Nos. 11,696—(171) | Minn. | Jun 21, 1899

COLLINS, J.

Defendant Carroll entered into a contract with defendant board *95in 1896 wherein he agreed to build a court house for the sum of $34,765.96. He was to be paid in instalments, on monthly estimates, 85 per cent, of the cost of labor performed and material furnished. The balance (15 per cent, of the contract price) was to be retained until the building was completed. Carroll, as principal, and this plaintiff, as surety, then executed and delivered to the board a bond in accordance with the provisions of Laws 1895, c. 354, § 1, and conditioned as therein prescribed. It appears- that Carroll failed to pay claims for work and labor performed and materials furnished as the claims matured, and in December, 1896, the board was notified of this failure by plaintiff surety. At a meeting of defendant board held in January, 1897, interested parties appeared before the members, stated the facts, and protested against the payment to Carroll of the amount due on an estimate theretofore made. The plaintiff surety, by its agent, took part in these proceedings, and, after showing that Carroll was in default in his payments for labor and material, objected to the payment of the amount due, unless it should be paid to laborers or materialmen. The board disregarded the objections, and thereafter paid an order upon the county given by Carroll to one of his general creditors for the sum of $1,500. It paid no part of the 15 per cent, which was to be withheld. Carroll abandoned his contract, and the building was completed by another party;

The plaintiff paid and satisfied all legal claims for which it was bound on its bond, and then brought this action to recover the amount paid out by defendant board after notice of Carroll’s default, and also to have ascertained the. balance due the latter on his contract, and to recover that sum, also, of the board. When plaintiff rested, the trial court dismissed the action in so far as it was brought to recover the amount paid out on Carroll’s order. It then proceeded to ascertain the sum due to the latter, but these matters subsequent to the dismissal are of no importance here. The appeal is from an order denying plaintiff’s motion for a new trial of all the issues, except as to those matters last mentioned, which' concerned an ascertainment of the sum due Carroll.

It is admitted that under the terms of the bond it was the duty of Carroll to pay all just claims for work and labor performed and *96material furnished in and about the performance of his contract as they became due; and the question for determination is whether the defendant board possessed the right, or owed the duty, after notice of Carroll’s default, to withhold payment of the sum due on the estimate, and to see that the money was applied in payment of the claims, thus protecting the surety from the loss which occurred by reason of the refusal on the part of the board either to withhold the money due on this estimate, or to pay it out on account of labor and material. Prior to the enactment of Laws 1895, c. 351, we had occasion to consider questions growing out of a charter provision which empowered a municipality to require a bond from a contractor of the same general import of the one now before us, and containing, as required by the charter and by the present statute, a condition that the contractor should pay for all labor done and material furnished as the claims became due, and it was there said that the bond possessed a double character: First, it secured to the municipality the completion of the work; and, second, it secured and protected all laborers and materialmen. Under that charter provision an action to enforce the rights of these men had to be brought in the name of the city, and to that extent and for that purpose it occupied the position of a trustee.

In respect to the party in whose name an action is to be commenced, chapter 351 differs from the charter provision, for in section 1 it is expressly provided that every interested party is to institute the action in his own name. The municipality is not a trustee for the purpose of enforcing a liability accruing to other parties through the delinquency of the contractor, for by express provision this right rests with the injured party. Nor is there any provision in chapter 351 which authorizes the municipality to interfere as between the latter and the contractor. The parties for whose benefit and protection the obligation is entered into are as independent of each other, under this law, as if separate bonds had been required and had been given. The board had agreed with the contractor, and it was its duty, to pay 85 per cent, of the estimates each month; and this agreement the contractor could enforce. In complying with the terms of the written contract, the county was fully protected by the bond, for the laborers and materialmen could obtain *97no lien rights as against it. If liens could have been obtained against this public property, it is quite clear, notwithstanding the bond, that the board would have had the right to protect the premises by refusing to pay upon the estimates .unless the laborers and materialmen were paid, and, having this right, it would seem to follow that a duty would arise towards this plaintiff as surety upon the bond. But such is not the case now under consideration, and, while it is the law that a creditor of an obligee upon a bond must deal fairly with a surety, he cannot be held to have dealt unfairly if he has simply complied with the terms of his contract, and has been powerless to do otherwise. The defendant board had no authority under the statute to enforce the contractor’s duty towards the laborers and materialmen by withholding payment on the estimates, and consequently it neglected no duty it owed to plaintiff surety. The practical operation of a decision in accordance with plaintiff’s contention would be to cast the burden upon the obligees in the bond, instead of upon the obligors.

Order affirmed.