemnitor (Contractor) further agrees in the event of any broach or default on his part in any of the provisions of the contract covered by said suretyship that the said surety, as surety, shall be subrogated to all the rights and properties of the Indemnitor in such contract. * * * ”
The receiver, the special master, and the District Court took the perfectly sound position that neither the subrogation contemplated by the quoted provision nor subrogation on any other theory is applicable to this case, because:
“As under the Pennsylvania decisions the laborers and materialmen did not have any right against the percentages retained by the City, but are merely in a position of general creditors of Peoples Brothers, Ine., the right of subrogation which the Surety Company has cannot arise any higher than that of the creditors whom it has paid.”
In this state of the law- — laborers and materialmen having no rights to reserved percentages — -there were, as to them, no rights to which the Surety Company could be subrogated. Likewise, Peoples Brothers, Inc., had no rights in the fund to which the Surety Company could he subrogated. Obviously, there was no right of subrogation anywhere.
The Surety Company recognized this, for it conceded throughout that sub-contractors had no lien on the fund reserved by the City and that this fund could not have been reached by the subcontractors through any process against the City. Indeed, both sides viewed in the same light the controlling decisions of the .Pennsylvania courts in this regard. Lesley v. Kite, 192 Pa. 268, 43 Atl. 959; Philadelphia v. McLinden, 205 Pa. 172, 54 Atl. 719; Sax v. School District, 237 Pa. 68, 85 Atl. 91.
But the Surety Company did not confine its argument to the question of subrogation, whether within or without the terms of the quoted provision in the Contractor’s application for bond, but maintained on authority of Prairie State Bank v. United States, 164 U. S. 227, 17 Sup. Ct. 142, 41 L. Ed. 412 and Henningsen v. United States Fidelity & Guaranty Co., 208 U. S. 404, 28 Sup. Ct. 389, 52 L. Ed. 547, that, as a surety — which had paid all laborers and materialmen and had thus released the contractor from his obligations to them and had also satis
“Deferred payments and any and all moneys and securities tliat may be due and payable at the time of such default, or on account of extra work or material supplied in connection therewith, or that may thereafter become due and payable on account of said contract, shall be credited for any claim that may be made upon the said Surety by reason of its suretyship as aforesaid.”
This purports to be an assignment of deferred payments by the Contractor to the Surety Company. If this was a valid assignment, it settles the case. But the special master and the court did not, on authority of Christmas v. Russell, 81 U. S. (14 Wall.) 69, 20 L. Ed. 762, regard it as a valid assignment, and, accordingly, held that upon the appointment of the receiver title to the percentages reserved by the City passed to the receiver for general creditors. The case of Christmas v. Russell turned mainly, if not entirely, upon a question of jurisdiction. Without discussing the views there expressed with reference to a valid equitable assignment, we are inclined rather to the views of the same court expressed in Ingersoll v. Coram, 211 U. S. 335, 29 Sup. Ct. 92, 53 L. Ed. 208, accepting the rule stated in Walker v. Brown, 165 U. S. 654, 17 Sup. Ct. 453, 41 L,. Ed. 865, to the effect that an express executory contract in writing, whereby the contracting parties sufficiently indicate an intention to make some particular property or fund therein described or identified, a security for a debt or other obligation,- creates an equitable lien on the property so indicated. Barnes v. Alexander, 232 U. S. 117, 120, 121, 34 Sup. Ct. 276, 58 L. Ed. 530; Hurley v. Ashbridge, 55 Pa. Super. Ct. 523, 526, 527; Stehle v. United Surety Co., 107 Md. 470, 68 Atl. 600.
Applying this rule to cases where a contractor, seeking surety, pledges deferred payments — moneys certain to be due and clearly indicated —-as an inducement for the bond, the courts have very generally recognized such a pledge as a valid consideration moving to the surety, first, to induce it to enter into the bond, and second, at a reduced premium because of' the reduced risk.
The obligation of the Contractor, having assigned to the surety deferred payments on default, became fixed as a part of the status of
We see no reason why parties, if so disposed, can not make such an assignment a valid consideration of a contract. As this is what the parties in this case did, we are of opinion that the fund in dispute should be awarded the Surety Company.
Stewart Street.
The Contractor entered into a contract with the City of Philadelphia for grading Stewart Street. Two similarly conditioned bonds were given by the Contractor with the American Surety Company of New York as surety. In this instance the receiver completed the contract and collected from the City a reserved percentage in the amount of $1,037.-63. The cost of completion to the receiver was $501.91. The surety demands the balance of $535.72 on account of claims it paid under its bond for labor and material in the sum of $664.08. This fund the District Court awarded the receiver for general creditors, allowing the Surety Company to prove its claim as a general creditor for the amount of its disbursements. The only difference between the claims made by the Surety Company for reserved percentages growing out of the Byberry Farms contract and out of the Stewart Street contract is that in the former the Surety Company, upon the receiver’s election not to complete the contract, finished it and received payment therefor out of the reserved percentages; in the latter, the receiver elected to finish the contract himself and, similarly, received payment out of the reserved percentages.
While in the Byberry Farms contract the surety by completing the contract did the work that released the reserved percentages and made them available, the receiver under the Stewart Street contract did the work with that result. Yet we do not see that this affects in any way the assignments by the contractor to the surety of reserved percentages in the event of default. The assignment in each case was absolute, and, we think, was valid. We are of opinion, therefore, that this fund should be awarded the Surety Company.
Fifty-Fourth Street Bridge.
The City of Philadelphia and the Pennsylvania Railroad Company entered into a contract with the Contractor for the construction of a bridge over the Railroad Company’s tracks at Fifty-Fourth Street for
One provision of the contract of the Contractor with the Bonding Company for the bond required by the City was similar in terms and identical in substance with that contained in the contract between the Contractor and the American Surety Company previously considered. It reads:
“In consideration of the company becoming surety, the said company shall as of the date hereof be subrogated to all of its rights, privileges, and properties as principal, or otherwise, in or under said contract, and the applicant further assigns, transfers, sets over and conveys to the said company, all of the deferred payments and retained percentages, and any and all moneys and properties that may be or hereafter becomes due and payable to the applicant (the Contractor) at the time of any breach or default in the contract,” etc.
American Bridge Company.
The decrees of the court below, when reformed in harmony with this opinion, are in all other respects affirmed, with costs to the appellants.
©ssFor other cases see same topic & KEY-NUMBER in all Key-Numbered Digests & Indexes
<§£s>ITor ottier cases see same topic & KEY-NUMBER in all Key-Numbered Digests & Indexes